The Bikou Dam is an embankment dam on the Bailong River just upstream of Bikou in Wen County, Gansu Province, China. Construction on the dam began in 1969, the generators were commissioned in 1976 and the dam was complete in 1977. The 101 m (331 ft) tall earth-core rock-fill dam creates a reservoir with a 521,000,000 m3 (422,382 acre⋅ft) capacity. The dam supports a 300 MW power station.[1][2][3]

Bikou Dam
Location of Bikou Dam in China
CountryChina
LocationBikou
Coordinates32°45′37″N 105°13′27″E
StatusOperational
Construction began1969
Opening date1977
Dam and spillways
Type of damEmbankment, earth-core rock-fill
ImpoundsBailong River
Height101 m (331 ft)
Length297 m (974 ft)
Width (crest)8 m (26 ft)
Dam volume4,241,000 m3 (5,547,019 cu yd)
Spillway capacity2,310 m3/s (81,577 cu ft/s)
Reservoir
Total capacity521,000,000 m3 (422,382 acre⋅ft)
Catchment area26,000 km2 (10,039 sq mi)
Power Station
Commission date1976
Hydraulic head86.2 m (283 ft) (max)
Turbines3 x 100 MW
Installed capacity300 MW
Annual generation1,463 GWh

See also

References

  1. "Bi Hydropower Station" (in Chinese). ChinaBaike. Archived from the original on 2 October 2011. Retrieved 29 August 2011.
  2. "Bi Hydropower Station" (in Chinese). ChinaWater. Archived from the original on 12 May 2014. Retrieved 29 August 2011.
  3. "Bikou Hydropower Station". Northwest Hydro Consulting Engineers. Archived from the original on 31 March 2012. Retrieved 29 August 2011.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.