ONGC Tripura Power Company

ONGC Tripura Power Company (OTPC) also known as Palatana Power Plant, is a thermal power plant station in Palatana, Udaipur in the Gomoti district of the northeastern Indian state of Tripura. It is ONGC's first power plant in India & also known as the biggest Plant in Northeast India[1]

Palatana Power Plant
Official nameONGC Tripura Power Company Limited (OTPC)
CountryIndia
LocationPalatana, Udaipur, Tripura
Coordinates22°29′59″N 91°26′22″E
Construction beganOctober 2005 (2005-10)
Commission dateJune 2013 (2013-06)
Owner(s)ONGC-Govt. of Tripura
Power generation
Units operational1 × 363.3 MW (as of 16 January 2014)
Units planned726.6 MW
Units under const.1 × 363.3 MW
Nameplate capacity
  • 726.6 MW
External links
Websitewww.otpcindia.in

Capacity

726.6 MW Combined Cycle Gas Turbine (CCGT) power plant at Palatana, Tripura, based on ONGC's domestic gas supply. The project is in advanced stage of implementation. EPC contract of about Rs. 2200 crores has already been awarded to BHEL on 11 August 2008. The Generation Project is being domiciled in ONGC Tripura Power Company Ltd. ("OTPC" or "the Company"), a Special Purpose Vehicle promoted by ONGC, IL&FS Limited and Government of Tripura (GoT).

StageUnit numberCapacity (MW)Date of commissioning
1st1363.32013 January
1st2363.32014 November [2]

Transmission project

A 400 kV D/C Transmission system connecting Palatana (generation project site) in Tripura to Bongaigaon in Assam over a distance of around 650 km for the evacuation of power from the generation project.

The development and operation of the transmission system would be undertaken by North-East Transmission Company Limited (NETCL) a joint venture of OTPC, Power Grid Corporation of India Ltd (PGCIL) and the North Eastern Region beneficiary states. OTPC has been granted in-principle approval for Mega Power Project (MPP) status by GoI on 27 July 2006 for the Project. The company is applying to MoP, GoI for final approval of MPP status and the same is expected to be obtained shortly. For evacuating Power from the gas based 726.6 MW power Project Generators, a trunk transmission line is being developed by another Special Purpose Vehicle (SPV), jointly promoted by Power Grid Corporation Ltd., OTPC and the North Eastern Region (NER) states. Inter-state and intrastate sub-transmission system and the distribution system within NER states shall be developed by Power Grid Corporation as the Central Transmission Utility (CTU) The Transmission Project was initially envisaged to be domiciled in a separate SPV, North-East Power Transmission Company Limited ("NEPTC") and developed through a BOOT operator. However given the criticality of timely completion of the Transmission System to the operations of the Generation Plant, a decision was taken to develop the transmission system as a component of the composite Project within OTPC. Subsequently, the process of merging NEPTC with OTPC was initiated; The petition for amalgamation of NEPTC with OTPC was approved by the Hon'ble Guwahati High Court in Sept 2007. Subsequently, in late 2007, in consultation with the Ministry of Power (MoP), it was decided that the integrated project be developed as a regional project. The power allocation from the project was revised and about 640 MW was allocated to the NER beneficiary states and the balance 100 MW was to be retained by OTPC for merchant/short-term sale (based on assumed capacity of 740 MW). Pursuant to this development, the Transmission project was again carved out for development through a separate SPV. Accordingly, the Transmission JV was again incorporate as "North East Transmission Company Ltd"(NETC). The transmission project is progressing smoothly with the process of award of transmission tower construction packages for completion in tandem with the commissioning of the Generation Project.[3]

Gas reserves

However, these natural gas reserves are yet to be commercially developed due to low industrial demand in the North-Eastern region. The complexities of logistics and attendant costs limit the economic viability of transportation of gas to other parts of the country where gas is in deficit. In order to optimally utilize the gas available in Tripura, ONGC proposes to initially develop a 726.6 MW Combined Cycle Gas Turbine (CCGT) thermal power plant ("the Project") close to its gas fields in the state of Tripura and supply power to the deficit areas of North Eastern States of India.[4]

Allocation of power

660 km long transmission line from the plant to Burnihat in Meghalaya through Silchar in Assam was completed by which power from the first unit could be catered to other states of the north-east. But the work for the 400 kV double circuit high tension line up to Bongaigaon from Burnihat is pending due to forest clearance.[5] The Following are the distribution of electricity to the different Northeastern States of India from the OTPC.

BeneficiaryPower(MW)
Arunachal Pradesh22 MW
Assam240 MW
Manipur42 MW
Meghalaya79 MW
Mizoram22 MW
Nagaland27 MW
Tripura196 MW
Total628 MW

OTPC will be selling the remaining 98 MW electricity.

References

  1. "ONGC Tripura Power Plant". Power Technology. 15 June 2011. Retrieved 27 February 2015.
  2. "BHEL commissions second gas-based power plant in Tripura - Economic Times". Articles.economictimes.indiatimes.com. Retrieved 27 February 2015.
  3. Syed Sajjad Ali (30 December 2013). "Palatana power plant to restart". The Hindu. Retrieved 27 February 2015.
  4. "ONGC Tripura Power Project". Otpcindia.in. Retrieved 25 October 2019.
  5. "ONGC's 2nd thermal unit at Palatana to be operational by June - Economic Times". Articles.economictimes.indiatimes.com. Retrieved 27 February 2015.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.