Upper Salmon Hydroelectric Development
The Upper Salmon Hydro Development utilizes a portion of the residual head between Meelpaeg Lake Reservoir and Round Pond within the watershed of the Bay d'Espoir Hydroelectric Development in Newfoundland and Labrador. The plant operates at a normal supply level of 241 m under a net head of 51 metres. The average rated flow of 189.5 m3/s is used to generate 84 megawatts (MW) of electrical power with an average annual production of 541 GWh. The unit, which is equipped with a Francis turbine, was first synchronized on January 19, 1983.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.