Alpha Wind Casimcea Wind Farm

The Wind Farm Casimcea is an under construction wind power project in Tulcea County, Romania. It will consist of an individual wind farm with 77 individual wind turbines with a nominal output of around 2,3-3  MW which will deliver up to 688 000 000 kWh of power, enough to power over 445,000 homes, with a capital investment required of approximately €300 million.[1]

Wind Farm Casimcea
CountryRomania
LocationCasimcea
StatusUnder construction
Commission date2012 (100 MW), 2013 (100 MW), 2014 (80 MW)
Construction cost€300 million
Owner(s)Alpha Wind
CAS Regenerabile
Power generation
Units operational77 x 2,3-3 MW
Nameplate capacity280 MW

References

  1. "Parc eolian de 200 MW la Casimcea" (in Romanian). green-report.ro. 2010-07-30. Archived from the original on 2010-08-02. Retrieved 2010-12-17.


This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.