Alpha Wind Casimcea Wind Farm
The Wind Farm Casimcea is an under construction wind power project in Tulcea County, Romania. It will consist of an individual wind farm with 77 individual wind turbines with a nominal output of around 2,3-3 MW which will deliver up to 688 000 000 kWh of power, enough to power over 445,000 homes, with a capital investment required of approximately €300 million.[1]
Wind Farm Casimcea | |
---|---|
Country | Romania |
Location | Casimcea |
Status | Under construction |
Commission date | 2012 (100 MW), 2013 (100 MW), 2014 (80 MW) |
Construction cost | €300 million |
Owner(s) | Alpha Wind CAS Regenerabile |
Power generation | |
Units operational | 77 x 2,3-3 MW |
Nameplate capacity | 280 MW |