Bheri Babai Diversion Multipurpose Project
Bheri Babai Diversion Multipurpose Project (BBDMP) is a multi-basin irrigation cum hydropower project lying in Banke and Bardiya District of western Nepal. The water is diverted from the Bheri River and discharged to Babai River. The project has a command area of 51,000 hectares in Banke and Bardiya districts. The elevation difference between the intake and irrigation area provided an opportunity to install 46.73 MW electricity. The project has a tunnel 12.2 kilometers long that was constructed using a tunnel boring machine (TBM) for the first time in Nepal. The project is owned by the Ministry of Energy, Water Resources and Irrigation. The project cost is NPR 29,97,000,0000.[1]
Bheri Babai Diversion Multipurpose Project | |
---|---|
Country | Nepal |
Location | Banke district and Bardiya District |
Purpose | Power, Irrigation |
Status | Under construction |
Construction began | 2004 |
Opening date | 2023 |
Owner(s) | Ministry of Energy, Water Resource and Energy |
Dam and spillways | |
Type of dam | Barrage type |
Impounds | Bheri River |
Height | 13 m (43 ft) |
Length | 6 x 15.30 m |
Commission date | 2023 |
Type | RoR |
Hydraulic head | 121.5 m (399 ft) |
Turbines | 3 Nos Francis-type |
Installed capacity | 46.73 MW |
As of 2020, 40% of the construction work is completed.
Project description
The headworks of the project is located in Chhote village of Lekhpharsa VDC on the right bank and Gothiyari village of Ramghat VDC on the left bank of the Bheri River. A diversion barrage across the Bheri will divert the flow to six intake orifices on the left bank of river. The flow is then conveyed to a three-bayed settling basin followed by a 12 km long headrace tunnel and 773 m long penstock pipe. A power station will be located on the right bank of the Babai River. The gross head of the project is 151 m while the design discharge is 40 m3/s.[1]
Contractors
- Tunnel: China Overseas Engineering Group Company (COVEC) and Robbins provided the TBM. The component was constructed ahead of schedule.[2]
- Headworks and Powerhouse: Raman-Wangden JV[3]
- Irrigation Canals: Not declared
See also
External links
References
- "About Project :: Bheri Babai Diversion Multipurpose Project (BBDMP)".
- "Bheri-Babai multi-purpose project to be completed before deadline". Retrieved 2020-06-29.
- Upadhyaya, Nagendra. "Bheri-Babai Diversion Multipurpose Project completes 40% work". My Republica. Retrieved 2020-06-29.