MKS 180 frigate
MKS 180 (Mehrzweckkampfschiff 180) is the working title for a planned frigate class intended to replace the Brandenburg class frigates for the German Navy. The ships are to be the largest surface warships to join the Navy since World War II. The first ship is planned to be commissioned by 2027.
Class overview | |
---|---|
Builders: | Damen Group/Blohm + Voss/Lürssen/German Naval Yards |
Operators: | German Navy |
Preceded by: | Baden-Württemberg-class frigate |
Cost: | |
In service: | 2028 |
In commission: | 2027 |
Planned: | 4+2 |
General characteristics (Note that the final design may differ) | |
Type: | Frigate |
Displacement: | up to 10,000 tonnes |
Length: | 160 m (524 ft 11 in) |
Ice class: | 1C/E1 |
Speed: | > 26 kn (48 km/h; 30 mph) maximum sustainable speed or 11.5 kn (21.3 km/h; 13.2 mph) with electric propulsion |
Range: | 4,000 nmi (7,400 km; 4,600 mi) at 18 kn (33 km/h; 21 mph) speed |
Endurance: | 21 days |
Boats & landing craft carried: | At least two 10 m class RHIB (Rigid-Hull Inflatable Boat), additional ones depending on mission |
Capacity: | Accommodation for 80 additional crew, e.g. special forces or signals intelligence specialists |
Complement: | Standard complement: 114 |
Sensors and processing systems: |
1 x Hensoldt TRS-4D multi-function surveillance radar 1 x Thales X-band APAR Block 2 multi-function fireradar 1 x active/passive low frequency variable depth towed sonar (if the ASW module is fitted) 1 x Mirador MK2 electro-optical tracking and observation system |
Electronic warfare & decoys: | Rohde & Schwarz KORA communications and radar ESM |
Armament: |
1 x Otobreda 127/64 naval gun with Vulcano guided ammunition 8 x NSM anti-ship and land attack missiles 16 x cells Mk 41 VLS for up to 64 ESSM Block 2 medium-range air defence missiles 2 x RIM-116 RAM CIWS launchers 27 mm autocannons 12,7 mm heavy machine guns Water guns and long range acoustic device |
Aircraft carried: | 1 x NH90 Sea Tiger maritime helicopter + UAV (unmanned aerial vehicle) or 2 x helicopters |
Aviation facilities: | Aircraft hangar for a single helicopter and UAV or an operable and parked helicopter |
Notes: | Designed to be continuously deployed with minimal maintenance for up to two years and operate for 5000 hours per year |
The ships are likely to enter service as the F126 class, continuing German Navy nomenclature.
Capabilities
The class is to be mission modular and is capable of accommodating so-called mission modules which include devices, space, sensors and weaponry necessary to carry out a given task optimally. If not in use, the modules can be maintained and replaced separate from the ship and also be exchanged between different ships in the class.
The ships are planned to replace the Brandenburg class in their anti-submarine warfare role if fitted with a modular towed array sonar (the ASW module).
Similar to the Baden-Württemberg class however, they will also be able to stay at sea for up to two years[1] without requiring maintenance at port, with crews rotating to and from the deployed ship every four months. This capability is expected to allow for a more efficient use of hulls by reducing the time spent during transfer from Germany to conflict zones such as the sea off the Horn of Africa where German ships repeatedly took part in counter-piracy missions such as Operation Atalanta, patrolling large areas for a long time. In this case, the "detention module" enables the crew to detain suspects and if need be quarantine them in a purpose-built medical facility.
Other intended uses are the enforcement of embargoes, escorting merchant shipping or commanding maritime task forces.[2] In 2015, modules for mine countermeasures (MCM) and a diving chamber were planned as well.[1]
Project history
First studies for a class of future surface ships were initiated in 2009. At the time, the goal was to develop a replacement for the 143A Gepard class fast attack craft. In reference to the five K130 class corvettes which were set to replace the older 143 Albatros class,[3] the project was termed MÜKE (Mittlere Überwasserkampfeinheit) or K131. Eight ships were planned to join the navy by the early 2020s and then be available to the 2050s.
The ships were to be mission modular. The Navy, increasingly tasked with conducting long overseas deployments with an aging fleet of ships influenced by cold war requirements, wished to obtain flexible ships that could be rapidly modified depending on need. This design driver, also influencing the F125 Baden-Württemberg class frigates at the time, caused the projected design to increase in displacement and complement compared to a typical corvette. By early 2011, the project was therefore expected to result in a "Multi-Role Combat Ship" (Mehrzweckkampfschiff). On March 25, 2013 the detailed requirements were formally decided on.[4]
During the following analysis phase, three designs were suggested, one fulfilling all requirements and two other less expensive ones fulfilling them partially. On June 8, 2015 the fully compliant design was selected.[1] By 2015 the number of ships had been cut to four with the first hull entering service by 2023 at a planned total cost of around 4 billion Euros and two more ships in a potential second batch.[5] The MKS 180 project would now also replace the aging F123 Brandenburg class frigates specialized on conducting anti-submarine warfare (ASW).[3]
The 2015 tender was open for bids from European companies, with Minister of Defence Ursula von der Leyen deciding not to prevent foreign bidders from participating under national security reasons. BAE Systems and German Naval Yards, Damen Group and Blohm + Voss as well as Thyssenkrupp Marine Systems and Lürssen were among the bidding teams.[6] In mid 2017, BAE Systems, offering a ship based on the Type 26, withdrew from the tender and in March 2018 the German government excluded Thyssenkrupp and Lürssen. Thyssenkrupp Marine Systems then partnered as a subcontractor to German Naval Yards, while Lürssen effectively became a partner to Damen, having acquired Blohm + Voss in 2016.[7]
In January 2020 after a five year long bidding process the Dutch Damen Group won the tender, although the ships will be constructed at the Blohm + Voss shipyard in Hamburg, Germany[8] and at the Peene-shipyard in Wolgast, Germany, both owned by Lürssen Group.[9] German Naval Yards protested the award, delaying the required legally binding contract signature. However, the company withdrew its protest when it and Lürssen announced they would pool their naval shipbuilding in a joint venture[10] and that the Kiel shipyard would participate in construction.[11]
The contract was signed on June 17, 2020.[12] In June 2020 the German parliaments budgetary committee officially cleared 6 billion Euros for the first four ships and two options with the first ship planned to be commissioned by 2027.[13]
The contract awarded to Damen covers the ships, training facilities as well as two ASW and two detention modules and amounts to 5,48 billion Euros while weapons are contracted separately.[14] Initial operating capability for the ships - to be based in Wilhelmshaven - is expected in 2028.
Thales at its facilities in the Netherlands and Germany will provide radar, IT and fire control systems,[11] in particular the Tacticos combat management system and the AWWS (above water warfare system) fire control solution.[15] In November 2020, the provider of the underwater warfare suite had yet to be decided.
Controversy over contract award
Daniel Günther, Minister President of the state of Schleswig-Holstein where Kiel is located, complained[16] in public over the decision to engage in a European tender, considering German know-how and jobs to be threatened by the governments decision. He reiterated that the construction of surface warfare ships ought to be listed as a "key technology" (Schlüsseltechnologie) which would formalise the governments ability (but not obligation) to exclude tenders on surface ships from EU competition law. According to Schleswig-Holsteins Minister of the Economy, Bernd Buchholz (FDP), this is a common practise in other European countries where government can even directly own stakes in national shipyards. He especially criticized that knowledge-intensive activities such as research and development would be occurring in the Netherlands.[17]
The union of metalworkers (IG Metall) and labour councils in shipyards and maritime subcontractors also criticized the decision, considering 15.000 jobs to be threatened[18] in a call on the government to protect shipyards, jobs and engage with industry to bring about a "restructurization" of shipbuilding in Germany.
On February 12, 2020, the cabinet decided to include the construction of surface ships among key technologies.[19] The intention to do so had already been formalized during negotiations between the governing parties SPD and CDU/CSU in 2018.[20] This has no impact on the MKS 180 tender, which had already been conducted Europe-wide.
References
- Braun, Rudolf. "MEHRZWECKKAMPFSCHIFF KLASSE 180 - Realisierung kann beginnen" (PDF). Marineforum. 7/8-2015: 20–24.
- "Erklärstück-Update: Das Mehrzweckkampfschiff 180". www.bundeswehr.de (in German). Retrieved 2020-07-28.
- Gädechens, Ingo (June 7, 2015). "Gädechens begrüßt die Auswahlentscheidung zum Mehrzweckkampfschiff MKS 180". Archived from the original on August 13, 2015. Retrieved June 28, 2020.
- http://www.dmkn.de/wp-content/uploads/2013/11/Seiten-aus-MF-13-11-2-MKS.pdf
- "ZEIT ONLINE | Lesen Sie zeit.de mit Werbung oder imPUR-Abo. Sie haben die Wahl". www.zeit.de.
- "Rund eine halbe Milliarde Euro Mehrkosten für vier MKS 180 -..." bundeswehr-journal. 2017-04-26. Retrieved 2020-07-28.
- Hanuschke, Peter. "Kieler Allianz fordert Blohm+Voss heraus". WESER-KURIER (in German). Retrieved 2020-07-28.
- "Marine: Niederländische Damen-Werft erhält Zuschlag für Mehrzweckkampfschiff". www.handelsblatt.com.
- NDR. "Vergabestreit um Marine-Großauftrag". www.ndr.de (in German). Retrieved 2020-07-28.
- Hanuschke, Peter. "Marineschiffbau: Lürssen und German Naval Yards kooperieren". WESER-KURIER (in German). Retrieved 2020-07-28.
- "Dutch leading role for German frigate project MKS-180". www.damen.com. Retrieved 2020-07-28.
- "Damen leading role for German Navy's MKS 180 frigate project". June 19, 2020.
- "Bundestag awards €6 billion for German Navy's four MKS 180 ships". June 18, 2020.
- "Bundestags-Haushaltsausschuss billigt neue Kriegsschiffe MKS180 – Augen geradeaus!". augengeradeaus.net. Retrieved 2020-07-28.
- "Thales to Supply Tacticos and AWWS for German Navy's Future MKS 180 Frigates". Naval News. 2020-11-18. Retrieved 2020-11-20.
- NDR. "Gescheiterter Marine-Auftrag: Günther kritisiert Bund". www.ndr.de (in German). Retrieved 2020-07-28.
- "Günther und Buchholz fordern vom Bund klare Perspektive für den Marine-Schiffbau".
- "Zukunft für den Marineschiffbau in Deutschland: Forderungen an Bundesregierung und Unternehmen" (PDF).
- "Kabinett beschließt wie erwartet: Marineschiffbau wird Schlüsseltechnologie – Augen geradeaus!". augengeradeaus.net. Retrieved 2020-07-28.
- "Koalitionsvertrag zwischen CDU, CSU und SPD 19. Legislaturperiode" (PDF). p. 58.