Siti I Hydroelectric Power Station

Siti I Hydroelectric Power Station, commonly referred to as Siti Power Station, is a 5.0 megawatts (6,700 hp) mini hydropower station in Uganda.[2]

Siti I Hydroelectric Power Station
CountryUganda
LocationSiti, Bukwo District
Coordinates01°15′00″N 34°38′13″E
StatusOperational
Commission dateMay 2017[1]
Power generation
Units planned2 x 2.5 MW
Nameplate capacity5.0 megawatts (6,700 hp)

Location

The power station is located across River Siti, in Siti Parish, Bukwo District, in the northern part of Uganda's Eastern Region, near the International border with the Republic of Kenya. This location, lies on the northeastern slopes of Mount Elgon, within Mount Elgon National Park, at an altitude of about 2,000 metres (6,600 ft), above sea level. It is located in proximity to its sister power station, Siti II Hydroelectric Power Station[3][4]

Overview

The power station is a run of river, mini hydropower installation, with capacity of 5 Megawatts. The development was developed at the same time with the 16.5 megawatts (22,100 hp) Siti II Hydroelectric Power Station. Both are owned by the same developer.[4] The impact assessment studies were done and presented prior to construction. One private developer, Elgon Hydro Siti Private, has applied for the development rights to the project.[5] The 21.5 Megawatt power complex comprising Siti I and Siti II is the largest power generating installation in northeastern Uganda. The power generated from this power generating complex will supply the local communities in Bukwo District and the balance will be integrated into the national power grid.

Construction timeline

In October 2014, the Electricity Regulatory Authority (ERA), licensed nine new renewable energy projects, including Siti I Hydroelectric Power Station. The power complex consists of two run of river generation units; Siti I with capacity of 5 Megawatts and Siti II, with capacity of 16.5 Megawatts. Construction started in March 2015,[6] and commercial operations began in May 2017.[1]

See also

References

  1. Ingram, Elizabeth (4 May 2017). "Operations begin at 5-MW Siti I small hydropower plant in Uganda". Hydroworld.com. Retrieved 15 August 2017.
  2. Deep Earth (31 October 2013). "Power Watchdog Assessing 21.5MW Siti Proposed Plant". DeepEarthInt.com. Retrieved 12 July 2014.
  3. Frontier (August 2016). "Siti 2 Hydro Power Project". Frontier.dk (Fronter). Retrieved 15 August 2017.
  4. Sources (5 May 2017). "Frontier Energy: Uganda`s Siti I hydropower plant starts operations". SyndiGate Media Inc. Quoting Middle East & North African Newspapers. Retrieved 15 August 2017.
  5. "Elgon Hydro Siti (Private) Public Hearing For A 21.5MW Generation License Concluded". Electricity Regulatory Authority - Uganda (ERA). 28 October 2013. Retrieved 12 July 2014.
  6. Sanya, Samuel (22 October 2014). "ERA Licenses 9 Renewable Energy Projects". New Vision. Kampala. Retrieved 23 October 2014.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.