Stourport power stations

Stourport power stations were two electricity generating stations that supplied electricity to Stourport-on-Severn Worcestershire and to the wider West Midlands area from 1927 to 1984. The two stations, A (1927–78) and B (1950–84), were collocated on a joint site adjacent to the River Severn south of Stourport-on-Severn.

Stourport power stations
CountryUnited Kingdom
LocationStourport, Worcestershire
Coordinates52°20′01″N 02°16′28″W
StatusDecommissioned and demolished
Construction began1926, 1949
Commission date1927, 1950
Decommission date1978, 1984
Owner(s)Shropshire, Worcestershire and Staffordshire Electric Power Company
(1926–1948)
British Electricity Authority
(1948–1955)
Central Electricity Authority
(1955–1957)
Central Electricity Generating Board
(1958–1984)
Operator(s)As owner
Thermal power station
Primary fuelCoal
Turbine technologySteam turbines
ChimneysA station 4, B station 2
Cooling towersNone
Cooling sourceRiver water
Power generation
Units operational(See text)
Make and modelBritish Thomson-Houston 35 MW, English Electric 60 MW
Nameplate capacity181 MW, 120 MW
Annual net output1035 GWh (1961)

Background

The Shropshire, Worcestershire and Staffordshire Electric Power Company had been founded in 1903 as the Shropshire and Worcestershire Electric Power Company. The company changed its name and obtained several Local Acts of Parliament to generate and supply electricity to areas of Shropshire and Worcestershire in the West Midlands.[1] These Acts included the Shropshire, Worcestershire and Staffordshire Electric Power Act 1905 (5 Edw. 7 c. clx); 1914 (4 & 5 Geo. 5 c. lxxxiv); 1918 (8 & 9 Geo. 5 c. xliii); 1919 (9 & 10 Geo. 5 c. cxxi).[2] The Company built and operated power stations at Dudley, Kidderminster and Smethwick.[1]

In 1916 the Shropshire, Worcestershire and Staffordshire Electric Power Company and Birmingham Corporation developed a scheme to build two large power stations to meet their combined needs for electricity.[3] The new power stations were to be at Nechells with two 15 MW generating sets and at Stourport with three 15 MW generating sets. However, the scheme was not taken forward on financial grounds.[3]

Legal powers were sought to build a power station at Stourport.[4] These powers were obtained under the provisions of the Shropshire, Worcestershire and Staffordshire Electric Power Act 1926 (16 & 17 Geo. 5 c. ciii).[5] The Company built the A power station on a riverside site (52°20'01"N 2°16'28"W) south of the town. The power station was inaugurated by the Prime Minister Stanley Baldwin on 2 June 1927.[6]

Stourport and electricity policy

Under the terms of the Electricity (Supply) Act 1926 the Central Electricity Board (CEB) was established.[7] The CEB identified high efficiency ‘selected’ power stations that would supply electricity most efficient and effectively; Stourport became a 'selected' station. The CEB also constructed the national grid (1927–33) to connect power stations within a region.[7][3]

In 1938 the CEB directed the company to install an additional 30 MW of plant at Stourport including boilers in time for commercial operation in 1940.[8]

In 1938 the Company obtained a Local Act of Parliament: the Shropshire, Worcestershire and Staffordshire Electric Power (Consolidation) Act 1938 (1 & 2 Geo. 6 c. lviii). This Act consolidated into one volume the numerous Acts that the Company operated under for many years.[9]

In 1939 the CEB permitted the Company close its older power stations at Smethwick and Hereford.[9] Power lines were installed from Stourport to the site of the Smethwick station to enable Smethwick to be supplied with electricity from Stourport power station.[9]  

The British electricity supply industry was nationalised in 1948 under the provisions of the Electricity Act 1947 the Shropshire, Worcestershire and Staffordshire Electric Power Company undertaking was abolished, ownership of Stourport power station was vested in the British Electricity Authority, and subsequently the Central Electricity Authority and the Central Electricity Generating Board (CEGB).[7] At the same time the electricity distribution and sales responsibilities of the company were transferred to the Midlands Electricity Board (MEB).[7]

Stourport A

Stourport A power station was built in stages from 1926 to 1944, the latter under the direction of the CEB. It was initially known as Stourport power station and became Stourport A when the new station, Stourport B, was built in 1950.

Specification

The A station had a low pressure steam side and a high pressure side and comprised:[10]

  • Coal-fired boilers:
    • Low pressure
      • 4 × 50,000 lb/h (6.3 kg/s) Stirling boilers, 350 psi at 686 °F (24.1 bar at 363 °C)
      • 2 × 90,000 lb/h (11.33 kg/s) Stirling boilers, 350 psi at 686 °F (24.1 bar at 363 °C)
      • 2 × 100,000 lb/h (12.60 kg/s) Stirling boilers, 350 psi at 686 °F (24.1 bar at 363 °C)
    • High pressure
      • 8 × 160,000 lb/h (20.16 kg/s) Stirling boilers, 650 psi at 850° (44.83 bar at 454 °C)
  • Generating plant:[10]
    • Low pressure
    • High pressure
      • 1 × 35 MW British Thomson-Houston turbo-alternator
      • 3 × 30 MW English Electric turbo-alternators
    • House set
      • 1 × 750 kW DC British Thomson-Houston turbo-alternator
  • The main sets generated current at 33 kV and 11 kV.

Coal was delivered to the station by barge from the River Severn and by railway along a specially constructed branch from the Severn Valley Railway line to an extensive coal store north of the station buildings.[11][12] Cooling water for the condensers was drawn from the River Severn.[10]

Operational data

Operating details of the A station was as follows:[10]

Operation of Stourport A low pressure station
Year Maximum output capacity MW Running hours Electricity supplied, GWh Thermal efficiency, %
1954 54 3302 63.624 13.60
1955 54 3156 70.105 12.08
1956 54 2026 34.965 10.08
1957 54 1278 26.491 11.01
1958 54 194 2.452 5.63

The decline in use (the reduced running hours) in the mid-1950s is evident; the thermal efficiency is also low.

Operating details of the A station high pressure plant are as follows:[10][13][14][15]

Operation of Stourport A high pressure station
Year Maximum output capacity MW Running hours (or load factor %) Electricity supplied, GWh Thermal efficiency, %
1954 119 5999 347.732 22.71
1955 119 5931 377.883 22.99
1956 119 6301 380.990 22.27
1957 119 5197 273.089 21.76
1958 119 4976 306.457 20.97
High pressure and low pressure combined
1946 (45.8 %) 714.525 22.34
1961 173 (24.9 %) 376.918 20.54
1962 173 (19.8 %) 300.420 20.33
1963 173 (19.78 %) 299.798 19.80
1967 168 (26.9 %) 408.0 20.50
1972 119 (16.8 %) 175.833 18.52

In 1963 and 1972 the only operational turbo-alternator sets were the HP 1 × 35 MW and 3 × 30 MW.[13][14]

In November 1952 one man was killed and one seriously injured at Stourport power station when they fell 100 feet from a hoist inside a chimney.[16]

In 1959 experimental heat pumps were installed at Stourport and Meaford power stations to heat the administrative buildings.[7]

Stourport A power station closed on 30 October 1978 when its generating capacity had fallen to 57 MW.[17]

Stourport B

Stourport B power station was built by the British Electricity Authority and was commissioned in two stages from 1950–54.

Specification

The B station comprised the following plant:[10]

Two ‘Unit’ boilers:

  • 1 × Stirling, two drum, pulverised coal-fired boiler, evaporative capacity 525,000 lb/h (66.15 kg/s), steam conditions 1,275 psi at 975 °F (87.93 bar at 524 °C) (No. 1 LP unit).  The furnace of this boiler was a slag-tap type, the first use of this type in the UK.[7]
  • 1 × International Combustion, two drum, pulverised coal-fired boiler, evaporative capacity 515,000 lb/h (64.89 kg/s), steam conditions 1,550 psi at 1060 °F (106.9 bar at 571 °C) (No. 2 unit).

Generators:

  • 2 × 60 MW English Electric hydrogen cooled turbo-alternators. Three cylinder double-flow type.  No. 1 (LP unit) and No. 2 HP Unit. Both generated current at 11 kV. The No. 2 generator, commissioned in 1954, had the most advanced steam conditions of any turbine on the United Kingdom public supply system: 1500 psi at 1050 °F (103.4 bar at 566 °C) at the turbine stop valve.[7]

The voltage was stepped up to 33 kV and 66 kV.

Cooling water for the condensers was drawn from the river.[10]

Operational data

Operating details of the B station was as follows:[10][18]

Operation of Stourport B low pressure station
Year Maximum output capacity MW Running hours Electricity supplied, GWh Thermal efficiency, %
1954 56 7366 407.747 30.53
1955 56 8048 462.310 30.83
1956 56 5212 293.768 30.29
1957 56 7400 390.776 29.75
1958 56 5290 280.805 29.95
1960 56 80 % (load factor) 393.521 29.48

In 1959/60 Stourport B L.P. was one of the CEGB's 20 steam power stations with the highest thermal efficiency.[18]

The combined output from the low and high pressure plant is given below:[10][13][14][19][20]

Operation of Stourport B high pressure station
Year Maximum output capacity MW Running hours (or load factor %) Electricity supplied, GWh Thermal efficiency, %
1955 56 602 18.692 25.23
1956 56 5603 299.136 30.34
1957 56 4214 224.931 30.07
1958 56 6796 360.770 30.16
1960 56 (63 %) 308.381 29.87
High pressure and low pressure combined
1961 112 (67.1 %) 658.481 29.77
1962 112 (63.6 %) 624.329 29.39
1963 112 (66.87 %) 656.144 29.16
1967 112 (65.9 %) 648.35 28.92
1972 112 (38.4 %) 377.537 27.03
1979 112 (31.3 %) 307.558 26.80
1981 112 (40.1 %) 393.174 27.65
1982 112 (23.7 %) 232.076 27.20

In 1959/60 Stourport B H.P. was one of the CEGB's 20 steam power stations with the highest thermal efficiency.[18]

The decline in use (the load factor) in the 1970s is evident.


The overall output of the station (A & B) in GWh is shown on the graph:

Stourport B power station was closed in 1984 and was subsequently demolished.[11] The area is now a housing estate. One of the roads is named Power Station Road.

See also

References

  1. Electricity Commissioners (1925). Electricity Supply. London: HMSO. pp. 204–07, 478–83.
  2. "Local Acts of Parliament". legislation.uk. Retrieved 23 July 2020.
  3. Hannah, Leslie (1979). Electricity before Nationalisation. London: Macmillan. pp. 58, 105–121. ISBN 0333220862.
  4. Tucker, D. G. (1977). "Electricity gnerating stations for public supply in the West Midlands 1888-1977" (PDF). Retrieved 23 July 2020.
  5. "Local Acts of Parliament 1926". legislation.uk. Retrieved 23 July 2020.
  6. "New power station at Stourport". The Times. 3 June 1927. p. 8.
  7. Electricity Council (1987). Electricity Supply in the United Kingdom: a Chronology. London: Electricity Council. pp. 45, 60, 64, 69, 70, 73, 78. ISBN 085188105X.
  8. "Shropshire, Worcestershire and Staffordshire Electric Power Company". The Times. 13 April 1938. p. 24.
  9. "Shropshire, Worcestershire and Staffordshire Electric Power Company". The Times. 25 April 1939. p. 22.
  10. Garrett, Frederick C. (ed) (1959). Garcke's Manual of Electricity Supply vol. 56. London: Electrical Press. pp. A-98, A-135.CS1 maint: extra text: authors list (link)
  11. "Stourport power station". Severn Valley Railway. 23 August 2017. Retrieved 23 July 2020.
  12. "Stourport power station 1947". Britain from above. Retrieved 23 July 2020.
  13. CEGB Annual Report and Accounts 1961, 1962, 1963 London: CEGB
  14. CEGB (1972). CEGB Statistical Yearbook 1972. London: CEGB. p. 13.
  15. Electricity Commission, Generation of Electricity in Great Britain year ended 31st December 1946. London: HMSO, 1947.
  16. "Fatal fall inside Chimney". The Times. 18 November 1952. p. 3.
  17. Hansard, House of Commons, Written Answers, Coal-fired Power Stations, 16 January 1984
  18. CEGB, Annual Report and Accounts 1959/60, CEGB London
  19. CEGB (1979). CEGB Statistical Yearbook 1978-79. London: CEGB. p. 7. ISBN 0902543598.
  20. CEGB (1982). CEGB Statistical Yearbook 1981-82. London: CEGB. p. 7. ISBN 0902543695.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.