National Highways Development Project

The National Highways Development Project (NHDP) is a project to upgrade, rehabilitate and widen major highways in India to a higher standard. The project was started in 1998 under the leadership of Prime Minister, Atal Bihari Vajpayee. National Highways account for only about 2% of the total length of roads, but carry about 40% of the total traffic across the length and breadth of the country. This project is managed by the National Highways Authority of India (NHAI) under the Ministry of Road, Transport and Highways. The NHDP represents 49,260 km of roads and highways work and construction in order to boost economic development of the country. The government has planned to end the NHDP program in early 2018 and consume the ongoing projects under a larger Bharatmala project.

The Network of National Highways in India

Project Phases

The project is composed of the following phases:

  • Phase I: The Golden Quadrilateral (GQ; 5,846 km) connecting the four major cities of Delhi, Mumbai, Chennai and Kolkata. This project connecting four metro cities, is 5,846 km (3,633 mi). Total cost of the project is Rs.300 billion (US$6.8 billion), funded largely by the government’s special petroleum product tax revenues and government borrowing. In January 2012, India announced the four-lane GQ highway network as complete.[1][2]
  • Phase II: North-South and East-West corridors comprising national highways connecting four extreme points of the country. The North–South and East–West Corridor (NS-EW; 7,142 km) connecting Srinagar in the north to Kanyakumari in the south, including spur from Salem to Kanyakumari (Via Coimbatore and Kochi) and Silchar in the east to Porbandar in the west. Total length of the network is 7,142 km (4,438 mi). As of 31 October 2016, 90.99% of the project had been completed, 5.47% of the project work is under Implementation and 3.52% of the total length is left.[3][4] It also includes Port connectivity and other projects — 435 km (270 mi). The final completion date to 28 February 2009 at a cost of Rs.350 billion (US$8 billion), with funding similar to Phase I.
  • Phase III: The government on 12 April 2007 approved NHDP-III to upgrade 12,109 km (7,524 mi)of national highways on a Build, Operate and Transfer (BOT) basis, which takes into account high-density traffic, connectivity of state capitals via NHDP Phase I and II, and connectivity to centres of economic importance.
  • Phase IV: The government on 18 June 2008 approved widening 20,000 km (12,000 mi) of highway that were not part of Phase I, II, or III. Phase IV will convert existing single-lane highways into two lanes with paved shoulders.
  • Phase V: As road traffic increases over time, a number of four-lane highways will need to be upgraded/expanded to six lanes. On 5 October 2006 the government approved for upgrade of about 5,000 km (3,100 mi) of four-lane roads.
  • Phase VI: The government is working on constructing 1,000 km (620 mi) expressways that would connect major commercial and industrial townships. It has already identified 400 km (250 mi) of Vadodara (earlier Baroda)-Mumbai section that would connect to the existing Vadodara (earlier Baroda)-Ahmedabad section. The World Bank is studying this project. The project will be funded on BOT basis. The 334 km (208 mi) Expressway between ChennaiBangalore and 277 km (172 mi) Expressway between KolkataDhanbad has been identified and feasibility study and DPR contract has been awarded by NHAI.
  • Phase VII: This phase calls for improvements to city road networks by adding ring roads to enable easier connectivity with national highways to important cities. In addition, improvements will be made to stretches of national highways that require additional flyovers and bypasses given population and housing growth along the highways and increasing traffic. The government has planned to invest Rs. 16,680 Cr for this phase. The 19 km (12 mi) long Chennai PortMaduravoyal Elevated Expressway is being executed under this phase.
National Highways Development Project at a glance
NHDP PhaseParticularsLengthIndicative cost ₹ ( in cr)
NHDP-I & IIBalance work of GQ and EW-NS corridors13,000 km (8,100 mi)42,000
NHDP-III4-laning10,000 km (6,200 mi)55,000
NHDP-IV2-laning20,000 km (12,000 mi)25,000
NHDP-V6-laning of selected stretches5,000 km (3,100 mi)17,500
NHDP-VIDevelopment of expressways1,000 km (620 mi)15,000
NHDP-VIIRing Roads, Bypasses, Grade Separators, Service Roads etc.700 km (430 mi)15,000
Total45,000 km (28,000 mi)1,690,500 (Revised to 2,200,000)

Note: 1 crore= 10 million

Timeline of the National Highways Development Project
PriorityNHDP PhaseLength (km)StatusApprovalCompletion Target
1 Phase I5,846 km (3,633 mi)CompleteDecember 2000December 2006
2 Phase II7,300 km (4,500 mi)Award in progressDecember 2003December 2009
3 Phase III A4,000 km (2,500 mi)Already identifiedMarch 2005December 2009
4 Phase V6,500 km (4,000 mi)5700 km of GQ + 800 km to be identifiedNovember 2005December 2012
5 Phase III B6,000 km (3,700 mi)Already identifiedMarch 2006December 2012
6 Phase VII A700 km (430 mi)Ring roads to be identifiedDecember 2006December 2012
7 Phase IV A5,000 km (3,100 mi)To be identifiedDecember 2006December 2012
8 Phase VII BRing roads to be identifiedDecember 2007December 2013
9 Phase IV B5,000 km (3,100 mi)To be identifiedDecember 2007December 2013
10 Phase VI A400 km (250 mi)Already identifiedDecember 2007December 2014
11 Phase VII CRing roads to be identifiedDecember 2008December 2014
12 Phase IV C5,000 km (3,100 mi)To be identifiedDecember 2008December 2014
13 Phase VI B600 km (370 mi)To be identifiedDecember 2008December 2015
14 Phase IV D5,000 km (3,100 mi)To be identifiedDecember 2009December 2015

"Financing of the National Highway Development Programme" (PDF). Archived from the original (PDF) on 28 February 2007.

Status from NHAI website

National Highways Development Project is being implemented in all phases except phase VI at present. The present phases are improving more than 49,260 km of arterial routes of NH network to international standards. The project-wise details of NHDP all phases is below as of 31 March 2018:

NATIONAL HIGHWAY DEVELOPMENT PROJECT(NHDP)
Projects Total Length(Km.) Already 4/6 Laned(Km.) Under Implementation (Km.) Contracts Under Implementation (No.) Balance length for award(Km.)
NHDP GQ 5,846 5,846

(100.00%)

0 0 -
NS - EW

Ph. I & II

7,142 7,142 0 0
Port

Connectivity

435 379 56 6 -
NHDP Phase III 11,809 6,835 3,227 81 1,747
NHDP Phase IV 13,203 2,054 4,654 64 6,495
NHDP Phase V 6,500 2,359 761 22 3,380
NHDP Phase VI 1,000 - 165 8 835
NHDP Phase VII 700 22 19 1 659
NHDP Total 46,635 23,922 9,340 221 13,373
Others (Ph.-I, Ph.-II & Misc.) 1844 1614 230 11 -
SARDP -NE 110 105 5 1 -
Total by NHAI 48,589 25,641* 9,575 233 13,373
*Total 20,000 km was approved under NHDP Phase IV, out of which 14,799 km was assigned to NHAI and remaining Km with MoRTH.

Subsummation in Bharatmala project

National Highway Development Project will close by first half of 2018, with the launch of Bharatmala project.[5] 10,000 km of highway construction left under NHDP will be merged with Phase I of the Bharatmala.[5] Sagarmala and Setu Bharatam are also expected to fill in the void created by closure of NHDP project.

See also

Similar rail development
Similar roads development
Similar ports and river transport development
Similar air transport development
Highways in India
General

References

  1. "Govt declares Golden Quadrilateral complete". The Indian Express. 7 January 2012.
  2. "National Highways Development Project Map". National Highways Institute of India.
  3. Sood, Jyotika (18 April 2017). "NDA to kick off India's most ambitious roads programme ever". livemint.com/. Retrieved 25 June 2017.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.