CityLynx Gold Line

The CityLynx Gold Line is a streetcar line in Charlotte, North Carolina, United States, the first phase of which opened in 2015. The line is an extension of the Charlotte Area Transit System's Lynx rail system and is ultimately intended to connect the University Park area of west Charlotte with Eastland Community Transit Center in east Charlotte via Uptown Charlotte.[6] It is proposed to follow a primarily east-west path along Beatties Ford Road, Trade Street and Central Avenue, through central Charlotte. As conceived, it was projected to be 10 miles (16 km) long with 34 stops and be completed between Rosa Parks Place and Presbyterian Hospital by 2019 at a cost of $211 million. CATS estimated that the completed route would have an average daily ridership of between 14,200 and 16,700 passengers by 2030.[7]

CityLynx Gold Line
One of the Birney-replica streetcars temporarily providing Gold Line service until modern cars recently received enter service, seen at the CTC stop on Trade St.
Overview
Statustemporarily closed; replacement bus service
OwnerCharlotte Area Transit System
LocaleCharlotte, North Carolina
TerminiCTC/Arena (west)
Hawthorne & 5th (east)
Stations6[1] (+11 under contructon)
23 (planned)
Service
TypeStreetcar
SystemCharlotte Area Transit System
Operator(s)Charlotte Area Transit System
Daily ridership1,500[2]
History
OpenedJuly 14, 2015 (Phase 1)[1][3]
Early 2021 (Phase 2)[4]
Technical
Line length1.5 mi (2.4 km) (Phase 1)[1]
10 mi (16 km) (planned)
Track gauge4 ft 8 12 in (1,435 mm)
ElectrificationOverhead wire, 650 V DC (2015)[5]
Route map

future extension
Rosa Parks
Community Transit Ctr
Montana Drive
LaSalle Street
Russell Avenue
Booker Avenue &
Oaklawn Avenue
↑ future extension
↓ Phase 2
French Street
Johnson C. Smith University
Bruns
Wesley Heights
I-77 (Bill Lee Freeway)
Irwin
Johnson & Wales
Gateway Station
Mint Street
Tryon Street
CTC/Arena
↑ Phase 2
↓ Phase 1
Davidson Street
McDowell Street
I-277 (John Belk Freeway)
CPCC Central Campus
Elizabeth & Hawthorne
Hawthorne & 5th
↑ Phase 1
↓ Phase 2
Hawthorne & 8th
US 74 (
Independence
Expressway
)
Sunnyside Avenue
future extension
↑ Phase 2
↓ future extension
Hawthorne at Barnhardt
The Plaza
Veterans Park
Morningside Drive
Arnold Drive
Briar Creek Road
Eastway Crossing
Eastway Drive
Sheridan Drive
Darby Acres
Landsdale Drive &
Rosehaven Drive
Winterfield Place
Eastland Community
Transit Center

The initial 1.5-mile (2.4 km), six-stop segment (Phase 1)[1] between then Time Warner Cable Arena (now Spectrum Center) and Presbyterian Hospital opened for service on July 14, 2015.[3][8][9] A further 2.5-mile (4.0 km) segment (Phase 2) from the Charlotte Transportation Center/TWC Arena to French Street, and from Presbyterian Hospital to Hawthorne Lane, is under construction and set to open for service in early 2021.[10] The third and final phase between Hawthorne Lane and Eastland CTC, and from French Street to Rosa Parks CTC, has been planned, but lacks funding.

History

Initial plans

In June 2006 initial costs for the completion of the Center City Corridor streetcar line were stated at about $250 million.[7] The streetcars would serve as a replacement for both the No. 7 and No. 9 CATS bus routes currently serving Beatties Ford Road and Central Avenue, respectively.[7] With an estimated cost and ridership in place, the Metropolitan Transit Commission (MTC) voted on the priority for its construction in November 2006.

At its November meeting the MTC voted to prioritize the construction and completion of both the Blue Line Extension to UNC Charlotte and the Red Line commuter rail to Lake Norman over the construction and completion of the Central City streetcar.[11] At this time the MTC also determined that initial engineering studies for the corridor would commence in 2013 with a phased completion by 2023.[11] Although construction was not slated to commence until the mid-2010s, streetcar tracks for the line were installed as part of a streetscape project along the Elizabeth Avenue segment between CPCC and Presbyterian Hospital to be complete by 2009.[12]

Although identified as the number three priority by the MTC, by 2008 CATS began to determine means by which to speed up its construction and be operational by 2013.[13] To further expedite the proposed streetcar line, in May 2008, the Charlotte City Council approved $500,000 to study the corridor in terms of an updated cost estimate, economic benefits and the eligibility of the corridor for federal funding.[14] However, in order to complete the line by 2013, CATS stated that additional capital will be required due to other projects already budgeted and in progress.[14]

In the spring of 2010, the Federal Transit Administration awarded the project a $25 million grant. On September 19, 2011, U.S. Transportation Secretary Ray LaHood formally awarded Charlotte with the grant for a 1.5-mile (2.4 km) starter streetcar line from Time Warner Cable Arena to Presbyterian Hospital. Construction was started in December 2012, with plans to begin service in 2015. The line was expected to cost $37 million, with the city paying $12 million; however, the city did not state how it will pay for an estimated $1.5 million in operating costs.[15]

Construction and opening of Phase 1

In November 2012, the Charlotte city council awarded a $26.3 million contract for construction of the starter segment to a partnership between Balfour Beatty Rail and Blythe Development Company.[16] The groundbreaking for the initial 1.5 mile (2.41 kilometer) segment of the line took place on December 12, 2012 in front of Presbyterian Hospital, with Secretary of Transportation Ray LaHood, Mayor Foxx and other officials in attendance.[17] By May 2014, the initial segment was 45 percent completed.[18][19] While the line had originally been scheduled to open in March 2015, in January 2015 the opening date was moved to June due to construction errors on the part of the contractor, and was subsequently moved to July 2015.[8][3]

On July 14, 2015, the Phase I section of the Gold Line began service. The U.S. Secretary of Transportation and former mayor of Charlotte, Anthony Foxx, delivered the keynote speech. Foxx had been one of the primary backers of the streetcar project.[9]

Phase 2 construction and renaming of line

In early 2012, Mayor Anthony Foxx proposed a 2.5-mile (4.02 km), $119 m. extension to the planned Center City Corridor streetcar line, which would extend line to Johnson C. Smith University. The proposal was turned down by a majority of the city council; on June 30, Foxx vetoed a revised city budget by the council which would have eliminated the extension. On October 30, further discussion failed to reach any consensus on how best to pay for an extension. Options considered included: charging fares for the streetcar (the city had planned for the streetcar to be free), increasing the special property tax rate charged to property owners inside Interstate 277, soliciting donations from businesses and institutions along the line, such as Johnson & Wales University or using a portion of new property taxes created from development along the line. Other options to raise funds, which would have required approval from the state, included increasing the rental car tax, hotel/motel tax or prepared food and beverage tax, levying a special fee on parking spaces or lobbying for a higher vehicle registration fee.[20]

Many city council members stated they did not favor an increase in property taxes as a result of the streetcar extension. In an effort to end the continuing deadlock, on December 10 Foxx proposed two alternative budgets, the smaller of which would eliminate the streetcar extension;[21] however, on December 17 the city council voted to postpone all budget decisions until early 2013.[22] At a meeting in Raleigh on January 31, 2013, Pat McCrory, the newly elected Governor of North Carolina and former mayor of Charlotte, told Charlotte's city attorney and its deputy city manager Ron Carlee that state funding for the Blue Line Extension could be at risk if Charlotte persisted with plans to build an extension to the streetcar line.[23] On April 10, 2013, the streetcar extension was temporarily dropped from the budget, though Carlee hoped to have a separate streetcar plan ready to vote on by June 2013.[24]

After protracted debate, on May 13, 2013, Ron Carlee, the new Charlotte city manager, said the $126 million extension, renamed the CityLynx Gold Line, could be funded without a property tax increase if the city could receive a federal grant for half the estimated cost, possibly through the Federal Transit Administration's New Starts Program. The remaining $63 million could be covered with surplus funds from other city programs. City council members voted to send the proposal to the Metropolitan Transit Commission on May 22, and with their approval, take a vote on May 28.[25] On May 15, 2013, Bay Area Economics, an independent consultant hired by the city in 2009 to conduct a streetcar economic impact study, reported the proposed second phase could generate 1.1 million square feet of new development for the city by 2035, and nearly $2.4 million in new property taxes.[26] On May 28, the Charlotte city council voted 7-4 to build the Phase 2 extension, setting aside $63 million for the purpose; the line will run from Sunnyside Avenue to French Street.[27][18] On September 3, it was reported the Gold Line extension had been passed over for a federal TIGER (Transportation Investment Generating Economic Recovery) grant, intended to cover the remaining $63 million it would cost to build the line.[28] On November 13, the city announced it would apply to the Federal Transit Administration for permission to begin planning the line in detail.

On January 27, 2014, the Charlotte city council voted 8-3 to spend up to $12 million on engineering work for the extension. Carlee said the city would have to spend some of the $63 million it had allocated for the extension in May to demonstrate to the FTA that the project was viable.[29] On February 26, the FTA issued its approval for CATS to begin project development for the extension and to apply for the Federal Small Starts grant in September 2014.[30] On September 8, the Charlotte city council voted 7-4 to build the second phase and proceed with applying for the federal grant. As part of the extension project, the Hawthorne Lane bridge over Independence Boulevard would be replaced to handle the weight of the streetcars.[31]

On June 22, 2015, the Charlotte city council voted 7-4 to approve $7.7 million for further Phase 2 design work.[32] The initial request for construction bids returned two bids in July 2016 that came in over budget, leading CATS to request a second round of bidding the following month.[33] On November 28, 2016, the council awarded a $94 million construction contract to Johnson Bros. Corporation to build the 2.5 miles of trackage in Phase 2, as well as associated road and landscaping work.[34] Construction began in 2017,[35] with completion required by August 31, 2020, under the terms of the federal funding used.[34] Starting on June 3, 2019; CATS replaced streetcar service along the line with a shuttle bus in order to facilitate construction of Phase 2 and make the existing stations taller by a few inches for the new trains to go through. Streetcar service was initially slated to resume in 2020, but was pushed back to 2021 to accommodate the 2020 Republican National Convention.[36] Issues with the construction contractor delayed the opening to early 2021.[10]

Future construction

The third and final phase of the CityLynx Gold Line between Hawthorne Lane and Eastland CTC, and from French Street to Rosa Parks CTC, has been planned, but lacks funding. This segment was originally scheduled for completion by 2023 at a cost of $231 million. It was reported in July 2015, however, that the city had no funds to contribute toward the building of the third phase.[9]

Rolling stock

Gomaco-built car 93 laying over on Trade Street, below the CTC/Arena Lynx light rail station

Future fleet

Year built Manufacturer Model Image Length Width Fleet Numbers Quantity Notes
2019-2020 Siemens Mobility Siemens S700 85 ft (26 m)[37] 104 in (2.64 m)[37] 401–406 6 units To enter service from early 2021.

Retired fleet

Years in Service Manufacturer Model Image Length Width Fleet Numbers Quantity Notes
2015–2019 Gomaco Trolley Company Birney-style replica streetcar 48.9 ft (15 m)[38] 10 ft (3.05 m)[38] 91–93 3 units Built in 2003-2004. Formerly used on the Charlotte Trolley from 2004 to 2010.

As of late 2020, a rail replacement bus service runs along the route of the CityLynx Gold Line, serving as a placeholder until Phase 2 of the line opens in early 2021. Until June 2019, when streetcar service was suspended to facilitate Phase 2 construction, the line used three vintage-style replica-Birney streetcars built in 2003–04 by the Gomaco Trolley Company (Nos. 91–93) and transferred from the former Charlotte Trolley system.[39] Powered by an overhead catenary system at 650 volts DC and driven by 30 HP General Electric traction motors, the streetcars were air-conditioned and handicapped-accessible, with a capacity of 105 passengers (48 seated, 57 standing)[9][38] They had a balance speed of 30 mph (48.28 km/h).[38] The replica trolleys will be retired and sold after Phase 2 of the line opens.[37]

In November 2016, Siemens Mobility was awarded a $40 million contract for six S700[lower-alpha 1] low-floor streetcars and associated parts to service the entire Gold Line route.[34][41] They were delivered between August 2019 and April 2020 and are numbered 401–406.[42] The vehicles have 56 passenger seats, with a total capacity of 255 passengers,[37] and have a maximum speed of 35 mph (56 km/h). [43] Their design and color schemes are similar to the vehicles used on the Blue Line.[44] [37]

While the line was served by the Gomaco-built faux-vintage streetcars, the overhead wire was powered at 650 volts DC, but CATS will raise the voltage to 750 V (standard voltage among U.S. light rail systems) when the modern Siemens vehicles take over the service.[5]

Fares

Phase 1 of the Gold Line was free for all passengers.[9] The standard CATS fares will be introduced once Phase 2 is operational.[37]

Criticism

The CityLynx Gold Line project has been criticized for its high cost and limited projected benefits for the areas it is intended to serve, though at the present time, the net benefits from future development as a result of the streetcar line are difficult to assess. The line is currently estimated to cost $150 million to build, with an additional $6.2 million a year incurred in operating costs. According to city officials, the cost increase is largely inflation-based.[31] Recent cost-benefit analyses have shown that at a cost of $1.58 per passenger mile (predicted for 2019), it would cost twice as much to operate as either city bus (77 cents/passenger mile, in 2012) or light rail services (68 cents/passenger mile, in 2012), while traveling over a shorter distance. [45]

See also

Notes

  1. These were model S70 when the order was placed, but in 2020 were retroactively rebranded as model S700 by Siemens.[40]

References

  1. "CityLYNX Rail Service Gold Line Gold Line Phase 1". Charlotte Area Transit System. Retrieved September 5, 2015.
  2. Harrison, Steve (August 25, 2015). "Streetcar ridership tops projections". The Charlotte Observer. Retrieved August 26, 2015.
  3. Fowler, Hayley (June 8, 2015). "CityLynx Gold Line streetcar set to open July 14 in uptown Charlotte". The Charlotte Observer. Retrieved February 27, 2016.
  4. "CityLYNX Gold Line Phase 2 December 2020 Update". City of Charlotte. December 2020. Retrieved December 12, 2020.
  5. Pence, Herbert (November 2015). "Going for Gold in Charlotte". Tramways & Urban Transit. UK: LRTA Publishing. pp. 434–437. ISSN 1460-8324.
  6. "CityLYNX Rail Service Gold Line Gold Line Overview". Charlotte Area Transit System. Retrieved August 30, 2014.
  7. Rubin, Richard (June 29, 2006). "City eyes east-west streetcar". The Charlotte Observer. pp. 4B.
  8. Harrison, Steve (January 15, 2015). "Charlotte streetcar opening delayed until June". The Charlotte Observer. Retrieved February 27, 2016.
  9. Harrison, Steve; Portillo, Ely (July 14, 2015). "Charlotte's Gold Line streetcar shimmers on first run". The Charlotte Observer. Retrieved May 20, 2017.
  10. Boraks, David (July 10, 2020). "Streetcar Could Open In January; CATS Blames Contractor For Delays". WFAE. Retrieved July 20, 2020.
  11. Rubin, Richard (November 16, 2006). "Rail plans to north, university roll ahead". The Charlotte Observer. pp. 1A.
  12. Rubin, Richard (January 7, 2007). "Lay track. Wait years. Ride - Plan: Streetcars to roll a decade after rails in place". The Charlotte Observer. pp. 1B.
  13. Harrison, Steve (March 28, 2008). "Streetcar move-up has CATS pressed". The Charlotte Observer. pp. 1B.
  14. Tierney, Dan (June 1, 2008). "City OKs further study of streetcars, their costs". The Charlotte Observer. pp. 1M.
  15. Harrison, Steve (September 20, 2011). "Charlotte streetcar project could bring up to 385 jobs". The Charlotte Observer.
  16. "Contract awarded for Charlotte streetcar project". Trains. November 20, 2012. Retrieved November 22, 2012.
  17. Bethea, April (December 12, 2012). "Despite uncertain future, Charlotte breaks ground on streetcar". The Charlotte Observer.
  18. "CityLynx Gold Line Fact Sheet" (pdf). Charlotte Area Transit System. July 2013.
  19. "CityLynx Gold Line Update" (pdf). Charlotte Area Transit System. May 2014.
  20. Harrison, Steve (October 30, 2012). "No breakthrough for Charlotte city council on streetcar". The Charlotte Observer.
  21. Harrison, Steve (December 11, 2012). "Foxx offers to cut streetcar to pass capital plan". The Charlotte Observer.
  22. Harry, Colleen (December 17, 2012). "Charlotte City Council delays budget vote". WBTV News.
  23. Harrison, Steve (January 31, 2013). "Memo: McCrory threatens light-rail money over streetcar". The Charlotte Observer.
  24. Harrison, Steve (April 11, 2013). "City's streetcar plan slows". The Charlotte Observer.
  25. Harrison, Steve (May 13, 2013). "Streetcar gets boost from city manager". The Charlotte Observer.
  26. Harrison, Steve (May 16, 2013). "Consultant: Streetcar could spark Charlotte development". The Charlotte Observer.
  27. Harrison, Steve (May 29, 2013). "In a switch, City Council OKs streetcar". The Charlotte Observer.
  28. Harrison, Steve (September 3, 2013). "Charlotte's streetcar misses grant, suffers setback". The Charlotte Observer.
  29. Harrison, Steve (January 27, 2014). "Charlotte makes $12 million bet on streetcar". The Charlotte Observer.
  30. Lyttle, Steve (February 26, 2014). "FTA gives CATS streetcar extension green light". The Charlotte Observer.
  31. Harrison, Steve (September 8, 2014). "Despite higher costs, Charlotte streetcar moves ahead". The Charlotte Observer.
  32. Wester, Jane (June 22, 2015). "City Council approves $7.7 million for second phase of streetcar line". The Charlotte Observer.
  33. "CATS to re-bid $150 million Charlotte streetcar expansion". Charlotte Business Journal. August 23, 2016. Retrieved December 1, 2016.
  34. "Next phase of Charlotte's streetcar moves forward with $134M in contracts approved". Charlotte Business Journal. November 29, 2016. Retrieved December 1, 2016.
  35. "Charlotte streetcar project enters second phase". Trains magazine. January 17, 2017. Retrieved January 18, 2017.
  36. Joe Marusak (May 14, 2019). "Charlotte's streetcar service will stop running for 18 months. Here's when and why". The Charlotte Observer.
  37. "CityLynx Gold Line Phase 2 FAQ" (PDF). Charlotte Area Transportation System. 2020. Retrieved December 12, 2020.
  38. "Charlotte Area Transit System Replica Birney Trolley Specifications". Gomaco Trolley Company. Retrieved December 12, 2020.
  39. "Charlotte CityLYNX streetcar opens". Tramways & Urban Transit. UK: LRTA Publishing. September 2015. p. 348.
  40. "Siemens rebadges North American low-floor cars". Tramways & Urban Transit (993). UK: Mainspring Enterprises Ltd. September 2020. p. 336. ISSN 1460-8324.
  41. "Siemens finalizes S70 streetcar deal with Charlotte". Railway Age. November 29, 2016. Retrieved December 1, 2016.
  42. "Worldwide Review [regular news section]". Tramways & Urban Transit (995). UK: Mainspring Enterprises Ltd. November 2020. p. 441. ISSN 1460-8324.
  43. "S700 streetcar". Siemens Mobility. Retrieved December 12, 2020.
  44. "Gold Line Overview". Charlotte Area Transit System. Retrieved September 7, 2015.
  45. Harrison, Steve (September 14, 2014). "Charlotte's streetcar projected to cost more than bus, light rail". The Charlotte Observer.

KML is from Wikidata


This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.