List of natural gas power stations in Vietnam
Source : updated with data from Ministry of Industry and Trade (MOIT) 2019 Report 58/BC-CBT,[1] updated with Decision 125/QD-DTDL,[2] updated using press releases.
Power plants | Other names | Sponsors | Capacity (MW) | Status | Province | Commission date | Source | Note |
---|---|---|---|---|---|---|---|---|
O Mon III Combined Cycle Gas Turbine Plant | EVN (ODA) | 1x750 | pre-permit/permitted | Can Tho | 2025 | MOIT Report 58/BC-CBT annex row I.13 | ||
O Mon IV Combined Cycle Gas Turbine Plant | EVN | 1x750 | pre-permit/permitted | Can Tho | 2023 | MOIT Report 58/BC-CBT annex row I.14 | ||
Dung Quat I Combined Cycle Gas Turbine Plant | EVN | 750 | pre-permit/permitted | Quang Ngai | 2024 | MOIT Report 58/BC-CBT annex row I.19 | ||
Dung Quat III Combined Cycle Gas Turbine Plant | EVN | 750 | pre-permit/permitted | Quang Ngai | 2025 | MOIT Report 58/BC-CBT annex row I.20 | ||
Nhon Trach 3&4 Combined Cycle Gas Turbine Plant | PVN | 2x750 | pre-permit/permitted | Dong Nai | 2023-2024 | MOIT Report 58/BC-CBT annex row II.5 | ||
Kien Giang 1&2 Combined Cycle Gas Turbine Plant | PVN | 2x750 | Announced | Kien Giang | After 2030 | MOIT Report 58/BC-CBT annex row II.6 | ||
Mien Trung 1,2 Combined Cycle Gas Turbine Plant | PVN | 2x750 | pre-permit/permitted | Quang Nam | 2024-2025 | MOIT Report 58/BC-CBT annex row II.7 | ||
Son My II Combined Cycle Gas Turbine Plant | AES Corporation, PVGAS | 3x750 | Announced | Binh Thuan | 2026-2028 | MOIT Report 58/BC-CBT annex row II.8 and [3] | ||
Dung Quat II Combined Cycle Gas Turbine Plant | BOT | 750 | Announced | Quang Ngai | 2026 | MOIT Report 58/BC-CBT annex row IV.12 | ||
Son My Combined Cycle Gas Turbine Plant | Electricité De France (EDF), Kiushu, Sojitz, PAC | 3x750 | Announced | Binh Thuan | 2028-2029 | MOIT Report 58/BC-CBT annex row IV.15 and [4] | ||
O Mon II Combined Cycle Gas Turbine Plant | no investor | 750 | Announced | Can Tho | 2026 | MOIT Report 58/BC-CBT annex row VI.3 | ||
Ca Na LNG gas power plant | Gulf Energy Development Group (Thailand) | 4x1500 | Announced | Ninh Thuan | unknown | [5] | ||
Ca Mau 1&2 gas power plant | PetroVietnam Power Ca Mau | 2x750 | operating | Ca Mau | 2008 | [6] and decision 125/QD-DTDL annex 3 row 22-23 | ||
Nhon Trach 1 gas power plant | PetroVietnam Power Nhon Trach | 450 | operating | Dong Nai | 2009 | [7] | ||
Nhon Trach 2 Combined Cycle Gas Turbine Plant | PetroVietnam Power Nhon Trach 2 | 750 | operating | Dong Nai | 2011 | [8] | ||
Bac Lieu LNG gas power plant | Delta Offshore Energy | 3200 | Announced | Bac Lieu | unknown | [9] | ||
Phu My 2.1 | Phu My Thermal Power Company, GENCO3 | 477 | operating | Vung Tau | 1997 | [10] and Decision 125/QD-DTDL annex 1 row 15 | ||
Ba Ria | Ba Ria Thermal Power Company, GENCO 3 | 340 | operating | Vung Tau | 1992-2002 | [11] and Decision 125/QD-DTDL annex 3 row 21 | ||
Phu My 2.1 extension | Phu My Thermal Power Company, GENCO 3 | 468 | operating | Vung Tau | 1999 | [12] and Decision 125/QD-DTDL annex 1 row 15 | ||
Phu My 4 | Phu My Thermal Power Company, GENCO 3 | 477 | operating | Vung Tau | 2004 | [12] and Decision 125/QD-DTDL annex 1 row 16 | ||
Phu Yen | J-Power | Announced | Phu Yen | [13] | ||||
Long Son Petrochemical Complex | Mien Nam Petrochemical Complex | SCG Group (Thailand) | 2x10 | permitted | Vung Tau | 2023 | [14] | |
O Mon | EVNGENCO2 | 2x330 | operating | Can Tho | 2009-2015 | [15][16] | ||
Phu My 1 | Phu My Thermal Power Company, GENCO 3 | 1118 | operating | Vung Tau | 2001 | [12][17] and Decision 125/QD-DTDL annex 1 row 14 | ||
Phu My 3 | Phu My 3 Bot Power Company LTD, BP Holdings BV (England), SempCorp Utilities company (Singapore), Kyushu and Nissho Iwai (Japan) | 720 | operating | Vung Tau | 2004 | [18][19] and Decision 125/QD-DTDL annex 3 row 18 | ||
Phu My 2.2 | Mekong Energy Company LTD, Electricité De France (EDF), Sumitomo, TEPCO | 720 | operating | Vung Tau | 2005 | [20] and Decision 125/QD-DTDL annex 3 row 17 | ||
Long Son | EVNGENCO3 | 3x1200 | Announced | Vung Tau | 2019-2025 | [21] |
This is a list of gas power plants in Vietnam.
Notes
- Announced: Projects that are in the planning decision of the government or companies but have not yet obtained a permit or permission for land use rights, coal supply rights.[22]
- Pre-permit development: Projects have started to implement one of the following items: environmental licenses, land and water use rights, financial security, transmission contract guarantees, etc.[22]
- Permitted: Projects that have been licensed for environmental licenses but have not yet begun to break ground.[22]
- Construction: Projects are being built after the groundbreaking ceremony.[22]
- Shelved: Projects do not have specific information on the project's progress but do not have enough information to declare the project canceled.[22]
- Cancelled: Projects are not progressing after a very long time with no information about the project; Projects converted to natural gas are considered to have not used coal anymore; projects have appeared in government documents but then disappeared.[22]
- Operating: Projects with an official date of Commercial Operation Date (COD).[22]
References
- Hoàng, Quốc Vượng (2019-06-04). "Report 58/BC-CBT on the Implementation Progress of Power Projects in the Revised PDP7". vepg.vn.
- Nguyễn, Anh Tuấn (2014-12-29). "Decision 125/QD-DTDL on Issuing List of power plants participating in the Competitive Generation Market 2015" (PDF). erav.vn.
- Ngọc Hà (2018-05-18). "Thêm một "ông lớn" Mỹ muốn triển khai dự án nhà máy nhiệt điện khí tại Việt Nam". vietstock.vn.
- P.V (2018-11-12). "Mô hình LNG cho tổ hợp khí-điện tại Sơn Mỹ – Bình Thuận". petrovietnam.petrotimes.vn.
- Nguyên Đức (2019-03-21). "Tập đoàn Gulf (Thái Lan) "nhắm" dự án điện khí Cà Ná 7,8 tỷ USD". Đầu Tư Online.
- PetroVietnam Power (2017-05-05). "Nhiệt điện khí Cà Mau 1&2". pvpower.vn.
- PetroVietnam Power (2017-05-05). "Nhiệt điện khí Nhơn Trạch 1". pvpower.vn.
- PetroVietnam PVPower NT2. "Nhà máy điện Nhơn Trạch 2 hiện tại vận hành rất ổn định, an toàn, cung cấp sản lượng điện hiệu quả, góp phần đảm bảo an ninh năng lượng quốc gia và phát triển kinh tế xã hội". pvpnt2.vn.
- Trung Chánh (2019-01-23). "Dự án điện khí 4,3 tỉ đô la được kỳ vọng giúp Bạc Liêu thoát nghèo". Kinh Tế Sài Gòn Online.
- Theo Thể thao và Văn hóa (2010-09-17). "Phú Mỹ - Trung tâm điện lực lớn nhất nước". nhandan.com.vn.
- Công Ty Cổ Phần Nhiệt Điện Bà Rịa (2011-09-15). "Tóm tắt quá trình hình thành và phát triển của Công ty Cổ phần Nhiệt điện Bà Rịa". btp.com.vn.
- MOIT (2017-05-16). "Nhiệt điện Phú Mỹ góp phần bảo đảm an ninh năng lượng quốc gia". moit.gov.vn.
- Thủy Tiên (2018-06-07). "J - POWER tìm hiểu để xây dựng nhà máy điện khí tại Phú Yên". baophuyen.com.vn.
- Hoàng Nam (2019-03-12). "Tổ hợp hóa dầu Long Sơn: Gỡ bỏ nút thắt cuối cùng". Đầu Tư Online.
- NANGLUONGVIETNAM (2017-09-22). "Nhiệt điện Ô Môn 1 sẽ chuyển sang chạy khí thay dầu FO". Năng Lượng Việt Nam.
- Nhã Uyên (2015-06-15). "Tổ máy 2 Nhà máy Nhiệt điện Ô Môn I: Hòa điện lần đầu vào lưới điện quốc gia". evn.com.vn.
- N. Hữu (2001-12-31). "Nhà máy Nhiệt điện Phú Mỹ 1 phát điện tổ máy cuối cùng". nld.com.vn.
- Theo (2010-09-15). "Khánh thành Nhà máy điện Phú Mỹ 3". nhandan.com.vn.
- Thanh Hương (2015-05-25). "SembCorp chi đậm để thế chân BP tại nhiệt điện Phú Mỹ 3". Đầu Tư Online.
- P.D (2005-10-20). "Vận hành Nhà máy điện Phú Mỹ 2.2, công suất 715 MW". nld.com.vn.
- Thanh Thủy (2018-02-23). "EVN và GENCO 3 đầu tư dự án điện khí quy mô 4,39 tỷ USD tại Bà Rịa - Vũng Tàu". ndh.vn.
- "End Coal | Frequently Asked Questions". End Coal. Retrieved 2019-07-25.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.