Rome–Naples high-speed railway

The Rome–Naples high-speed railway line is one of the railways in the Italian high-speed rail network. Initially opened in December 2005, it is the first railway line in Italy to be electrified at 25 kV AC (instead of traditional 3 kV DC) and the first in the world to use ETCS Level 2 in normal rail operations.

Rome–Naples high-speed railway
A straight section line of the line near Anagni
Overview
Native nameFerrovia Roma-Napoli (alta velocità)
StatusOperational
OwnerRete Ferroviaria Italiana (RFI)
LocaleItaly
TerminiRoma Termini
Napoli Centrale
Service
TypeHeavy rail
SystemItalian high-speed rail system
Operator(s)Rete Ferroviaria Italiana
History
Opened19 December 2005
completed on 13 December 2009
Technical
Line length204.6 km (127.1 mi)
Number of tracks2
Track gauge1,435 mm (4 ft 8 12 in)
Minimum radius5,450 metres (17,880 ft) except for short sections
Electrification25 kV AC
Operating speed300 kilometres per hour (190 mph)
SignallingERTMS/ETCS level 2
Maximum incline2.1%
Route map

4.505
Roma Tiburtina
3.419
0.000
2.061
4.256
Roma Prenestina
4.975
Serenissima tunnel
(1273 m)
(5.288)
Serenissima
(opened 17.12.2006)
6.248
6.410
signalling border
(12.018)
Salone
12.935
Salone crossing loop
Rome-Sulmona railway
26.480
Massimo tunnel
(1330 m)
27.810
29.738
Colli Albani tunnel
(6628 m)
36.366
36.615
Labico crossing loop
50.947
Castello tunnel
(1250 m)
52.197
61.178
Anagni crossing loop
Morolo
66.372
Sgurgola tunnel
(2293 m)
68.665
79.499
Macchia Piana tunnel
(1801 m)
81.300
82.347
La Botte tunnel
(1516 m)
83.683
88.404
Ceccano crossover
97.148
Colle Pece tunnel
(1048 m)
98.196
111.985
San Giovanni crossing loop
132.892
Sant'Angelo crossing loop
Rocca d'Evandro-San Vittore
142.328
Bivio Cassino Sud
142.352
Montelungo tunnel
(2897 m)
145.249
147.921
Campozillone tunnel
(3963 m)
151.884
152.843
Tora-Piccilli crossing loop
170.472
Briccelle tunnel
(1347 m)
171.816
173.485
Pignataro crossover
176.782
Caserta North junction no 1
Capua
195.676
Gricignano junction no 1
Gricignano-Teverola
209.985
Napoli Afragola
211.337
Santa Chiara tunnel
(1315 m)
212.652
214.760
signalling border
215.336
Casoria Nord junction
(to Salerno (via Mount Vesuvius))
Autostrada A1 - European route E45
220.861
(0.894)
222.397
Napoli Centrale

Planning for the high-speed route commenced during the 1980s following its identification as a favourable option for development ahead of several proposed options. During May 1995, following a competitive tender, contracts for the line's construction were awarded to a range of contractors that were collectively known as the IRICAV UNO consortium.[1] Construction of the line involved the boring of 28.3 km of tunnels, as 13 percent of the selected route was underground. Despite the geological challenges present, the construction process was relatively steady and proceeded to plan. During March 2001, it was announced that all civil engineering works had been completed, fulfilling the agreed schedule and with little divergence in terms of costs.

The first section of the railway, between Roma Termini and Gricignano di Aversa, was opened to traffic on 19 December 2005. The final 25 kilometres (16 miles) from Gricignano to Napoli Centrale opened on 13 December 2009. It is owned and operated by Rete Ferroviaria Italiana (RFI), while the trains running upon the railway are operated by both the state rail company Trenitalia and the privately-owned open access company Nuovo Trasporto Viaggiatori (NTV). When the line has been fully completed, trains will typically take one hour and ten minutes to travel between the two cities. The line is part of Corridor 1 of the European Union's Trans-European high-speed rail network, which connects Berlin and Palermo.

History

Background

During the 1980s, Italian railway planners studied options for the expansion of its fledging high-speed rail network.[1] It was quickly identified that a new railway between Rome and Naples would be particularly desirable amongst the potential options, not least at it would interface with existing lines (such as the existing Florence–Rome high-speed railway) to form a high speed network that better connected the south and north of Italy. The initiative also aligned with European politicians, who recognised the wider strategic value represented of a wider high speed network spanning the majority of regions across the member states of the European Community (later rebranded as the European Union).[1]

Following an extensive surveying effort, a route for the proposed railway was selected; its total length was 204 km, of which 13 percent (28.3 km) was to run through a series of bored tunnels.[1] Early on, it was decided that the envisioned construction programme ought to be divided into several lots, covering different sections of the railway's route.[1] These were put out to competitive tender, during which bidders submitted detailed design specifications for their proposed civil works. From this process, a number of contracts were awarded to five contractors, these being Pegaso, Icla, Italstrade, Vianini and Condotte. Furthermore, these companies were also collectively appointed as the general contractor for the railway, known as the IRICAV UNO consortium.[1]

Construction

During May 1995, construction of the railway commenced, immediately following the issuing of the contracts.[1] The majority of the route's complex undertakings were the underground works performed; the majority of boring was driven through volcanic rock that possessed generally favourable properties. Where deformation phenomena was predicted (or detected), various techniques were employed to stabilise the ground, such as the use of shotcrete, fibre glass structural elements, and additional concrete lining where applicable.[1] Several of the lengthier tunnels of the line were accompanied by secondary access tunnels, each large enough to permit their use by road vehicles. Relatively few alterations or remedial works were required during the railway's construction.[1]

By the end of 1999, approximately 21.6 km of tunnel had been completed, roughly equivalent to 99% of the railway's underground sections.[1] The average advance rates of these tunnels was typically 20 meters per day, discounting accessory works such as access tunnels and shafts. Some tunnels, such as the Colli Albani and Sgurgola tunnels, had been bored at a relatively fast rate and constant rate, indicative of a good match between the construction techniques applied and the geological conditions present.[1] This outcome likely supported the relatively small divergence between estimated and actual costs incurred by the works. During March 2001, it was announced that all of the railway's civil engineering works had been completed as per schedule.[1]

The longest tunnel on the line through the Alban Hills is 6,725 metres (4 miles) long. The minimum radius of curves is 5,450 metres (5,960 yards) and the centres of the running lines are 5 metres (16 feet 5 inches) apart. The maximum gradient of the line is 21 per thousand.

Between 2004 and 2005, a series of tests was carried out prior to the line being opened for commercial operations, to obtain approval for the line to be regularly operated at up to 300 km/h (190 mph). During these tests, an ETR 500 train achieved a speed of 347 km/h (216 mph), such speeds having been made possible by the line's 25 kV AC railway electrification system (rather than the traditional Italian use of 3 kV DC), and the adoption of new signaling, control and train protection system provided by the European Rail Traffic Management System/European Train Control System (ETCS). It was the first railway line in Italy to be electrified at 25 kV AC at 50 Hz and the first in the world to use ETCS Level 2 in normal rail operations.

Opening and post-opening developments

The first 193 kilometres (120 miles) of the line was brought into service on 19 December 2005. The new line begins near Roma Prenestina station (4.5 kilometres (2.8 miles) from Roma Termini) and ends at Gricignano di Aversa, where a connecting line leads to the Rome-Naples via Formia line, which is used for the last 25 kilometres (16 miles) to reach Napoli Centrale station. The line features three other interconnections that link with the historical Rome-Naples via Cassino line, near Anagni, Cassino and Caserta. Via its interlinking with other Italian high speed lines, the Rome-Naples line has facilitated a competitive railway connection between Naples and Milan along which the railway has reportedly gained market share in contrast to road and air travel.[2]

On 13 December 2009, work was completed on the last 18 km line of the line between Gricignano and Napoli Centrale. This includes the Napoli Afragola station, which was originally due to be open in 2009 when the construction contract was first awarded, but construction had to be temporarily put on hold while the work was retendered.[3] Thus, construction was delayed on several occasions and did not get fully underway until 2015. It was opened on 6 June 2017, with regular traffic for passengers starting from 11 June 2017.[4]

Since opening, the Afragola Station has been typically served by 36 high-speed trains running upon the line, carrying a projected 10,000 passengers, each day; 18 of these being Frecciarossas operated by the state rail company Trenitalia while the other 18 trains are Italos by the privately-owned open access company Nuovo Trasporto Viaggiatori (NTV).[5] A new interchange with the railway shall be formed at Afragola station following the reconstruction of the Circumvesuviana line, which had been reportedly scheduled for completion in 2022.

The Naples–Salerno high-speed railway (also known as the Linea a Monte del Vesuvio—"line up Mount Vesuvius") was completed in June 2008 to allow high-speed trains to and from Salerno and the south to bypass Napoli Centrale station. The length of the high-speed section is about 205 kilometres (127 miles). The connecting line to Gricignano di Aversa is now not used for normal operations.[6]

See also

References

  1. "Appendix B: The design and construction of tunnels for the new Bologna-Florence high speed/capacity railway line" (PDF). link.springer.com. Retrieved 15 September 2020.
  2. Barrow, Keith (2 May 2019). "Exporting the Italian recipe for high-speed success". railjournal.com.
  3. "Afragola station delayed" (156). Today's Railways Europe. December 2008: 52. Cite journal requires |journal= (help)
  4. "Prime Minister inaugurates Napoli Afragola station". Railway Gazette. 6 June 2017. Retrieved 7 June 2017.
  5. "Napoli Afragola - Italy’s remarkable new station." Rail Engineer, 28 June 2017.
  6. "Roma-Napoli: il tracciato" (in Italian). Rete Ferroviaria Italiana. Archived from the original on 19 December 2008. Retrieved 15 February 2009.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.