Site C dam

The Site C Dam is an under construction run-of-the-river hydroelectric dam on the Peace River near Fort St. John in northeastern British Columbia, Canada. It is located approximately 80 kilometres downstream from the W. A. C. Bennett Dam. When completed in 2024, the Site C Dam will become the 4th largest producer of hydroelectricity in British Columbia with an installed capacity of 900 MW and an expected annual output of 5,100 GWh of electricity.[1][2][3]

Site C
Dam construction as of April 2017
Location of Site C in British Columbia
Official nameSite C Project
LocationBritish Columbia, Canada
Coordinates56°11′41″N 120°54′51″W
StatusUnder construction
Opening date2024 (planned)
Construction costC$20 billion, est.
Owner(s)BC Hydro
Dam and spillways
Type of damEarth fill[1]
ImpoundsPeace River
Height60 m (200 ft)[1]
Length1,050 m (3,440 ft)[1]
Reservoir
Surface area9,330 ha (23,100 acres)[1]
Power Station
Installed capacity900 MW [1]
1,100 MW (max) [1]
Annual generation5,100 GWh[1]

The project has drawn considerable opposition from several quarters due to its planned flooding of agricultural land, damage to the local environment, high construction cost, possible alternatives, and the uncertainty of future electricity prices and demand in the province. Two Treaty 8 First Nations, and local landowners have made legal challenges to the dam, though these were dismissed by the federal Court of Appeal.[4][5] In addition, over 200 scholars, as well as the Royal Society of Canada, have expressed concerns to the federal Liberal government, citing weakness in the regulatory review process and the environmental assessment for the project.[6][7] In May 2016 the federal government stated it is "not revisiting projects that have been reviewed and approved".[8] On 11 December 2017, John Horgan, the Premier of British Columbia, announced: "We've come to a conclusion that, although Site C is not the project we would have favoured or would have started, it must be completed,"[9] thus guaranteeing the completion of the project.

History

When completed, Site C will be the third of four major dams on the Peace River that were initially proposed in the mid-twentieth century. The first project was the flagship W. A. C. Bennett Dam 19 kilometres west of Hudson's Hope. The Bennett Dam began operation in 1968 and formed Williston Reservoir, which is 95% larger than the Site C reservoir will become.[10] Construction of the Peace Canyon Dam was completed in 1980 at a point 23 km downstream of the W. A. C. Bennett dam. The third dam,"Site C," was also proposed at the time for a site 83 km downriver of the Peace Canyon dam, or approximately 7 km southwest of Fort St. John. Site C would flood an 83 km length of the Peace River valley, widening the river by up to three times, as well as a 10 km length of the Moberly River valley and 14 km of the Halfway River valley. The fourth proposed dam on the British Columbia segment of the Peace River, Site E, near the BC–Alberta border, was removed from the planning process during hearings in 1982.

Portion of 80 kilometre stretch of valley planned for flooding

After hearings between 1981 and 1983, the British Columbia Utilities Commission turned down the Site C project.[11] The commission was critical of BC Hydro's forecasting methods, declaring that it neither explicitly took energy prices into account nor relied on statistically significant past patterns of behaviour.[11] BC Hydro then chose to purchase electricity under long-term contracts from independent power producers, and it continues to do so today. As of 2017 these annual purchases are about four times the capacity of Site C. Once the initial contracts with BC Hydro expire, these independent producers may be free to export their electricity.[12]

In April 2010, passage of the Clean Energy Act exempted the project from further BC Utilities Commission review.[13] Site C was being reconsidered by BC Hydro for two years prior as the utility reconsidered expansion of its dam capacity on the Peace.[2] Also in April 2010, the provincial government announced it would move forward on planning for the project, moving it to the regulatory review phase.[2] The review was mandated under the Canadian Environmental Assessment Act, 2012 (CEAA 2012) and the British Columbia Environmental Assessment Act (BCEAA). To avoid duplication, the governments of Canada and British Columbia set up a cooperative federal-provincial environmental assessment, including a joint review panel (JRP) process.[14]

In October 2014, Site C received environmental assessment approvals from the federal and provincial governments after a three-year environmental review, including a federal/provincial Joint Review Panel process.[15] In December 2014, the provincial government announced a final investment decision, approving the construction of the hydroelectric project at a cost of $8.335 billion, as well as a project reserve of $440 million. A notice of Site C construction commencing in 2015 was issued in July 2015.[16] By March 2016, site clearing, attempts at bank stabilization and the search for bedrock took the majority of BC Hydro's focus - there were no "works" in the ground; the diversion tunnels had not yet been started. BC Premier Christy Clark's stated intention was to get dam construction "to the point of no return" by the time of a scheduled general election in May 2017.[15] The provincial election resulted in the previous Liberal government being defeated and a New Democratic government taking office. The newly elected government requested the BC Utilities Commission 2017 review.

The project has sparked controversy for a number of reasons: First Nations treaty rights are at issue,[17] the dam is thought by many to be economically unviable, and there are concerns about the loss of agriculturally productive land and the overall environmental impact.[18] The federal/provincial Joint Review Panel found that the need for the electricity had not been clearly demonstrated, nor were alternatives to the project evaluated.[14]

Cost

Site C Dam construction site near Fort St. John. Clearing on far side of river is part of the construction zone.

A cost estimate produced during the 2007 feasibility study placed the financial cost at a maximum of C$6.6 billion based on the 1981 design, safety, and engineering standards.[19][20] An updated cost projection was released in May 2011 placing the estimated cost at $7.9 billion,[21] which was revised to $8.3 billion in 2014.[20] This does not include the cost of a transmission line to major population centres, estimated to be in the range of $743 million additional, bringing the total estimated cost to approximately $9 billion.[22] At the invitation of the British Columbia Utilities Commission, Deloitte published a report on the project, and noted that it's likely to miss a crucial river diversion deadline; this will bring the cost to just under $10 billion.[23] Some experts have stated that the costs may reach as high as $11 to 12 billion.[24]

Economic estimates in 2016 by Harry Swain, former chair of the Joint Review Panel and former BC deputy minister of Industry, projected that if all the power were sold to the US spot market, as little as $1.8 billion would be returned, and the rest ($7 billion) of the cost would be covered by taxpayers. Power consumption has not been increasing despite increasing population.[25] Swain also stated that power roughly equivalent to that produced by Site C could be reclaimed from American producers under the Columbia River Treaty at no capital cost to the province; the power is currently sold to American utilities at about half the projected cost of Site C power.[15] British Columbia Utilities Commission has stated that the Canadian entitlement under the treaty, however, is not a suitable source of dependable capacity.[26]

Site C is planned to have 132.5MW of capacity per $billion. In BC Hydro's latest upgrades, the John Hart Dam is planned for 120.2MW of capacity per $billion and the Ruskin Dam is planned for 142.5MW of capacity per $billion.

Members of the Treaty 8 First Nations boycotted the official Site C announcement ceremony at the Bennett Dam in April 2010,[17] and the West Moberly First Nation publicly stated that it was considering legal action to oppose the dam.[17] In April, 2016, a group of landowners and farmers from BC's Peace River Valley launched a legal challenge to the project. The landowners' case states that the Provincial government ignored concerns about the project raised by the Joint Review Panel, including its cost, failure to demonstrate the need for the project, and lack of evaluation of alternatives.[4] Also in April 2016, BC Treaty 8 First Nations filed a legal challenge in the Supreme Court of BC. The Peace Valley Landowners’ Association, BC Treaty 8 First Nations, Alberta Treaty 8 First Nations, and Blueberry River First Nation were pursuing actions in federal court.[4]

As of December 2016, five judicial reviews of Site C's environmental approvals have been dismissed. These include two challenges from the Peace Valley Landowner Association in the B.C. Supreme Court and the Federal Court of Appeal, as well as a pair of challenges against the project's federal and provincial environmental approvals from the West Moberly and Prophet River First Nations. On 23 January 2017, the sixth legal challenge was dismissed, involving Treaty 8 First Nations, which was in the federal court.[27]

Scholars' concerns

In May, 2016 a group of over 200 Canadian scholars signed a letter raising serious concerns about the process used to approve the Site C dam. The Royal Society of Canada took the "unusual step" of writing a separate supporting letter to Prime Minister Justin Trudeau.[28] The letter from those "concerned scholars" summarized their concerns: "Our assessment is that this process did not accord with the commitments of both the provincial and federal governments to reconciliation with and legal obligations to First Nations, protection of the environment, and evidence-based decision-making with scientific integrity."[6] Scientists argue that the environment impacts of the dam and the lack of First Nations consent make the dam a "'bellwether' of the Trudeau government's commitment to develop resources in a more science-based, sustainable and socially responsible way."[7] The federal government rejected the scholars' call to halt construction. Environment and Climate Change Minister Catherine McKenna's office indicated that the government had no intention to revisit the Site C environmental assessment.[8]

Utilities Commission 2017 review

BC's opposition New Democratic Party promised a review of the project by the BC Utilities Commission (BCUC) should they win the 2017 general election. Hydro critic Adrian Dix called the B.C. Liberal government "reckless" for not having already done the review, as was recommended by the federal-provincial Joint Review Panel led by Harry Swain.[15] On 2 August 2017, following a Provincial election, the NDP government requested that the BCUC evaluate the cost to BC Hydro ratepayers of continuing, suspending or terminating construction of the Site C dam. In its Final Report published on 1 November 2019, the BCUC reached two overarching conclusions:

  • The cost to ratepayers of suspending construction would be significantly higher than either continuing or terminating the project, to the tune of $3.6 billion. In addition, there are significant risks that it would not be possible to restart the project due to permitting and other issues.
  • The cost to ratepayers of continuing or terminating construction is similar, given the assumptions that the BCUC finds to be most reasonable. Both alternatives also have risks which may cause one or the other to be more costly to ratepayers either in the short-term or over a longer period.[29]

To assist the government in its decision-making, the BCUC included in the Final Report some sensitivity analyses to show how the cost estimates would change if different assumptions were applied.[30]

Following the release of the Final Report the BCUC responded to additional questions from the BC government which clarified that:

  • Site C sunk and termination costs were correctly treated in the rate impact analysis (sunk costs were excluded; Site C termination costs were added to the cost of the alternative portfolio); [31]
  • The same financing cost assumption was used for Site C and wind/geothermal investments in order to ensure the review was agnostic regarding ownership structure;
  • Demand-side management costs were included in the alternative portfolio at their cost to the utility, as these would be the costs incurred by BC Hydro;
  • The period used to recover Site C sunk costs from customers if the project was terminated would be subject to BCUC approval. While no determination as to the appropriate period was made, a 30-year period was assumed for the rate impact analysis with sensitivity analysis on 10- and 70-year amortization periods; and
  • The BCUC considered electrification in arriving at its assessment that it would be more appropriate to use BC Hydro’s low load forecast in its economic analysis. The BCUC also considered recent developments in the industrial sectors, accuracy of historical load forecasts, GDP and other forecast drivers, price elasticity assumptions, future rate increases, potential disrupting trends and historical flattening electricity demand.[32]

Agricultural land impacts

Annual flooding has deposited rich sediments along the low bank portions of the Peace River. The creation of the Williston Lake reservoir has improved agricultural use on the former floodplain. Since 1967, the annual spring flood measured at Hudson's Hope has been reduced by two-thirds, along with a reduction in ice jams and ice scouring above the riverbank.[33] The Site C project will result in the largest exclusion of land in the 40-year history of BC's Agricultural Land Reserve (ALR). Of the land to be flooded, there are 2,601 hectares (6,430 acres) of Class 2 ALR land within the project activity zone. Permanent losses are estimated at 541 ha (1,340 acres) of currently cultivated land and 1,183 ha (2,920 acres) of land under grazing licence or lease areas. In all, 2,775 ha (6,860 acres) of land will be removed from the ALR for the project. The Joint Review Panel accepted BC Hydro's assessment that "production from the Peace River bottom lands is small and is certainly not important in the context of B.C." The Panel's assessment of earning potential in the next several decades led them to conclude: "The highest and best use of the Peace River valley would appear to be as a reservoir."[14]

Professional agrologist Wendy Holm, past president of the B.C. Institute of Agrologists, noted that flooding agricultural land in the Peace River valley is a bad idea, because it is "the only large tract of land for future horticultural expansion in the province." She notes that much of B.C.'s produce is imported from California, and growing food locally would increase food security for the province.[34]

According to David Suzuki, flooding valuable farmland to build the dam will undermine Canada's international commitments under the Paris Agreement. Suzuki considers the farmland essential to reduce B.C.'s dependence on imported foods and minimize the carbon fuels needed to transport those foods: "It seems to me crazy to put farmland in the north underwater," Suzuki said. "We live in a food chain now in which food grows on average 3,000 kilometres from where it's consumed. The transport of all that food is dependent on fossil fuels. Food has got to be grown much closer to where it's going to be consumed."[35]

Advantages

In April 2015, the federal and provincial governments named a Joint Review Panel to hold a public hearing on Site C.[36]

In addition to a long list of recommended changes, their assessment stated: "Despite high initial costs, and some uncertainty about when the power would be needed, the Project would provide a large and long-term increment of firm energy and capacity at a price that would benefit future generations. It would do this in a way that would produce a vastly smaller burden of greenhouse gases than any alternative save nuclear power, which B.C. has prohibited."[37] At the time the report was released, the panel added, "Site C would be the least expensive of the alternatives, and its cost advantages would increase with the passing decades as inflation makes alternatives more costly."[38]

In reference to the Paris climate accord, Site C is predicted to prevent approximately 30 to 70 million tonnes of carbon dioxide from being generated in the atmosphere.[39]

Ottawa has discussed a new electricity inter-tie to move Site C power between BC and Alberta. Justin Trudeau commented "I think anything we can work together inter-provincially or nationally [to get] emissions down, emphasizing hydroelectricity, creating opportunities to get off coal, to get off natural gas, where possible, is good for the country. It’s good for our emissions profile; it’s good for the economy we need to build," [40]

Costs to Indigenous Peoples

Northeastern BC Indigenous peoples have already had their rights undermined by other resource development projects, like the WAC Bennett Dam which is on the same river as Site C. BC Hydro, the public utility which built and operates the Bennett dam, opened a public display at the dam itself that acknowledged the harm done to the Tsay Keh Dene and Kwadacha First Nations. Speaking at the opening of the exhibit, a BC Hydro spokesperson said that the utility "deeply regrets those impacts and we commit that we will not repeat the mistakes of the past".[41] The government failed to give proper consideration to Canada's legal obligation to protect Indigenous rights. It also failed to examine the impact of an influx of temporary workers on the safety of women, especially Indigenous women. The risk of serious harm to the rights of Indigenous peoples requires that large-scale resource development proceed only with their free, prior and informed consent.

First Nations have identified hundreds of sacred sites or areas with cultural or historic significance in the planned Site C flood zone.[42] The Indigenous peoples of the area use the valley to hunt, fish trap, and gather berries as well as conduct ceremonies and harvest wild foods. The valley is prime habitat for moose, which is a food source they rely on, and other animals like the bear and eagle. The dam could also harm an already threatened fish species, the bull trout. The flooding of the valley may poison the fish with methylmercury for 20–30 years.[43]

Resource extraction has led to rapid population growth in the region. As a result of road construction and logging, non-Indigenous fisherman and hunters now have access to dwindling harvests. Just over 110 square km is recognized as reserve lands and this is not enough to sustain First Nations cultures and traditions.[44] Indigenous peoples have ongoing rights to harvest foods and practice their customs throughout their broader territory but because of intensive resource development there are fewer and fewer places left where this is possible. The Peace River Valley falls within the bounds of Treaty 8, which recognizes First Nations rights to hunt, trap, and fish throughout the region. Activist Helen Knott has said that if the valley is flooded then the promise of that treaty will be violated.


Alternatives

Electricity conservation is the least-cost alternative. BC Hydro achieved savings at $20/MWh, while the estimated savings were at $30/MWh. Columbia Treaty and non-treaty power now sold to the US, is available at approximately $30/MWh, equivalent to Site C quantities. BC Hydro determined in the 2013 Integrated Resource Plan, DSM 5, that more than double the amount of power from Site C could be obtained from conservation at up to $45/MWh.

In 2017, Alberta received quotations for 600 MW of wind power at $37/MWh.

When BC Hydro buys power from independent power producers they set a price as low as $76.20 per megawatt hour for intermittent power from wind farms, and as high as $133.80 for firm hydro power. The average price paid, as of 2010, was $100 per megawatt hour.[45] Site C is expected to cost $83 per megawatt hour for firm hydro power.[46]

British Columbia has committed to reducing greenhouse gases to 33 per cent below 2007 levels by 2020; however, the province is far short of that goal, only achieving a 6.5% reduction as of 2015.[47] Although the Site C dam is expected to have a large initial electricity surplus, the province has proposed to sell this power rather than choosing to reduce fossil fuel consumption in the province.[48][40]

See also

References

  1. "Backgrounder: About Site C" (PDF). BC Hydro. Archived from the original (PDF) on 23 June 2016. Retrieved 4 February 2016.
  2. "Province announces Site C Clean Energy Project". BC Hydro. 19 April 2010. Retrieved 26 April 2010.
  3. "Site C Backgrounder" (PDF). BC Hydro. 23 June 2016. Archived from the original (PDF) on 23 June 2016. Retrieved 29 April 2018.
  4. Gillis, Damien (22 April 2015). "Landowners launch Site C Dam court challenge, First Nations next". Common Sense Canadian. Retrieved 26 June 2015.
  5. "Federal Court of Appeal dismisses First Nations' challenge of B.C.'s Site C dam". The Globe and Mail. Retrieved 21 April 2017.
  6. Site C: Statement by Concerned Scholars, Program of Water Governance, University of British Columbia, Retrieved: 2016-06-22
  7. Cheadle, Bruce (24 May 2016). "Royal Society of Canada, academics, call Site C dam a test for Trudeau Liberals". The Canadian Press. CTV News. Retrieved 22 June 2016.
  8. McCarthy, Shawn (24 May 2016). "Ottawa pushes ahead with Site C dam amid opposition from academics". The Globe and Mail. Retrieved 22 June 2016.
  9. McElroy, Justin (11 December 2017). "B.C. government to go ahead with Site C hydroelectric dam project". CBC News. Retrieved 11 December 2017.
  10. The Times Colonist newspaper 7 October 2016 pg a15
  11. H, M. "BC Hydro Energy Project Certificate Application for Site C". www.ordersdecisions.bcuc.com. Retrieved 7 July 2016.
  12. "Independent Power Producer (IPP) Projects in British Columbia" (PDF). West Coast Environmental Law. May 2009. Retrieved 11 June 2017.
  13. "Clean Energy Act". www.bclaws.ca. Retrieved 7 July 2016.
  14. Swain, Harry; Beaudet, Jocelyne; Mattison, James (May 2014), Site C Clean Energy Project (PDF), Minister of the Environment, Government of Canada and Minister of Environment, Government of British Columbia, retrieved 11 July 2016
  15. "Site C not the best choice for B.C.'s energy needs, report author says".
  16. "Notice of Site C Construction Activities" (PDF) (Press release). BC Hydro. 8 July 2015. Retrieved 17 July 2016.
  17. Burrows, Matthew (22 April 2010). "Natives plan to fight Site C dam planned for Peace River". The Georgia Straight. Retrieved 26 April 2010.
  18. McElroy, Justin (16 December 2014). "Everything you need to know about the Site C dam". Global News. British Columbia. Retrieved 22 June 2016.
  19. "Tab for Site C dam could hit $6.6 billion". Vancouver Sun. 5 December 2007. Retrieved 2 April 2011.
  20. "Frequently Asked Questions". Site C Clean Energy Project. BC Hydro. Retrieved 25 June 2016.
  21. Garstin, Michaela (26 May 2011). "Total projected cost of Site C dam to be $7.9 billion". Northeast News. Fort St. John, British Columbia. Retrieved 11 August 2011.
  22. Bennett, Nelson (1 December 2015). "Editorial: Cost uncertainty a Site C certainty | Mining & Energy | Business in Vancouver". Biv.com. Retrieved 11 June 2017.
  23. "Site C Construction Review" (PDF). Deloitte. 9 September 2017. Retrieved 29 November 2017.
  24. Gilchrist, Emma (5 August 2015). "EXCLUSIVE: Site C Dam 'Devastating' for British Columbians, Says Former CEO of BC Hydro". DeSmogCanada. Victoria, British Columbia. Retrieved 17 July 2016.
  25. "Opinion: Site C: Truly awful economics". 16 June 2016. Retrieved 25 June 2016.
  26. "Q&A: Fourteen questions for BC Hydro CEO Jessica McDonald". Alaskahighwaynews.ca. 22 January 2016. Retrieved 11 June 2017.
  27. Wakefield, Jonny. "Court dismisses Site C First Nations' legal challenge". Dawson Creek Mirror. Retrieved 21 April 2017.
  28. Over 200 leading scholars call on government to suspend Site C dam
  29. BCUC letter to the Deputy Minister of Energy, Mines and Petroleum Resources Respecting the Site C Inquiry, 23 November 2017, page 1. Report Errata was issued on 16 November 2017 to correct two math related errors, however the changes to the final analysis was not material and did not affect the BCUC’s overall findings.
  30. BCUC letter to the Deputy Minister of Energy, Mines and Petroleum Resources Respecting the Site C Inquiry, 23 November 2017, page 2; Site C Inquiry Report, Executive Summary, page 10
  31. BCUC letter to the Deputy Minister of Energy, Mines and Petroleum Resources Respecting the Site C Inquiry, 23 November 2017, pp. 4, 5
  32. BCUC letter to the Deputy Minister of Energy, Mines and Petroleum Resources Respecting the Site C Inquiry, 23 November 2017, pp. 18-25
  33. Church, Michael (14 October 2014). The Regulation of Peace River: A Case Study for River Management - Michael Church - Google Books. ISBN 9781118906163. Retrieved 11 June 2017.
  34. Holm, Wendy (2 July 2016). "Why all the fuss over the Site C dam?". The Georgia Straight. Vancouver, British Columbia. Retrieved 17 July 2016.
  35. Suzuki, David (2 July 2016). "Site C Is a Climate-Change Disaster, Says Suzuki". The Tyee. Vancouver, British Columbia. Retrieved 17 July 2016.
  36. Hume, Mark (20 April 2015). "Lawyer argues in B.C. Supreme Court that Site C decision was illegal". The Globe and Mail. Retrieved 11 June 2017.
  37. "Site C Clean Energy Project Joint Review Panel Report" (PDF). Canadian Environmental Assessment Agency. Retrieved 11 June 2017.
  38. Mike Laanela (9 May 2014). "Site C dam review says benefits outweigh costs - British Columbia - CBC News". Cbc.ca. Retrieved 11 June 2017.
  39. https://vancouversun.com/technology/opinion+site+clean+energy+advantage/11557709/story.html
  40. Peter O'Neil (20 June 2016). "Justin Trudeau 'open' to $1-billion B.C. power line into Alberta". Vancouver Sun. Retrieved 11 June 2017.CS1 maint: multiple names: authors list (link)
  41. Jonny Wake eld. "B.C. Hydro acknowledges W.A.C. Bennett dam’s dark side." Dawson Creek Mirror. 10 June 2016.
  42. "The Point of No Return." Amnesty International, 2016, p. 5., www.amnesty.ca/sites/amnesty/files/Canada Site C Report.pdf.
  43. "The Point of No Return." Amnesty International, 2016, p. 9., www.amnesty.ca/sites/amnesty/files/Canada Site C Report.pdf.
  44. "The Point of No Return." Amnesty International, 2016, p. 8., www.amnesty.ca/sites/amnesty/files/Canada Site C Report.pdf.
  45. Simpson, Scott (4 August 2010). "Hydro paying average $100 per megawatt hour for new IPP power". Vancouver Sun. Retrieved 17 July 2016.
  46. "BC Hydro responds to environmental approval of Site C". Bchydro.com. 14 October 2014. Retrieved 11 June 2017.
  47. Kazi Stastna (14 April 2015). "How Canada's provinces are tackling greenhouse gas emissions - Canada - CBC News". cbc.ca. Retrieved 11 June 2017.
  48. Harry Swain (16 June 2016). "Opinion: Site C: Truly awful economics". Vancouver Sun. Retrieved 11 June 2017.

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.