Talin Power Plant
The Talin Power Plant (Chinese: 大林發電廠; pinyin: Dàlín Fādiànchǎng) or Dalin Power Plant is a mix-generation power plant in Siaogang District, Kaohsiung, Taiwan.[1]
Talin Power Plant | |
---|---|
Official name | 大林發電廠 |
Country | Republic of China |
Location | Siaogang, Kaohsiung, Taiwan |
Coordinates | 22°32′10″N 120°20′8″E |
Status | Operational |
Construction began | 1967 |
Commission date | 1969 2017 (1 X 800 MW unit) |
Owner(s) | Taipower |
Operator(s) | Taipower |
Thermal power station | |
Primary fuel | Coal, oil, natural gas |
Power generation | |
Units operational | 1 X 800 MW (coal) 2 X 300 MW (coal) 2 X 375 MW (coal) 500 MW (coal) 550 MW (LNG and oil) |
Make and model | Mitsubishi Heavy Industries General Electric |
Nameplate capacity | 2,400 MW |
External links | |
Commons | Related media on Commons |
Fuel supply
The plant receives its coal supply for the fuel from Mainland China (48%), Indonesia (37%) and Australia (13%) to the adjacent Port of Kaohsiung and by conveyor to the plant from the port.
Future expansions
The plant generation units will be replaced by two 800 MW ultra supercritical units from the current existing low-efficiency units. The construction permit was given on 25 October 2011 by the Ministry of Economic Affairs and scheduled for commercial operation on 1 July 2016 and 1 July 2017 respectively.[2][3]
Events
29 May 2016
Two workers killed and fiver others injured when the scaffolding used by them for work collapsed.[4]
19 October 2016
One generator of the plant tripped at 7:32 a.m. and was rectified four hours later.[5]
8 August 2017
The ignition of the first stage of ultra supercritical steam generator at the plant of 200 MW capacity in stages until it reaches its total capacity of 800 MW in the coming weeks.[6]
July 2018
The number one generator of the plant experienced mechanical failure on 28 July 2018. Inspection was carried out two days later on 30 July 2018.[7]
Awards
On 8 November 2010, the power plant won the outstanding award at the 23rd National QCC Competition, organized by Industrial Development Bureau of the Ministry of Economic Affairs.[8]
Transportation
The power plant is accessible South West from Siaogang Station of Kaohsiung MRT.
References
- "VFDS, Video Fire Detection System-case studies". Gkbsecurity.com. Retrieved 2014-05-01.
- "http://www.taipower.com.tw/e_content/content/construction/construction01-1.aspx?sid=2". Archived from the original on 2014-05-08. External link in
|title=
(help) - "Environmentalists protest Taipower Dalin plant expansion plan".
- "2 workers killed, 5 injured after scaffold collapses - Society - FOCUS TAIWAN - CNA ENGLISH NEWS".
- http://focustaiwan.tw/news/aeco/201610190009.aspx
- Liao, Yu-yang; Hsu, Elizabeth (7 August 2017). "New generator expected to help ease power shortage". Focus Taiwan. Retrieved 8 August 2017.
- Kuo, Hsing-i; Hsu, Hsiao-ling (30 July 2018). "Coal-powered generator at power plant malfunctions; power supply safe". Focus Taiwan. Retrieved 30 July 2018.
- "Taiwan power company-Taipower Events". taipower.com.tw. Archived from the original on 2014-05-17.