The Beijing–Hong Kong high-speed train (simplified Chinese: 京港高速动车组列车; traditional Chinese: 京港高速動車組列車) is a high-speed train service operated by China Railway Guangzhou Group (CR Guangzhou) on Beijing–Guangzhou–Shenzhen–Hong Kong HSR in China. Operated with G79/80 train numbers between Beijing West and Hong Kong West Kowloon on a daily basis, it is currently the fastest train service and the only high-speed train service between Beijing and Hong Kong, with an approximate travelling time of 9 hours.[1]

Beijing–Hong Kong high-speed train
京港高速动车组列车
京港高速動車組列車
A CR400AF-A EMU on G80 service stopping at Platform 12 of Beijing West Railway Station
Overview
Service typeG-series trains
StatusOperational
LocaleChina
PredecessorG79/82
First service
  • 26 December 2012 (Beijing West ↔ Guangzhou South)
  • 28 December 2013 (Beijing West ↔ Shenzhen North)
  • 5 January 2017 (Beijing West ↔ Futian)
  • 23 September 2018 (Beijing West ↔ Hong Kong West Kowloon)
Current operator(s) CR Guangzhou
Route
StartBeijing West
Stops
EndHong Kong West Kowloon
Distance travelled2,439 kilometres (1,516 mi)
Average journey time
  • 8h 58m (G79)
  • 8h 56m (G80)
Service frequencyDaily
Train number(s)
  • G79 (Beijing West → Hong Kong West Kowloon)
  • G80 (Hong Kong West Kowloon → Beijing West)
Line(s) usedBeijing–Guangzhou–Shenzhen–Hong Kong HSR
On-board services
Class(es)
  • Business seat
  • First class seat
  • Second class seat
Catering facilities
  • Dining car
  • Trolley refreshment service
Technical
Rolling stockCR400AF-A
Track gauge1,435 mm (4 ft 8 12 in)
Operating speed350 km/h
Track owner(s)China Railway

History

The G79/80 service dates back to 26 December 2012, when the BeijingZhengzhou section of the Beijing–Guangzhou–Shenzhen–Hong Kong HSR was opened. At its opening, the service was between Beijing West and Guangzhou South under the numbers G79/82. Later on 28 December 2013, the southern terminus of the service was extended to Shenzhen North and the number of the Shenzhen-bound service was changed from G82 to G80.[2]

On 5 January 2017, the service was extended to Futian.[3]

With the inauguration of the Guangzhou–Shenzhen–Hong Kong XRL Hong Kong section on 23 September 2018, the southern terminus of the service was again extended to Hong Kong West Kowloon.[4][5]

On 30 January 2020 the service was suspended due to the COVID-19 pandemic.[6]

On 28 March 2020, the service has restored between Beijing West and Shenzhen North, but service to West Kowloon station is still suspended.

Operations

The service operates on a daily basis under the following timetable:[1][7][8]

Effective from 23 September 2018
G79 Stops G80
ArriveDepartArriveDepart
10:00Beijing West17:01
11:0711:09Shijiazhuang15:5015:54
12:3112:34Zhengzhou East14:2514:28
14:1714:20Wuhan12:3812:41
15:3815:41Changsha South11:1711:20
18:0118:06Guangzhou South08:5609:00
18:3518:39Shenzhen North08:2408:27
18:58Hong Kong West Kowloon08:05

Train formation

The service is operated by 16-car CR400AF-A trainsets with the formation shown below. Car 3-14 are for second class seats with 3+2 seating. The dining car is located in Car 9 and wheelchair space is provided on Car 8. Car 2 and 15 are first class car with 2+2 seating. Car 1 is for business seats only and Car 16 is a hybrid of first class seats and business seats.[9]

Car No. 123-78910-141516
Type SW
Business
ZY
First class
ZE
Second class
ZE
Second class
ZEC
Second class/dining car
ZE
Second class
ZY
First class
ZYS
Business/first class
Seating capacity 1760907548906028 + 5

Previously used rolling stocks

References

  1. "Long-haul train schedule" (PDF). MTR. Retrieved 2018-09-26.
  2. "郑州铁路局12月28日实行新运行图 新增旅客列车11对" (in Chinese). Retrieved 2018-09-26.
  3. "福田高铁直达全国30市县" (in Chinese). 2017-01-06. Retrieved 2018-09-26.
  4. "Hong Kong Launches First High Speed Rail Service". finance.yahoo.com. Retrieved 2018-09-26.
  5. "北京开往香港首趟高铁满员启程" (in Chinese). Retrieved 2018-09-26.
  6. "High Speed Rail train service has been suspended and Hong Kong West Kowloon Station closed since 30 January until further notice".
  7. "G79时刻表" (in Chinese). Retrieved 2018-09-26.
  8. "G80时刻表" (in Chinese). Retrieved 2018-09-26.
  9. "CR400AF-A/B动车组". www.china-emu.cn (in Chinese). Retrieved 2018-09-27.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.