The Canal Latéral à la Loire was constructed between 1827 and 1838 to connect the Canal de Briare at Briare and the Canal du Centre at Digoin, a distance of 196 kilometres (122 mi). It replaced the use of the river Loire, which was unreliable during winter floods and summer droughts. Aqueducts were used to cross the Allier at Le Guétin (in the commune of Cuffy) and the Loire at Digoin. However, because of the extreme length required, an aqueduct was not built to cross the Loire at Briare until 1896, when the Briare aqueduct was constructed.

Canal latéral à la Loire
The port on the canal at Marseilles-lès-Aubigny
Specifications
Length196.1 km (121.9 mi) [1]
Locks37 [1] or 38 [2]
History
Construction began1827
Date completed1838
Geography
Start pointCanal de Briare at Briare
End pointCanal du Centre at Digoin [2]
Beginning coordinates47.63197°N 2.73671°E / 47.63197; 2.73671 at aqueduct crossing Loire in Briare
Ending coordinates46.47756°N 3.98053°E / 46.47756; 3.98053 at aqueduct crossing Loire in Digoin
Branch(es)Embranchement de Châtillon
Connects toCanal de Briare, Canal du Centre
Canal latéral à la Loire and its connections

History

By the late 18th century with the completion of the Canal du Centre, the Bourbonnais route from the Seine to the Saône was substantially the same as at present, except for the use of the navigable Loire between Briare and Digoin. The introduction of steam haulage and dredging failed to produce the reliability of the canals, so it was in 1822 that the order to build was finally given to the Compagnie des Quatre Canaux. Although the original intention was to place the canal on the right bank, the towns of Nevers, la Charité and Cosne had no room for a canal and eventually construction started in 1827 on a canal on the left bank. Two massive stone aqueducts were built at Digoin and at Guétin to avoid level crossings of rivers with length 243m and 470m respectively, but this was not possible at Briare because of the danger of blocking the river during flood periods.

With the adoption of the Freycinet gauge in 1879, and the upgrading of the canal system, the frequent delays of several days to cross the Loire at Briare became intolerable. The Briare aqueduct was built over the Loire in Briare between 1890 and 1896 by the engineer Abel Mazoyer to make a connection with the Canal de Briare four locks up from its initial entrance. The Briare aqueduct stands on fourteen piers. These support a single metal beam carrying a trough with more than 13,000 tonnes of water, 2.2 metres deep. The width of the aqueduct, towpaths included, is 11.5 meters and its length is 662.7 meters. Eight sluices make it possible to empty the aqueduct in the event of severe freezing.

En Route

Cruise traffic in Briare
Canal latéral à la Loire route map

See also

References

  1. McKnight, Hugh (2005). Cruising French Waterways, 4th Edition. Sheridan House. pp. 172–177. ISBN 978-1-57409-087-1.
  2. Jefferson, David (2009). Through the French Canals. Adlard Coles Nautical. pp. 127–129. ISBN 978-1-4081-0381-4.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.