Choa Chu Kang West MRT station
Choa Chu Kang West MRT station is a proposed Mass Rapid Transit (MRT) station on the Jurong Region Line in Choa Chu Kang, Singapore. There will be two station names in the JRL naming exercise - Brickland and Choa Chu Kang West.[1][2][3]
JS2
Choa Chu Kang West 蔡厝港西 சுவா சூ காங் வெஸ்ட் Choa Chu Kang West | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Mass Rapid Transit (MRT) station | ||||||||||||||||
Owned by | Land Transport Authority | |||||||||||||||
Line(s) | ||||||||||||||||
Platforms | Island | |||||||||||||||
Tracks | 2 | |||||||||||||||
Construction | ||||||||||||||||
Structure type | Elevated | |||||||||||||||
Platform levels | 1 | |||||||||||||||
Bicycle facilities | Yes | |||||||||||||||
Disabled access | Yes | |||||||||||||||
History | ||||||||||||||||
Opening | 2026 | |||||||||||||||
Electrified | Yes | |||||||||||||||
Services | ||||||||||||||||
| ||||||||||||||||
Location | ||||||||||||||||
Choa Chu Kang West Choa Chu Kang West station in Singapore |
History
On 9 May 2018, LTA announced that Choa Chu Kang West station would be part of the proposed Jurong Region line (JRL). The station will be constructed as part of Phase 1, JRL (West), consisting of 10 stations between Choa Chu Kang, Boon Lay and Tawas, and is expected to be completed in 2026.[4]
Contract J102 for the design and construction of Choa Chu Kang West Station and associated viaducts was awarded to Shanghai Tunnel Engineering Co. (Singapore) Pte Ltd at a sum of S$465.2 million. Construction will start in 2020, with completion in 2026.[5] Contract J102 also includes the design and construction of Choa Chu Kang station and Tengah station, and associated viaducts and A&A works to the existing Choa Chu Kang Station complex.[6]
Location
The station will be straddled over the existing Choa Chu Kang Avenue 3, just east of the junction with Choa Chu Kang Avenue 1. It is located within the Choa Chu Kang planning area between the Keat Hong and Peng Siang Subzones,[7] nested within an existing housing estate, near to Sunshine Place.
Access to the station will be via 2 exits, 1 of each side of Choa Chu Kang Avenue 3.[8]
References
- "Jurong Region Line to serve NTU, Tengah estate, Jurong Industrial Estate - CNA". 2019-09-21. Archived from the original on 2019-09-21. Retrieved 2019-09-21.
- "Residents and students welcome Jurong Region Line but find it confusing". 2019-09-21. Archived from the original on 2019-09-21. Retrieved 2019-09-21.
- "Jurong Region Line". 2019-09-21. Archived from the original on 2019-09-21. Retrieved 2019-09-21.
- "Joint News Release by the Land Transport Authority (LTA) & SLA - Jurong Region Line: Enhancing Connectivity in the West | Press Room | Land Transport Authority". 2019-09-21. Archived from the original on 2019-09-21. Retrieved 2019-09-21.
- "LTA Awards Civil Contracts to Construct Five Stations for the Jurong Region Line | Press Room | Land Transport Authority". 2019-09-21. Archived from the original on 2019-09-21. Retrieved 2019-09-21.
- "Tender information | Land Transport Authority". 2019-09-21. Archived from the original on 2019-09-21. Retrieved 2019-09-21.
- "Singapore's Jurong West Planning Area". Key Location. Retrieved 2019-09-21.
- "Jurong Region Line". 2019-09-21. Archived from the original on 2019-09-21. Retrieved 2019-09-21.