Honolulu Rail Transit
The Honolulu Rail Transit Project (also known as the Honolulu High-Capacity Transit Corridor Project) is a light metro system under construction in Honolulu County, Oahu, Hawaii, U.S. The mostly-elevated system features design elements from both heavy rail systems and light metros,[7] with a commuter rail-like design incorporated into trains and suburban stations. It will become the first large-scale publicly run metro system in the United States to feature platform screen doors and driverless trainsets.[8] The first phase of the project, linking East Kapolei on the ʻEwa Plain and Aloha Stadium, is scheduled to open in late 2021. Its second phase continuing the line across urban Honolulu to Ala Moana Center is due to open in December 2026.[9]
Honolulu Rail Transit Project | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project construction in Waipahu, July 2015 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Overview | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Status | Under construction | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner | HART | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | Honolulu County, Hawaii | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Termini | East Kapolei Ala Moana Center | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stations | 21 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Website | www | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Type | Light metro[1][2][3] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Services | 1 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Rolling stock | Hitachi Rail Italy (Driverless Metro) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
History | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Opened | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line length | 20 mi (32 km) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Number of tracks | 2 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Character | Almost entirely elevated | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 4 ft 8 1⁄2 in (1,435 mm) standard gauge | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrification | 750 V DC third rail[6] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
For more than 20 years, debate over the development of a rail system in Honolulu has been a major point of contention in local politics, especially leading into the 2008, 2012, and 2016 election cycles. Proponents of the system say it will alleviate worsening traffic congestion, already among the worst in the United States, despite table 3-12 in the final Environmental Impact Statement indicating a mere 1.7% improvement by 2030 vs the no build option.[10] [11]They assert that the urban agglomeration in south Oahu is ideally suited to rail as it is constrained by mountains to a narrow strip along the coast, which will be well served by a single rail line. On the opposite side, freeway advocate Panos Prevedouros questions its cost effectiveness compared to alternatives[10] and claims that it will have marginal impact on future congestion and that new roads will therefore still be required.[12] The rest of the rail opponents mostly object to its cost, and for many to their paying for it without it serving their own neighborhoods.
The project is financed by a surcharge on local taxes as well as a $1.55 billion grant from the Federal Transit Administration (FTA). After major cost overruns, the tax surcharges were extended in 2016 by five years to raise another $1.2 billion; however that additional funding was only sufficient for construction out to Middle Street in Kalihi. The FTA stated that its contribution is contingent to completion of the line all the way to Ala Moana Center and will not be increased.[13] After much wrangling, the state legislature in 2017 approved $2.4 billion in additional taxes to allow the city to complete the project according to the original plan.[14]
Construction of the final 4.3-mile (6.9 km) section through downtown Honolulu, which is expected to be the most difficult to build, is just starting. The contractor selection process for this section was restarted in September 2017 and is expected to take eighteen months.[15] The first major contract for that section, a $400 million contract to relocate utilities to clear the path of the line, was awarded in May 2018.[16]
The final cost has grown from preliminary projections of $4 billion in 2006[17] to between $9 billion[18] and $10 billion by 2017.[19] Critics have called for a "forensic audit" to establish the cause of the increase.[20][21][22] The tax increase legislation passed in 2017 also requires the State auditor carry out an audit of the project's accounts[23] and to consider alternatives for completing the system.[24]
History
Plans for a mass transit line to connect Honolulu's urban center with outlying areas began in the 1960s,[25] but funding was not approved until 2005.[26] The controversy over the rail line was the dominant issue for local politics leading into the 2008 Honolulu elections,[27] and culminated in a city charter amendment which left the final decision to a direct vote of the citizens of Oahu.[28] Construction of the rail line was approved with 53% of voters in favor,[29] and ground broke on project construction on February 22, 2011.[30][31]
Previous projects
For more than 50 years, some Honolulu politicians have attempted to construct a rail transit line. In 1966, then-mayor Neal S. Blaisdell suggested a rail line as a solution to alleviate traffic problems in Honolulu, stating, "Taken in the mass, the automobile is a noxious mechanism whose destiny in workaday urban use is to frustrate man and make dead certain that he approaches his daily occupation unhappy and inefficient."[25]
Frank Fasi was elected to office in 1968, and started planning studies for a rail project,[32] named Honolulu Area Rapid Transit (HART), in 1977.[33] After Fasi lost the 1980 reelection to Eileen Anderson, President Ronald Reagan cut off funding for all upcoming mass transit projects, which led Anderson to cancel HART in 1981.[34][35][36] Fasi defeated Anderson in their 1984 rematch and restarted the HART project in 1986,[37] but this second effort was stopped in a 1992 vote by the Honolulu City Council against the necessary tax increase.[26][38]
Fasi resigned in 1994 to run for governor, with Jeremy Harris winning the special election to replace him. Harris unsuccessfully pursued a bus rapid transit project as an interim solution until he left office in 2004.[39] His successor, Mufi Hannemann, began the Honolulu High-Capacity Transit Corridor Project (HHCTCP), the island's fourth attempt to build a mass transit system operating in a dedicated right-of-way.
Studies
The City and County of Honolulu Department of Transportation Services released the first formal study related to the HHCTCP on November 1, 2006, the Alternatives Analysis Report. The report compared the cost and benefits of a "fixed guideway system", along with three alternatives. The first expanded the existing bus system to match population growth. A second option called for a further expansion to the bus system, with improvements to existing roads. The third alternative proposed a two-lane flyover above the H-1 freeway between Pearl City and Honolulu International Airport, continuing over Nimitz Highway, and into downtown Honolulu. The report recommended construction of the fixed guideway, and is considered the city's official justification for building a rail line.[40][41]
A second planning document, the Draft Environmental Impact Statement (DEIS), studied possible natural and social impacts of the construction and operation of the HHCTCP. The DEIS was completed and cleared for public release by the Federal Transit Administration (FTA) on October 29, 2008. After minor changes were made to comply with state law, the document was distributed via the city's official project website four days later. The DEIS indicated that impacts of the rail project would include land acquisition from private owners on the route, displacement of residents and businesses, aesthetic concerns related to the elevated guideway, and noise from passing trains.[42]
The city was criticized for timing the release only two days before the 2008 general election. City Councilmember Ann Kobayashi, running as a mayoral candidate against incumbent Hannemann, suggested that the city deliberately withheld key information to early voters who had already cast their ballots for the mayoral candidates, and a city charter amendment related to the project.[43][44] The anti-rail advocacy group Stop Rail Now criticized the report for not further discussing bus rapid transit and toll lanes, options studied earlier by the city in its Alternatives Analysis.[45][46]
The third and final official planning document, the Final Environmental Impact Statement (FEIS), was approved and cleared for public release by the FTA on June 14, 2010. The FEIS addresses and incorporates public comments received regarding the DEIS.[47] The FTA subsequently declared the environmental review process complete in a record of decision issued on January 18, 2011.[48]
Impact on Honolulu mayoral elections
The importance of the Honolulu High-Capacity Transit Corridor Project in the 2008 mayoral election led one observer to describe the vote as a "referendum on rail transit".[27] Two challengers emerged as rivals to incumbent Mufi Hannemann: City Councilmember Ann Kobayashi and University of Hawaii professor Panos D. Prevedouros. Kobayashi supported a "rubber-tired" mass transit system, as opposed to the conventional steel-wheel-on-steel-rail system chosen by the Hannemann administration. Prevedouros, on the other hand, opposed any type of mass transit project, favoring construction of a reversible tollway over the H-1, similar to the Managed Lane option which the Alternatives Analysis studied and rejected as unworkable, and reworking existing road systems to ease congestion.[49] No candidate won a majority of votes in the September 20 non-partisan primary, forcing a runoff between Hannemann and Kobayashi;[50] Hannemann successfully retained his post with 58% of the vote in the November 4 general election.[51]
On April 22, 2008, the Stop Rail Now advocacy group announced their intent to file a petition with the city to place a question on the 2008 ballot to create an ordinance that read: "Honolulu mass transit shall not include trains or rail".[52] Stop Rail Now attempted to submit the petition with 49,041 signatures to City Clerk Denise De Costa on August 5, but was initially denied after De Costa claimed the city charter did not allow the petition to be submitted less than 180 days before a general election, as the wording of the petition called for a special election.[53][54] Stop Rail Now filed a lawsuit to force the city to accept the petition, and the courts ruled in Stop Rail Now's favor on August 14.[55] Stop Rail Now's petition drive ultimately failed on September 4 when De Costa deemed only 35,056 of the signatures valid, well short of the 44,525 required.[56]
In response to the possibility that Stop Rail Now's petition would fail, the City Council had however voted on August 21 to place a proposed amendment to the city charter on the ballot, asking voters to decide the fate of the project.[57] Mayor Hannemann signed the proposal the following day.[58] The City Council's proposed amendment was not intended to have a direct legal effect on the city's ability to continue the project, but was meant as a means for Oahu residents to express their opinions on its construction.[28] The charter amendment was approved with 53% of votes cast in favor of rail and 47% against. Majorities of voters in Leeward and Central Oahu, the areas that will be served by the project, voted in favor of the amendment, while the majority of those living outside the project's scope in Windward Oahu and East Honolulu voted against it.[29] In mid-2010, Hannemann resigned as major to run for governor and Kirk Caldwell assumed the position of interim mayor.[59]
In the 2016 Honolulu mayoral elections the main three candidates again took opposing views on rail. Honolulu City Council Member Charles Djou, former mayor Peter Carlisle, and incumbent Kirk Caldwell all ran for mayor with the stated goal of finishing rail. However, Republican Djou ran on drastically cutting spending on rail by cutting funding on buying cars on the rail before its completion, and hiring mainland consultants.[60] Kirk Caldwell also stated that spending on rail should be cut, but instead by shortening the rail to end at Middle Street.[61] Carlisle was the only candidate in support of funding the full rail system and stated that rail has gone too far to be stopped.[62] Kirk Caldwell won the election, and promptly went on to adopt Carlisle's position that rail should be completed.
Delays and cost overruns
Construction on the HHCTCP rail line was originally scheduled to begin in December 2009 but did not occur on that date owing to delays in the project review process and delays in obtaining federal approval of the environmental impact statement.[63]
In January 2010, Republican Governor Linda Lingle publicly recommended that the city alter plans for the rail line after news reports on FTA documents where the federal agency raised issues over declining tax revenues in connection with a global economic recession,[64] and commissioned a study by the state to review the project's finances in March.[65] The state financial study, publicly released on December 2, 2010, indicated that the project would likely experience a $1.7 billion overrun above the $5.3 billion projected cost, and that collections from the General Excise Tax would be 30% below forecasts. Then Mayor Peter Carlisle (Democrat) dismissed the study as "damaged goods," and "a pre-determined anti-rail rant." He also pointed to several conclusions as "erroneous" and "inaccurate" before concluding that "spending a third of a million dollars for this shoddy, biased analysis is an appalling waste of our tax dollars."[66] Lingle's Democratic successor, Neil Abercrombie, publicly stated that the financial analysis would not affect his decision to approve or disapprove of the project, saying that the state's responsibility is limited to the environmental review process, and that decisions regarding the project's finances belong to the city and the FTA.[67] Governor Abercrombie subsequently approved the project's final environmental impact statement on December 16, 2010.[68] The Honolulu City Council held a hearing on January 12, 2011 about the state's financial review, but the hearing was not attended by any state officials, who had been invited to testify.[69]
On January 18, 2011, the FTA issued a "record of decision", indicating that the HHCTCP had met the requirements of its environmental review and that the city was allowed to begin construction work on the project.[48] The record of decision allowed the city to begin negotiating with owners of land that will be purchased for the project, to begin relocating utility lines to make way for construction of the line and stations, and to purchase rolling stock for the rail line.[70][71] A ground-breaking ceremony was held on February 22, 2011 in Kapolei, at the site of the future East Kapolei station along Kualakai Parkway.[30][31]
In March 2012, Dan Grabauskas was hired on a three year contract as CEO and Executive Director of HART.[72] In 2014 HART CEO Dan Grabauskas blamed lawsuits, launched in 2011, for some of the cost overruns after bids to construct the first nine stations exceeded the budget by $100 million. His claims were disputed by the plaintiffs in one of the cases who said HART could have put the stations out to tender and that HART had deliberately delayed the legal proceedings so a judgement would only be delivered after a significant proportion of the line had been completed.[73]
Testing and more delays
Interim service over the first ten miles of the line between East Kapolei and Aloha Stadium was scheduled to commence operations in October 2020. However, due to complications during the COVID-19 pandemic the start date was pushed back three months.[74][75] By November 2020, the opening had again slipped to late 2021 due to delays in testing equipment.[4]
Burial issues
Like most major infrastructure work in Hawaii, construction of the rail line is likely to uncover historic human remains, notably in its downtown Honolulu section. The Oahu Island Burial Council (part of the State Historic Preservation Division, within the State of Hawaii Department of Land and Natural Resources) refused to sign a programmatic agreement on October 21, 2009, over concerns about likely burial sites located along the line's proposed route over Halekauwila Street in Kakaʻako. Three construction projects in the area since 2002 have each encountered unforeseen human remains that led to delays, and archaeologist Thomas Dye stated, "The council is absolutely right that you should expect to find burials on Halekauwila Street".[76]
The Burial Council's core contention was the city's decision to conduct an archaeological survey of the rail line's route in phases, meaning construction on a majority of the line will be complete by the time the survey in the Kakaʻako area is performed, which in turn increases the likelihood that any remains discovered will be moved instead of being allowed to remain in situ.[77] In response to the Burial Council's concerns, the city agreed to begin conducting an archaeological survey of the area in 2010, two years earlier than originally planned.[76] The state Department of Land and Natural Resources later signed the city's programmatic agreement on January 15, 2011, over the continuing concerns of the Burial Council.[78]
The city's decision to conduct the archaeological survey in phases subsequently led to a lawsuit filed on February 1, 2011, by the Native Hawaiian Legal Corporation on behalf of cultural practitioner Paulette Kaleikini. The suit, which named both the city and the State of Hawaii as defendants, contended that state law requires the full length of the rail line to have an archaeological survey conducted before any construction takes place, and seeks to void the environmental impact statement and all construction permits issued for the project.[79] Kaleikini's lawyers filed on February 18 a request for an injunction to stop work on the project until the case is resolved.[31] The suit was initially dismissed on March 23, 2011, after Circuit Court Judge Gary Chang ruled that state and federal laws allow the archaeological surveys to be conducted in phases.[80] Kaleikini's lawyers subsequently appealed to the Hawaii Supreme Court, which heard oral arguments in the case on May 24, 2012.[81] The court ruled on August 24, 2012, that it agreed with plaintiff Kaleikini that the archaeological survey needed to be completed before construction could take place, and that the State Historic Preservation Division did not comply with state law when it approved the project. The case has now been remanded to Circuit Court.[82] On December 27, 2012, the United States District Court for the District of Hawaii granted the plaintiffs' injunction, and ordered that all construction-related activities in segment 4 of the archaeological survey be halted until compliance with the Hawaii Supreme Court decision made earlier this year is met. This ruling does not affect construction activities in the first three segments, nor does it affect construction planning, design, or engineering in segment 4, which is the final segment to be built. The Phase 4 area encompasses the downtown area and its immediate environs, including Chinatown, Mother Waldron Park, and Beretania Street. Judge Tashima, the only sitting judge on the case, ruled on condition of the injunction that the city is required to file periodic status updates on their compliance with the judgment. The injunction will then terminate 30 days after defendants file a notice of final compliance.[83]
Social impact
The development of this project has been a point of contention among environmental, indigenous, and residential interest groups, as the United States Department of Transportation is accountable for nationwide compliance with Title VI of the Civil Rights Act of 1964.[84] Specifically, residents of the North Shore, Wai‘anae Coast, and Central and East regions of Oahu, home to mostly middle and lower-class communities, but also those of mostly upper class Hawaii Kai and Windward Oahu, pay the higher excise tax without reaping the direct benefits of the Rail Transit project. Indigenous Hawaiians constitute large percentages of the communities scattered along the southwest coast of the island, where residents generally exist under the national poverty line, but the project may possibly serve wealthier, “local” Hawaiian residents while bypassing the poorer indigenous Hawaiian community.[85] Numerous studies have identified various benefits, including increased home values and increased median household income, that fall upon residences located near a rail transit station; public transit implementation thus constitutes a measure of public and private investment in a community.[86]
Financing
Initial General Excise Tax (GET) surcharge
After winning the 2004 election, Hannemann announced that construction of a rail line was an administration priority.[87] The following May and upon prompting by the city, the Hawaii State Legislature passed a bill (Act 247) to allow counties a one-half percent increase in the Hawaii General Excise Tax (GET), from 4% to 4.5%, to fund transportation projects. According to the bill, increased revenue would be delivered to counties implementing the raised tax to fund general public transportation infrastructure throughout Hawaii, and to pay for mass transit in the case of the City and County of Honolulu.[88][89] Money collected from the initial 4% GET would remain state revenue.
Republican governor Linda Lingle initially threatened to veto the bill, believing that money destined for county governments should be collected by the individual counties.[90][91] After compromising with legislative leaders and Mayor Hannemann, however, she allowed the bill to become law. On July 12, 2005, the bill was enacted as Act 247 of the Session Laws of Hawaii 2005, without the Governor's signature.[89][90][91][92] A month later, the Honolulu City Council authorized the one-half percent GET increase,[93] and Hannemann signed the measure into law on August 24.[94] Act 247 required Honolulu to use the funds only for the construction and operation of a mass transit system, and barred its use for public roads and other existing transit systems, such as TheBus. Since no other county authorized the excise tax increase before the deadline of December 31, 2005, the Hawaii GET remains at 4% for Hawaii's three other counties.[89][95] The increase went into effect on January 1, 2007, and was due to expire on December 31, 2022.[89]
The Legislature considered a bill in the 2009 legislative session that would have redirected income from the half-percent increase back to the state to offset a $1.8 billion projected shortfall in the following three fiscal years.[96][97][98][99] The bill was opposed by Mayor Hannemann and other city leaders who believed that redirecting the money would jeopardize federal funding for the project,[100] and was eventually dropped after U.S. Senator Daniel Inouye indicated to the Legislature that he shared the city's concerns.[101][102]
GET surchange extensions and "Hotel Tax" surcharge
In January 2016, the Council extended the GET for another five years to add $1.2 billion in funding to cover a budget blowout. The Council also required that the money raised by the extension go into a contingency fund and to pay for disability access to the system. HART was required to provide quarterly financial reports to the Council.[103]
On September 1, 2017 the Legislature, after meeting for a week in a special session on rail financing, approved further taxes to raise $2.4 billion for the project. The taxes include a further three-year extension to the 0.5 percent General Excise Tax surcharge, which will now expire in 2030, and a thirteen-year, 1.0 percent surcharge on the existing 9.25 percent statewide Transient Accommodation Tax (TAT) which is charged to tourists. Efforts to pass a funding bill in May 2017 had failed and the impetus for the special session was a FTA deadline of September 15 for a funding plan to cover the shortfall.[104] The bill also grants the state government oversight over the project including the appointment of two non-voting representatives on the HART board and calls for an audit of HART by the state auditor. It was signed into law by the governor on September 5.[23]
Federal Transit Administration's request for recovery plan
In mid 2016, the FTA requested that HART develop a "recovery plan" by August 7, 2016. Also in June a separate report by Jacobs Engineering, the project management contractor, said under a worst-case scenario the final cost would $10.79 billion.[105]
In January 2017, a group called "Salvage the Rail" published a plan, based on Option 2A from six alternatives proposed by the FTA to HART in 2016,[106] that would terminate the elevated section at Middle Street and run at street level to the terminus along a route one block inland from the HART plan. The system would need to be reconfigured to use new driver-operated low floor vehicles, lowering the platforms on the stations already constructed.[107][108] Proponents say it would save $3 billion and four years of construction, as well as avoid disturbing burial sites under the downtown area.
After a lodgement extension was granted by the FTA, HART submitted its recovery plan in April 2017 which concluded that completion of the original 21 station route was the only viable option. An alternative "Plan B" to build only 14 stations within the already funded $6.5 billion budget, was ruled out because of lower ridership, legal risks, insufficient contingency and other reasons. The new project cost was $8.165 billion with media reports indicating that after financing charges are included it could be over $10 billion. An updated schedule for opening said the section from East Kapolei to Aloha Stadium will open at the end of 2020 and operation of the full route by December 2025.[109][110]
In September 2017, HART submitted an updated recovery plan to the FTA with a new estimate price of $9.02 billion. The plan still includes $8.165 billion in construction costs, but has reduced financing costs of $858 million following state legislation granting both prolonged and new taxes to fund the project.[18] The State Auditor has been tasked to consider alternatives for completing the system, as part of its audit of HART.[24] As of January 2018 the FTA has not formally accepted the new recovery plan but has asked HART for more details including how it came up with its tax-revenue forecasts.[111]
In February 2019, the FTA served HART with two subpoenas. The first asked the agency to send investigators documents relating to its real estate acquisition program. HART said some of the documents show it overspent on relocating residents and businesses along the rail route, which may have cost up to $4 million.[112] The second sought the minutes from all board of directors meetings from 2011 through 2018, including the board-members’ private discussions in executive sessions.[113]
In September 2019, the FTA accepted the recovery plan.[114]
Route
The project constructs an almost entirely elevated rapid transit line from the eastern edge of Kapolei, near the University of Hawaii-West Oahu campus, to Ala Moana Center (East of Honolulu downtown). The line passes through communities along southern Oahu, via Honolulu International Airport and downtown Honolulu. It will have twenty-one stations and run from Kapolei to Honolulu, passing through Waipahu, Pearl City, Waimalu, Aiea, and Halawa. The only at-grade trackage is a 0.6-mile (0.97 km) section near Leeward Community College.[115]Originally, the line was to fork near Aloha Stadium into two routes, one passing further south via Honolulu International Airport, and the other through Salt Lake, before reuniting at Middle Street in Kalihi. The city council initially decided to build the Salt Lake route before the airport route, as a result of horse-trading with City Councilmember Romy Cachola, whose constituents included Salt Lake residents and whose vote was needed to pass the decision.[116][117] After the city charter amendment on rail transit passed, the City Council reconsidered the decision, and decided to re-route the rail line to pass by Pearl Harbor and the airport, without a Salt Lake alignment.[118][119] The airport route is 4% more expensive, but is expected to have significantly higher ridership since it will ferry workers to both the airport and the Pearl Harbor military base.
As of November 2016, the western portion of the line (East Kapolei – Aloha Stadium) was scheduled to open in late 2020, and the full line (East Kapolei – Ala Moana Center) is scheduled to open in late 2025.[120] The project is divided into four segments or sections, with overlapping construction periods and revenue service dates.[121]
Section name[121] | Length | Termini | Opening | Ref. | ||
---|---|---|---|---|---|---|
1 | West Oahu-Farrington | 6.9 miles (11.1 km) | East Kapolei | Pearl Highlands | 2021 (scheduled) | [122][123][124] [125][126][127] |
2 | Kamehameha Highway | 3.9 miles (6.3 km) | Pearl Highlands | Aloha Stadium | 2021 (scheduled) | [128][129][130] |
3 | Airport | 5.1 miles (8.2 km) | Aloha Stadium | Middle Street | 2022 (scheduled) | [131][132][133] |
4 | City Center | 4.1 miles (6.6 km) | Middle Street | Ala Moana Center | 2025 (scheduled) | [134] |
The following extension sections are not funded and have no scheduled completion date: | ||||||
West Kapolei extension | West Kapolei | East Kapolei | not funded | [135] | ||
UH Mānoa extension | Ala Moana Center or Iwilei | University of Hawaii at Manoa | not funded | [135][136] | ||
Waikīkī extension | Ala Moana Center | Liliʻuokalani Avenue | not funded | [135] | ||
Salt Lake extension | Aloha Stadium | Middle Street | not funded | [135] |
When complete, the trains will carry more than 6,000 people per hour,[137] from 4 am to midnight.[120] It is estimated the trains will serve 119,600 daily riders.[138]
The long term plan includes four extensions: two extensions east of Ala Moana Shopping Center, to the University of Hawaii-Manoa campus and to Waikiki, one extension west from East Kapolei to Kalaeloa, and the link through Salt Lake which was dropped from the initial plans.[139][140] In 2010, it was estimated the extensions could be completed after the initial four-section project, possibly as early as 2030.[135] None of these extensions are currently funded, but in November 2017, the rail authority took a first step towards preserving a corridor for the extension between Ala Moana Center and the University of Hawaii at Manoa.[141]
Farrington and Kamehameha segments
On October 21, 2009, the city announced Kiewit Pacific Co. had won the $483 million contract to build the first two sections of the line (the 7-mile (11 km) long Farrington and 4-mile (6.4 km) long Kamehameha sections), bidding $90 million under the expected price. The stations were tendered separately.[140][142]
The construction of the rail line started from suburban areas in Kapolei and Ewa, and progresses east towards the urban center in Honolulu. There will be 112 columns from East Kapolei to Ewa.[143] The choice to start from Kapolei was made because the first phase must include a baseyard for trains, which is more cheaply built away from the center, and also because the city chose to delay construction in the urban center to later phases of the project due to associated major impacts to existing infrastructure and unpopular traffic delays.[144]
To speed construction, the elevated trackway is built using precast concrete box girder bridge segments.[145] This method was first used for MARTA in the 1980s.[146] The trackway was designed by FIGG Bridge Engineers (who were responsible for the superstructure, referring to the box girder segmental bridge) and HNTB (substructure, referring to the columns). It is supported on single piers, each 6 to 7 feet (1.8 to 2.1 m) in diameter at the base and 30 feet (9.1 m) high, flaring at the top to support the lower section of the box girder; the piers are themselves supported by drilled shafts from 7 to 8 feet (2.1 to 2.4 m) in diameter.[145]
Casting of the box girder segments began in 2014 at a rate of 13 segments per day; in total, 5,238 segments will be required for the first 10 mi (16 km) phase.[147] The segments are cast locally in Kalaeloa.[148] Each segment weighs 50 short tons (45 t) and measures (L×W×H, with length measured along the direction of the rails) 11 by 30 by 7 feet (3.4 m × 9.1 m × 2.1 m),[149] and the deck ranges in thickness from 8 to 15 inches (200 to 380 mm).[145] Once the piers were erected, a pier bracket ram was placed and a launching gantry was used to bridge the span between adjacent piers; a deck-mounted crane lifted the precast segments onto the gantry, which supported them while they were tensioned together.[150] In total, 430 of the 438 spans in Phase 1 were assembled using precast box girder segments, at an average rate of 1 to 2 days per span.[145]
For the eight long spans required to bridge the H-1/H-2 Waiawa interchange in Pearl City, a balanced cantilever construction method was used instead. This covers the segments from Pier 252 to Pier 256.[149] Instead of precast segments, Kiewit used segments cast in-place, starting from the piers set in the freeway medians and working towards adjacent piers. The yellow-painted traveling forms at each end were used to cast each segment, then moved to the fresh end to cast the next segment. Each segment required 8,000 pounds (3,600 kg) of rebar and 48 cubic yards (37 m3) of concrete, and weighed 105 short tons (95 t). 73 segments were required.[151] The final pour for the balanced cantilever was performed in September 2016.[152]
Airport segment
The third section of the route to be completed is the 5 mi (8.0 km) Airport section east from Aloha Stadium to Middle Street that includes four stations, including the Honolulu International Airport station. AECOM won the contract to design the Airport section in 2012 with a $38.8 million bid.[153] The construction contract was awarded to a joint venture of Shimmick-Traylor-Granite (STGJV) in August 2016, who bid $874.8 million;[154][155] construction started in December 2016.[156]
The Airport section consists of 214 total spans which are also being constructed using precast concrete box girder bridge segments, like the earlier Farrington and Kamehameha sections, but for the Airport section, the segments are lifted and supported by an overhead gantry crane while they are tensioned.[157] Both a conventional overhead gantry and an articulating gantry are being used during the guideway assembly.[158] More than 2700 precast segments are required for the Airport section, which also includes more than 230 columns for the piers and 5400 permanent sound walls. For the pier foundations, shafts were drilled up to 350 feet (110 m) deep,[159] including one excavated to 357 feet 4 inches (108.92 m) with a diameter of 10 feet (3.0 m). This was believed to have established a new record for a drilled shaft caisson. The column, in Kalihi Stream on Kamehameha Highway between Middle Street and Puʻuhale Road, will be part of the support for Kahauiki station.[160] Where the guideway contacts the supporting piers, custom bearings have been installed to accommodate movement ranging from 2 to 19 inches (51 to 483 mm) and rotation of 0.015–0.03 radians.[161]
The STGJV announced in December 2020 it had completed the last of the 2,708 precast concrete guideway segments for the Airport section, with this last segment scheduled to be installed over Ualena Street near Lagoon Drive in spring 2021. Each segment uses approximately 18 cu yd (14 m3) of concrete. Finished segment weights vary between 40 to 65 short tons (36 to 59 t) and have dimensions of 30.5 feet (9.3 m) wide, 10.75 feet (3.28 m) long, and either 8.5 or 4.5 feet (2.6 or 1.4 m) high. The lower height is used in several places along the Airport section to accommodate overhead clearances and flight path restrictions.[162]
City Center segment
The fourth and final segment of the route, the 4 mi (6.4 km) City Center section terminating at Ala Moana Center, may be completed under a public-private partnership (PPP). It is estimated the City Center section will cost $1.6 billion to complete.[163] Under the proposed PPP, the City Center section would be procured under a design-build-finance-operate-maintain (DBFOM) contract, which would award the successful bidder the right to operate and maintain the entire system for a period of 25 years after completing the City Center section. The City of Honolulu would retain oversight over operations and maintenance, public information, and responsibility for fare vending and enforcement.[164] A contract for $400 million to clear utilities in the City Center section was awarded in May 2018.[16]
HART issued a request for proposals (RFP) for the DBFOM contract for the City Center Guideway and Stations section in late 2018[165] and announced it had received proposals from several bidders by July 2020.[166] However, the bids for the construction of the City Center Guideway and Stations significantly exceeded HART's cost estimates, at $2.7 billion compared to the $1.4 billion estimate,[167] and HART officially discontinued pursuing a PPP approach to completing the City Center section in November 2020.[168] The bids for the operation and maintenance portion of the contract (ranging from $4.2 to $5.3 billion) were closer to the estimate ($4.95 billion).[167] On December 14, 2020, HART issued a request for information, asking for input from the construction industry for the best way to structure a RFP that would receive realistic bids.[169]
Stations
Local construction company Nan, Inc. won contracts to build six of the nine western stations in 2015; the West Oahu Station Group contract (for East Kapolei, UH-West Oahu, and Ho'opili) was worth $56.1 million,[170] and the Kamehameha Highway contract (for Pearl Highlands, Pearlridge, and Aloha Stadium) was worth $116 million.[171] The Farrington Highway Station Group contract (for West Loch, Waipahu, and Leeward Community College) was awarded in 2015 to Hawaiian Dredging for $79 million.[172] The STGJV were awarded the contract to build the four Airport section stations (Pearl Harbor Naval Base, Honolulu International Airport, Lagoon Drive, and Middle Street) as part of their $875 million contract for the Airport section.[173]
The Hawaiian Station Naming Working Group (HSNWG), an expert working group, was named by the Honolulu City Council Resolution 09-158 on April 29, 2009 to develop Hawaiian names for each station of the Honolulu Authority for Rapid Transportation (HART) system.[174][175][176] HSNWG proposed Hawaiian names for the nine rail stations on the Ewa end of the rail system (stations west of and including Aloha Stadium) in November 2017,[177] and HART adopted the proposed names on February 22, 2018.[178] On April 17, 2019, HART released a list of Hawaiian names proposed by HSNWG for the remaining 12 rail stations on the eastern end of the rail system, between Pearl Harbor and Ala Moana Center.[5][179] The 12 names were released for public comment, and the HSNWG will review comments before presenting a final list of names to the HART Board of Directors.[180][181]
List of stations
Name | Section[121][182] | Image | Platform | Opening | Notes | |
---|---|---|---|---|---|---|
Hawaiian | English | |||||
Kualaka‘i[183] | East Kapolei | West O'ahu / Farrington 6.9 mi 11.1 km |
1 (center) | 2021 (scheduled) | Serves Kapolei, Makakilo, and ʻEwa Beach. Designated park-and-ride station.[184] | |
Keone‘ae[185] | University of Hawaii West O'ahu | 2 (side) | 2021 (scheduled) | Serves Keone‘ae campus. Designated park-and-ride station.[184] | ||
Honouliuli[186] | Ho'opili | 2 (side) | 2021 (scheduled) | Serves Honouliuli | ||
Hō‘ae‘ae[187] | West Loch | 2 (side) | 2021 (scheduled) | Serves West Loch, ʻEwa Beach, and Waipahu | ||
Pouhala[188] | Waipahu | 2 (side) | 2021 (scheduled) | Serves Waipahu and Waikele | ||
Hālaulani[189] | Leeward Community College | 1 (center) | 2021 (scheduled) | Serves Leeward Community College and Waikele | ||
Waiawa[190] | Pearl Highlands | 2 (side) | 2021 (scheduled) | Serves Pearl Highlands, Pearl Highlands Center, and Pearl City. Designated park-and-ride station.[184] | ||
Kamehameha Highway 3.9 mi 6.3 km | ||||||
Kalauao[191] | Pearlridge | 2 (side) | 2021 (scheduled) | Serves Pearlridge Center, Pearl City, Waimalu, and Aiea | ||
Hālawa[192] | Aloha Stadium | 2 (side) | 2021 (scheduled) | Serves Aloha Stadium, Aiea, Salt Lake, and Moanalua. Designated park-and-ride station.[184] | ||
Airport 5.1 mi 8.2 km | ||||||
Makalapa[193] | Pearl Harbor Naval Base | 2 (side) | 2022 (scheduled) | Serves Joint Base Pearl Harbor–Hickam, and Salt Lake | ||
Lelepaua[194] | Honolulu International Airport | 2 (side) | 2022 (scheduled) | Serves Daniel K. Inouye International Airport and Salt Lake | ||
Āhua[195] | Lagoon Drive | 2 (side) | 2022 (scheduled) | Serves Lagoon Drive and Mapunapuna | ||
Kahauiki[196] | Middle Street | 2 (side) | 2022 (scheduled) | Also known as Hauiki. Serves Kalihi and Honolulu Harbor | ||
City Center 4.1 mi 6.6 km | ||||||
Mokauea[197] | Kalihi | 2 (side) | 2025 (scheduled) | Serves Kalihi | ||
Niuhelewai[198] | Kapālama | 2 (side) | 2025 (scheduled) | Serves Kalihi, Kapālama, and Honolulu Community College | ||
Kūwili[199] | Iwilei | 2 (side) | 2025 (scheduled) | Serves Iwilei and Kalihi | ||
Holau[200] | Chinatown | 2 (side) | 2025 (scheduled) | Also known as Hōlau or Ho‘olau. Serves Chinatown | ||
Kuloloia[201] | Downtown | 2 (side) | 2025 (scheduled) | Serves Downtown Honolulu, Aloha Tower, and Capitol District | ||
Ka‘ākaukukui[202] | Civic Center | 2 (side) | 2025 (scheduled) | Serves the Ward, Ward Centers, and Maikiki | ||
Kūkuluāe‘o[203] | Kākā‘ako | 2 (side) | 2025 (scheduled) | Serves Kakaʻako, Maikiki, and Ward | ||
Kālia[204] | Ala Moana Center | 1 (center) | 2025 (scheduled) | Serves Ala Moana, Ala Moana Center, Kapiʻolani, Mano, and Waikiki |
Rail Operations Center
The Rail Operations Center (ROC; also known as the Maintenance and Storage Facility) is the 43-acre (17 ha) railyard, operations, and maintenance facility, divided into four buildings. It is in Pearl City, between the campuses of Leeward Community College and Waipahu High School, just west of Hālaulani. The design has been awarded LEED Silver certification.[205]
The buildings on the ROC campus are:
- Operation & Servicing Building (OSB) – housing primary vehicle maintenance facilities and the Operations and Control Center, where operators will monitor and control vehicle movement
- Maintenance of Way Building (MOW) – housing equipment used to inspect and repair tracks
- Train Wash Facility (TWF) – an automated facility to clean vehicle exteriors
- Wheel Truing Building (WTB) – a maintenance facility for vehicle wheels
The contract for the ROC was awarded to the Kiewit/Kobayashi Joint Venture in 2011.[206] The contract was initially awarded at a cost of $195 million; when the ROC was completed in July 2016, the actual incurred costs were $274 million.[207]:39
Rolling stock
The line will use 256 ft (78 m) four-car train sets, each with the capacity to carry about 780 passengers, similar in weight to light rail systems elsewhere in the United States (such as the MAX in Portland, Oregon), as opposed to heavier, and thus more expensive, lines found on rapid transit systems like the subways and elevated systems of Chicago and New York City.[208] However, the stations will be standalone structures and will be substantially bigger than typical light rail stations. Physically, the Honolulu system will have a good deal in common with light rapid transit systems such as SkyTrain in Vancouver, British Columbia or the Copenhagen Metro, as well as the Docklands Light Railway in London. The system will be the first metro system in the United States to feature platform gates and will be driverless.[209]
Rolling stock for the line will initially include 80 cars in 20 four-car train sets.[210] Each car will be 64 ft (20 m) long, weigh 72,000 lb (33,000 kg), and have 36 seats with a listed total capacity of 195 people.[208] The cars will be powered by a third-rail electrification system.[211]
Contract and delivery
The contract for the rail cars (named the Core Systems Design-Build-Operate-Maintain Services contract) was signed on November 28, 2011 by HART and Ansaldo Honolulu, a joint venture between AnsaldoBreda and Ansaldo STS.[212] AnsaldoBreda and Ansaldo STS previously collaborated on the construction and operation of vehicles for the Copenhagen Metro[213] and the Brescia Metro. Both companies were later purchased by Hitachi Rail in 2015[214] and Ansaldo Honolulu was subsequently renamed to Hitachi Rail Honolulu (HRH). Under the $1.4 billion contract, HRH is responsible for designing and fabricating the rail cars ($574 million), a test to validate train performance ($167 million), and operations and maintenance (O&M) during the first five years of revenue service ($339 million), with an option to continue O&M services for HART for an additional five years ($318 million) provided the review of the first five years is favorable.[212]
The two unsuccessful bidders for the rail car contract, Bombardier Transportation and Sumitomo Corporation of America, filed protests over the award.[215] Both protests were rejected during the administrative process, but Bombardier sought judicial review of their bid protest.[216] The administrative decision against Bombardier's protest was affirmed by both the state Circuit Court and the Intermediate Court of Appeals.[217][218]
The first two cars arrived in Hawaii in March 2016,[219][220] and the first train was unveiled to the public at the Rail Operations Center on May 2, 2016.[221] To meet "Buy America" requirements for federally-subsidized transit projects, the bodyshells are fabricated at the Hitachi Rail Italy plant in Reggio Calabria, Italy, then shipped to HRI's Pittsburg, California plant for final assembly.[219] The Pittsburg factory has since been partially leased to Bombardier Rail, who will assemble cars for BART there.[222]
In December 2016, Hitachi Rail Italy reported defects were discovered in the welds in the extruded aluminum beams of twenty-seven car shells, four of which were already in Hawaii. The manufacturer will fix the problems, but warned delivery may be delayed as production of new vehicles will be halted.[223] In March 2017 HART said they would meet the interim opening needs after repair of the defective cars and that full opening would not be affected.[224]
In May 2017, trains were towed on tracks in Honolulu for the first time, to check clearances.[225] Testing of trains under their own power commenced in October 2017.[226]
Timeline of progress
- February 2006 – A draft transportation plan includes $2.5 billion for a fixed-rail system between Kapolei and Manoa.[227]
- June 2006 – Officials estimate the infrastructure construction cost at estimated at $3 billion, $200 million more than a previous estimate, for a 24-mile system. This does not include the cost of the trains.[17]
- January 2007 – The General Excise Tax (GET) within Honolulu County is increased by 0.5% with the extra funds earmarked for a mass transit system. The increase was set to expire on December 31, 2022.
- February 2007 – The City Council approves the Minimum Operating Segment from East Kapolei to Ala Moana Centre, via Salt Lake Boulevard.[110]
- October 2008 – The Draft Environmental Impact Statement (DEIS) is released to the public. The projected cost is $3.7 billion including $1 billion for contingencies.[228]
- November 2008 – Fifty three percent of voters support an measures to give the Honolulu City Council authority to proceed with "establishment of a steel wheel on steel rail transit system". The estimated cost is $4 billion.[229]
- January 2009 – The middle portion of the route between Aloha Stadium and Middle Street is amended to have stations at the Pearl Harbor Naval Base and the Honolulu Airport which had one of the original options. The previous route followed Salt Lake Boulevard.[119]
- June 2010 – The Final Environmental Impact Statement (FEIS) is released to the public. Estimated cost is $5.5 billion. Patronage by 2030 is projected to be 116,300 riders per day.[230][231]
- December 2010 – A report, commissioned by outgoing Governor Lingle, is released which warns the project could cost at least $1.7 billion more than the city’s projected $5.5 billion price tag.[66]
- March 2012 – Dan Grabauskas becomes Executive Director and CEO of HART on a three year contract. He takes his position in April 2012.[72][232]
- May 2012 – Construction workers started pouring concrete on the foundations that will hold the rail columns.[233]
- December 2012 – Honolulu City Council and the Federal Transit Authority (FTA) sign agreement for the project with a budget of $5.12 billion including $1.55 billion provided by the Federal Government. Full system revenue service is projected for January 31, 2020.[234]
- September 2014 – HART canceled the initial tender for the first nine stations after the bids were higher than budget. "The lowest bid by Nan, Inc. came in at $294.5 million, or $110 million more than the $184 million the transit authority had budgeted." The first trips on the railway are expected to be delayed, probably until 2018.[235]
- November 2015 – FTA withholds payment of a $250 million allotment until the council could show it had sufficient funding to complete the project.[236]
- January 2016 – Five year extension to the General Excise Tax surcharge adopted to add $1.2 billion in funding.[234]
- May 2016 – HART chairwoman Colleen Hanabusa shared a confidential document detailing budget estimates as of March 1, 2016, showing that the rail project is expected to cost $6.9 billion.[237]
- April 2016 – An audit of the project by the City criticized HART for using outdated financial figures and budgets, lack of documentation for "change orders", and warned the HART estimates of the cost overruns were unreliable.[238][239] HART officials disputed the audit's findings.
- May 2016 – The FTA revealed that they estimate the total cost as $8.1 billion for the 20 mi (32 km) line. In addition completion of the rail system would be delayed nearly five years until December 2024, versus HART's federal funding agreement stating that full line service from East Kapolei to Ala Moana Center would start in January 2020.[240]
- June 2016 – Report from Jacobs Engineering, the project management oversight contractor, says that under a worst-case scenario the final cost would $10.79 billion.[105]
- August 2016 – Dan Grabauskas resigns as CEO and Executive Director of HART but will be the official CEO until October 2016. From August until October, the Department of Transportation Service Director Mike Formby served as interim CEO.[232][241][242]
- October 2016 – Krishniah N. Murthy named interim CEO and Executive Director of HART and served in this position until December 2017.[243]
- April 2017 – HART sent a "Recovery Plan" to the FTA which concluded that completion of the original 21 station route was the only viable plan. The new project cost given is $8.165 billion with media reports indicating that after financing costs are included it will be over $10 billion. Opening of part of the system, from East Kapolei to Aloha Stadium, is scheduled for the end of 2020 with final completion of the full route by December 2025. The project is reported to be 36 percent complete as of March 2017.[109][110]
- July 2017 – Andrew Robbins named new CEO and Executive Director of HART at a base salary of $317,000, replacing interim CEO and Executive Director Krishniah N. Murthy in December 2017.[243][244]
- September 2017 – A new law is enacted to extend and increase taxes to raise an additional $2.4 billion for the project. The GET surcharge is extended by three years to 2030 (generating about $1 billion) and a surcharge of one percent is placed on the statewide hotel room tax for 13 years (generating $1.3 billion).[104][23] HART submits a new recovery plan to the FTA with an estimated final cost of $9.02 billion with savings attributed to reduced financing costs given the new taxes.[18]
- January 2020 – Andrew Robbins, executive director and CEO of the Honolulu Authority for Rapid Transportation, said the first 10 miles of the Honolulu rail system would be completed by December 2020 as predicted, and will also be ready to run passenger service between Kapolei and Aloha Stadium three months earlier, by Oct. 20, 2020. Robbins said he was so confident of the new date that he was willing to stick his neck out.[245]
- May 2020 – “Completion of the first 10-mile segment of the line from East Kapolei to Aloha Stadium, originally scheduled for October, will be delayed by about eight weeks, according to Honolulu Authority for Rapid Transportation executive director Andrew Robbins... And the city, which had forecast opening the line to riders by December, has pushed that date back to next March.“[246]
- June 2020 – “More recently, the FTA has been projecting the project would be finished in September 2026, and insisted that the city incorporate that later date into its 2019 rail ‘recovery plan.’”[247]
- July 2020 – The city finally received much-anticipated proposals from private industry to finish the project’s major remaining construction work and then run the system for its first 30 years. The bids won’t be publicly released until the contract is awarded by unidentified officials.[248]
- September 2020 – one of the PPP bidders for the final city center segment from Middle Street to Ala Moana Center revealed themselves during a recent quarterly earnings call. Ronald Tutor, CEO of Tutor Perini, disclosed that his company is part of the Tutor Perini / Parsons joint venture for the final segment of Honolulu rail. While HART estimated that this last stretch would cost $1.4 billion, Tutor stated that his company’s bid was “over $2 billion.”[249]
- October 2020 – “The estimated cost of rail has jumped once again, bringing the construction and interest tab to the $10 billion threshold. The mayor tells us it will probably grow more, and the shortfall to pay for it all now tops more than $1.2 billion.”[250]
- November 2020 – In an effort to keep $250 million in federal funding from lapsing at the end of the year, Mayor Kirk Caldwell bypassed HART CEO Andrew Robbins and sent a letter to the Federal Transit Authority requesting a one year extension through the end of 2021. A rough outline of a plan included in the letter suggested a total cost of $11.2 billion including approximately $1 billion in financing costs, and a completion date of 2033.[251]
References
- Bogonovich, Mike. "Automated Light Metro for Honolulu". ascelibrary.org. American Society of Civil Engineers. Retrieved September 25, 2019.
- Smith, Sandy. "Honolulu Negotiates With Feds Over Light Metro Line". Next City. Retrieved September 25, 2019.
- "Light rail? Heavy rail? Subway? Rail transit modes fall on a continuum". Greater Greater Washington. April 4, 2019. Retrieved September 25, 2019.
- Honore, Marcel (November 24, 2020). "Rail's Interim Service Could Be Pushed Back A Year Amid COVID-19, Testing Woes". Honolulu Civil Beat. Retrieved January 2, 2021.
- "Nā Inoa" (PDF). honolulu.gov. April 15, 2019. Retrieved December 3, 2019.
- "TP -1: Core Systems Description Honolulu High -Capacity Transit Corridor Project" (PDF). Honolulu Authority for Rapid Transit. Retrieved December 8, 2018.
- Mangieri, Gina (May 19, 2016). "Could light rail help train reach Ala Moana and beyond?". KHON2. Retrieved October 28, 2016.
- Administrator. "The Honolulu Rail Project - Based on the Copenhagen Driverless Metro System". ansaldohonolulurail.com.
- "Rail Facts - All FAQs". honolulutransit.org. Retrieved November 4, 2020.
- "Honolulu ranked worst in country for traffic". Hawaii News now. Retrieved August 31, 2017.
- "Honolulu Rail Final EIS, Table 3-12" (PDF). http://hartdocs.honolulu.gov/docushare/dsweb/Get/Document-16806/20110701-final-eis-chapter-03.pdf. Retrieved November 4, 2020. External link in
|website=
(help) - "What Can We Do About the Rail? Nothing. Tackle Traffic Congestion!". Honolulu City Beat. January 29, 2015. Retrieved August 31, 2017.
- Kojima, Craig T. (2016). "Feds to city: No more money for rail, no stopping at Middle Street". Honolulu Star Advertiser. Retrieved August 31, 2016.
- Nanea Kalani (September 1, 2017). "Rail bail-out bill goes to Ige after House approves". Honolulu Star Advertiser. Retrieved September 2, 2017.
- "Rail officials start over on selecting builder for last stretch". Honolulu Star Advertiser. September 8, 2017. Retrieved September 25, 2017.
- "HART awards $400 million contract to relocate utilities to make way for Honolulu rail". Honolulu Star-Advertiser. May 7, 2018. Retrieved December 20, 2019.
- "Rail transit system cost estimate: $3 billion". Honolulu Advertiser. June 23, 2006. Retrieved September 1, 2017.
- "The Estimated Cost Of Honolulu Rail Just Dropped By $1 Billion". September 18, 2017. Retrieved September 25, 2017.
- "Caldwell says state lawmakers' rail-funding plan falls short". Honolulu Star Advertiser. August 24, 2017. Retrieved September 6, 2017.
- "The Hard Reality Of Honolulu Rail Costs". Honolulu Civil Beat. August 25, 2017. Retrieved September 6, 2017.
- "City rail audit won't look for fraud?". Grassroot Institute. August 18, 2017. Retrieved September 20, 2017.
- "Rep Tupola Backs Forensic Audit for HART". Hawai`i Free Press. August 15, 2017. Retrieved September 20, 2017.
- "Honolulu rail bailout becomes law with Ige's signature". Honolulu Star Advertiser. September 5, 2017. Retrieved September 6, 2017.
- "Bring Honolulu Rail Down To Earth". Honolulu Civic Beat. September 27, 2017. Retrieved September 28, 2017.
- "Blaisdell hails Oahu mass transit project", Honolulu Star-Bulletin, pp. A12, May 24, 1966
- Reyes, B.J. (August 11, 2005), "Council gives transit go-ahead 13 years after initial rejection", Honolulu Star-Bulletin, retrieved October 16, 2008
- Carlson, Ragnar (September 3, 2008), "Hail to the chief", Honolulu Weekly, archived from the original on September 28, 2011, retrieved October 16, 2008
- Au, Laurie (October 19, 2008), "Voters can derail $4B project", Honolulu Star-Bulletin, archived from the original on June 1, 2010, retrieved March 8, 2011
- Au, Laurie (November 10, 2008), "Voters on route drive rail victory", Honolulu Star-Bulletin, retrieved July 7, 2010
- Park, Gene (February 12, 2011), "Rail ready to break ground", Honolulu Star-Advertiser, retrieved February 12, 2011
- Park, Gene (February 23, 2011), "It's a go!", Honolulu Star-Advertiser, 130 (23), p. A1, retrieved February 23, 2011
- "Fasi To Start Rail Transit Study", Honolulu Star-Bulletin & Advertiser, p. A1, February 16, 1969 (Note: At this time, the Honolulu Star-Bulletin and Honolulu Advertiser published Sunday editions jointly under the name Honolulu Star-Bulletin & Advertiser.)
- Tune, Jerry (July 7, 1977), "A Transit Line with a HART", Honolulu Star-Bulletin, pp. A12
- Matsunaga, Mark (February 19, 1981), "Reagan stops HART in its tracks", Honolulu Advertiser, p. A1
- Matsunaga, Mark (May 5, 1981), "Mayor to abandon HART, beef up buses", Honolulu Advertiser, pp. A1
- Glauberman, Stu (May 5, 1981), "Mayor Calls HART Study to Abrupt Halt", Honolulu Star-Bulletin, p. A1
- Matsunaga, Mark (August 14, 1986), "Transit system plan revived", Honolulu Advertiser, p. A3
- Mariani, Jeanne (September 23, 1992), "Rail line dead – for now", Honolulu Star-Bulletin, p. A1
- Dicus, Howard (January 30, 2004), "Harris: 'Honolulu must build fixed rail'", Pacific Business News, retrieved October 16, 2008
- Kua, Crystal (November 3, 2006), "Council panel backs rail as mass-transit solution", Honolulu Star-Bulletin, retrieved October 15, 2008
- City and County of Honolulu Department of Transportation Services (November 1, 2006), Honolulu High-Capacity Transit Corridor Alternatives Analysis Report Chapter 1, Chapter 2, Chapter 3 to 7, retrieved February 25, 2009
- U.S. Department of Transportation Federal Transit Administration; City and County of Honolulu Department of Transportation Services, Draft Environmental Impact Statement Executive Summary (PDF), retrieved February 25, 2009
- Au, Laurie (October 31, 2008), "City releases portion of rail report", Honolulu Star-Bulletin, retrieved July 7, 2010
- Shikina, Robert (November 3, 2008), "Kobayashi rails against city for timing of report", Honolulu Star-Bulletin, retrieved November 6, 2008
- Hao, Sean; Roig, Suzanne (November 3, 2008), "Hawaii rail transit cost now at least $4.34B", Honolulu Advertiser, retrieved March 5, 2011
- U.S. Department of Transportation Federal Transit Administration; City and County of Honolulu Department of Transportation Services (2008-11), Honolulu High-Capacity Transit Corridor Project Draft Environmental Impact Statement/Section 4(f) Evaluation Cover to Contents, Chapter 1 Archived January 3, 2011, at the Wayback Machine, Chapter 2 Archived January 3, 2011, at the Wayback Machine, Chapter 3, Chapter 4 (Part 1) Archived January 3, 2011, at the Wayback Machine, Chapter 4 (Part 2), Chapter 5, Chapters 6–8 Archived January 3, 2011, at the Wayback Machine, References to Index Archived April 14, 2010, at the Wayback Machine, Appendix A (Conceptual Alignment Plans and Profiles) Archived January 3, 2011, at the Wayback Machine, Appendix B (Conceptual Right-of-Way Plans), Appendix C (Construction Approach) Archived December 11, 2009, at WebCite, Appendix D (Record of Agency Correspondence and Coordination), Appendix E (Record of Public and Stakeholder Correspondence and Coordination) Archived January 3, 2011, at the Wayback Machine, retrieved on January 5, 2009
- Hao, Sean (June 15, 2010), "Final study for rail line gets feds' OK", Honolulu Star-Advertiser, retrieved February 1, 2010
- Park, Gene (January 19, 2011), "Rail gets OK to break ground", Honolulu Star-Advertiser, retrieved January 20, 2011
- Au, Laurie (September 10, 2008), "Mayoral debate turns raucous", Honolulu Star-Bulletin, retrieved October 16, 2008
- Borreca, Richard; Au, Laurie (September 21, 2008), "Hannemann and Kobayashi reset sights for Nov. 4", Honolulu Star-Bulletin, retrieved October 20, 2008
- Au, Laurie (November 5, 2008), "Hannemann win re-election with 58%", Honolulu Star-Bulletin, retrieved November 5, 2008
- Au, Laurie (April 22, 2008), "Rail critics utilize power of pen", Honolulu Star-Bulletin, retrieved October 20, 2008
- Au, Laurie (August 5, 2008), "Lawsuit looms over validity of anti-rail petition", Honolulu Star-Bulletin, retrieved November 6, 2008
- Section 3-404 (PDF), Revised Charter of Honolulu Archived September 7, 2008, at the Wayback Machine, retrieved on February 25, 2009
- Au, Laurie (August 20, 2008), "City clerk rushing to certify anti-rail effort", Honolulu Star-Bulletin, retrieved November 6, 2008
- Au, Laurie (September 4, 2008), "Anti-rail group's effort denied by courts, clerk", Honolulu Star-Bulletin, retrieved November 6, 2008
- Au, Laurie (August 21, 2008), "Council OKs ballot question on transit", Honolulu Star-Bulletin, retrieved November 12, 2008
- Au, Laurie (August 22, 2008), "Mayor vows to put transit on ballot", Honolulu Star-Bulletin, retrieved November 12, 2008
- Dayton, Kevin (January 11, 2019). "Premature contracts increased rail cost by $354M". Star-Advertiser. Honolulu. Retrieved January 11, 2019.
- Charles Djou, "Rail" (http://djou.com/issues/rail/ Archived October 30, 2016, at the Wayback Machine)
- Mendoza, Jim; Lincoln, Mileka; Davis, Chelsea (June 16, 2016). "Mayor wants to shorten rail route, ending at Middle Street". Hawaii News Now. Retrieved March 11, 2017.
- Grace Lee, "Mayoral candidate Peter Carlisle says rail project cannot be stopped" (http://www.hawaiinewsnow.com/story/31997123/mayoral-candidate-peter-carl-isle-says-rail-project-cannot-be-stopped)
- Hao, Sean (January 3, 2010), "Honolulu rail behind schedule, with construction start unclear", Honolulu Advertiser, retrieved February 1, 2011
- Hao, Sean; Pang, Gordon Y.K. (January 9, 2010), "Honolulu's rail costs put state at financial risk, governor says", Honolulu Advertiser, retrieved February 1, 2011
- Hao, Sean (August 26, 2010), "Time short for Lingle's call on rail", Honolulu Star-Advertiser, retrieved February 1, 2011
- "Carlisle dismisses Lingle's rail report". Pacific Business News. December 3, 2010. Retrieved September 1, 2017.
- DePledge, Derrick (November 5, 2010), "Abercrombie to weigh rail EIS", Honolulu Star-Advertiser, retrieved February 1, 2011
- Park, Gene (December 17, 2010), "Governor signs off on review of rail", Honolulu Star-Advertiser, retrieved February 1, 2011
- Park, Gene (January 13, 2011), "State skips hearing on rail finance studies", Honolulu Star-Advertiser, retrieved February 1, 2011
- Park, Gene (February 20, 2011), "If they build it, will developers come?", Honolulu Star-Advertiser, retrieved February 20, 2011
- LaFrance, Adrienne (February 21, 2011), "Rail Groundbreaking: Phony or For Real?", Honolulu Civil Beat, Peer News LLC, retrieved February 22, 2011
- "Danial Grabauskas Named HART Executive Director". City and County of Honolulu: Department of Customer Services. March 1, 2012. Retrieved January 11, 2019.
- "Honolulu rail CEO blames cost overruns on legal challenges, but critics say it is incompetence". August 15, 2014. Retrieved September 6, 2017.
- "Editorial: COVID-19 brings more delays and money problems for Honolulu's rail". Honolulu Star Advertiser. May 16, 2020. Retrieved May 25, 2020.
- Honore, Marcel (May 12, 2020). "City Council Grows Anxious As Rail's COVID-19 Problems Deepen". Honolulu Civil Beat. Retrieved May 25, 2020.
- Hao, Sean (October 20, 2009), "Burial council won't sign rail pact", Honolulu Advertiser, retrieved July 7, 2010
- Conrow, Joan (May 26, 2010), "grave matters", Honolulu Weekly, archived from the original on November 19, 2011, retrieved January 30, 2011
- Park, Gene (January 16, 2011), "City plan accounts for problematic burial sites", Honolulu Star-Advertiser, retrieved January 30, 2011
- Daranciang, Nelson (February 1, 2011), "Lawsuit claims rail endangers burial sites", Honolulu Star-Advertiser, 129 (364), p. B1, retrieved February 1, 2011
- Daranciang, Nelson (March 24, 2011), "Judge Rejects Suit Challenging Rail Survey", Honolulu Star-Advertiser, retrieved March 24, 2011
- Hervey, Tiffany (June 27, 2012), "Buried Truth", Honolulu Weekly, archived from the original on October 25, 2012, retrieved July 19, 2012
- Grube, Nick (August 24, 2012), "Rail Derailed? Hawaii Supreme Court Rules Against Honolulu", Honolulu Civil Beat, Peer News LLC, retrieved August 24, 2012
- Schwind, Paul. "Honolulu Rail Remedy – Phasers On Minimal". Web. Hawaii Reporter. Retrieved January 17, 2013.
- Lowe, Kate. March 2014. “Bypassing Equity? Transit Investment and Regional Transportation Planning.” Journal of Planning Education and Research. vol. 34, no. 1. 30-44.
- Trask, Haunani-Kay. From a Native Daughter: Colonialism and Sovereignty in Hawai’i. Common Courage Press, Monroe, ME. 1993.
- Karner, Alex and Richard A. Marcantonio. April 2018. “Achieving Transportation Equity: Meaningful Public Involvement to Meet the Needs of Underserved Communities.” American Society for Public Administration, Section on Transportation Policy and Administration. Vol. 23, no. 2. 105-126.
- Kua, Crystal (January 1, 2005), "Director prioritizes rail transit", Honolulu Star-Bulletin, retrieved October 16, 2008
- Kua, Crystal (May 5, 2005), "City measure touts rail tax", Honolulu Star-Bulletin, retrieved October 16, 2008
- State of Hawaii Department of Taxation (July 29, 2005), State of Hawaii Department of Taxation Announcement 2005-11 (PDF), archived from the original (PDF) on December 11, 2009, retrieved June 21, 2009
- Kua, Crystal (July 12, 2005), "Late deal avoids transit veto", Honolulu Star-Bulletin, retrieved October 16, 2008
- Zimmerman, Malia (July 12, 2005), "Surrounded By Democrats at the Capitol, Hawaii's Republican Governor Rescinds Decision to Veto Tax Increase Measure", Hawaii Reporter, archived from the original on August 9, 2007, retrieved October 16, 2008
- DePledge, Derrick; Dingeman, Robbie (July 12, 2005), "Deal puts transit tax back on track", Honolulu Advertiser, p. A1, retrieved July 7, 2010
- Kua, Crystal (August 11, 2005), "Transit project to raise taxes", Honolulu Star-Bulletin, retrieved October 16, 2008
- Kua, Crystal (August 24, 2005), "Mayor signs tax, calls for multi-faceted traffic solutions", Honolulu Star-Bulletin, retrieved October 16, 2008
- Daranciang, Nelson (December 31, 2006), "Excise tax increase begins tomorrow", Honolulu Star-Bulletin, retrieved February 2, 2011
- Wu, Nina (January 22, 2009), "Legislature battles to avert $1.8B deficit", Honolulu Star-Bulletin, retrieved July 7, 2010
- DePledge, Derrick; Boylan, Peter (June 21, 2009), "Governor emphasizes Hawaii's deficit woes as Legislature opens", Honolulu Advertiser, retrieved June 21, 2009
- Hawaii State Legislature, 2009 Regular Session, Senate Bill 1626 Status, archived from the original on June 15, 2009, retrieved June 21, 2009
- Hawaii State Legislature, Senate Bill 1626 Senate Draft 1, Relating to Taxation, archived from the original on June 10, 2011, retrieved June 21, 2009
- Nakaso, Dan (January 24, 2009), "Stimulus could revive Honolulu, mayor says", Honolulu Advertiser, retrieved June 21, 2009
- DePledge, Derrick (March 11, 2009), "Legislature keeping its tax-raising options open", Honolulu Advertiser, retrieved June 21, 2009
- Borreca, Richard (March 11, 2009), "Lawmakers fear revenue slump", Honolulu Star-Bulletin, retrieved July 7, 2010
- "City Council approves tax surcharge extension for Honolulu rail project". Hawaii News Now. January 28, 2016. Retrieved September 2, 2017.
- "$2.4 Billion Rescue Bill For Honolulu Rail Wins Final Approval". Honolulu City Beat. September 2, 2017. Retrieved September 2, 2017.
- "New 'worst-case scenario' report reveals full 20-mile rail route could cost $10.79B". Hawaii News Now. June 24, 2016. Retrieved September 6, 2017.
- Ray Tsuchiyama (June 29, 2016). "A Rail System Option That Offers The Best Fit For Honolulu". Honolulu Civil Beat.
- "Salvage the Rail: Group renews call to bring rail to street level". Island News KITV4. February 7, 2017. Retrieved September 28, 2017.
- "MODIFYING HONOULU AREA RAPID TRANSIT (HART) FOR STREET LEVEL OPERATION IN DOWNTOWN HONOLULU (January 2017)" (PDF). Salvage The Rail. Retrieved September 28, 2017.
- "HART committed to rail project's original route in recovery plan submitted to FTA". Pacific Business News. May 1, 2017. Retrieved August 15, 2017.
- "HART Recovery Plan". Honolulu Authority for Rapid Transportation. April 28, 2017. Archived from the original (PDF) on August 31, 2017. Retrieved August 15, 2017.
- "Honolulu Rail Recovery Plan Remains A Work In Progress". Honolulu Civil Beat. January 8, 2018. Retrieved January 11, 2018.
- "Feds serve Honolulu's rail agency with 2nd subpoena".
- "Honolulu rail project subpoenaed by feds for third time".
- Dayton, Kevin (September 5, 2019). "FTA approves Honolulu rail recovery plan". Honolulu Star-Advertiser. Retrieved December 27, 2019.
- Sneider, Julie (August 2019). "Honolulu transit leaders eye late 2020 start to city's first passenger-rail system". Progressive Railroading. Retrieved December 17, 2019.
- Consillio, Kristen (November 17, 2008), "Rail route changes trigger harsh words", Honolulu Star-Bulletin, retrieved July 7, 2010
- Kua, Crystal (February 22, 2007), "Rail Route to Go Via Salt Lake", Honolulu Star-Bulletin, retrieved January 18, 2008
- Au, Laurie (January 29, 2008), "New rail route OK'd", Honolulu Star-Bulletin, retrieved July 7, 2010
- Hao, Sean (January 29, 2009), "Council changes transit route to serve airport", Honolulu Advertiser, retrieved January 29, 2002
- Honolulu Authority for Rapid Transit. "Rail Facts". Retrieved November 26, 2016.
- "Honolulu Rail Transit Project Overview" (PDF). Honolulu Authority for Rapid Transportation. October 2016. Retrieved December 19, 2019.
- "West Oahu-Farrington Highway Guideway Contract for Design-Build Construction Contract No. SC-DTS-1000137". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "West Oahu Station Group -FD Contract No. SC-HRT-1200116". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "West Oahu Stations Group Construction Contract". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "Farrington Hwy Station Group Design Contract No. SC-HRT-11H0013". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "Farrington Highway Station Group Construction Contract". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "Farrington Highway Station Group II". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "Kamehemeha [sic] Highway Guideway Design Build Contract No. CT-HRT-11H00195". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "Kamehameha Highway Station Group Design Consultant Contract No. CT-HRT-130022". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "Kamehameha Highway Stations Group Construction Contract No. CT-HRT-1600152". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "Airport Segment Guideway and Utilities Contract No. SC-HRT-1200038". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "Airport Station Group Design Consultant Contract No. SC-HRT-1200038". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "Airport Guideway and Stations Design-Build Contract No. CT-HRT-1600385". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "City Center Section Utilities & Guideway Contract No. SC-HRT-1200149". Honolulu Authority for Rapid Transportation. Retrieved December 20, 2019.
- "2: Alternatives Considered" (PDF). Honolulu High-Capacity Transit Corridor Project: Final Environmental Impact Statement/Section 4(f) Evaluation (Report). Department of Transportation Services, City and county of Honolulu. June 2010. pp. 2–48. Retrieved December 20, 2019.
- Honolulu Rail Transit Project: Final Supplemental Environmental Impact Statement/Section 4(f) Evaluation and Amended Record of Decision (PDF) (Report). Honolulu Authority for Rapid Transportation. September 2013. Retrieved December 20, 2019.
- City and County of Honolulu Department of Transportation Services. "Q&A: Honolulu Rail Transit" (PDF). Archived from the original (PDF) on January 17, 2009. Retrieved January 5, 2009.
- Bussewitz, Cathy (August 26, 2017). "Hawaii scrambles to keep train project from going off rails". AP News. Retrieved December 20, 2019.
- City and County of Honolulu Department of Transportation Services, Rail Transit Map (Part 1: Kapolei-Ewa), (Part 2: Waipahu-Aiea), (Part 3: Stadium-Kalihi), (Part 4: Kalihi-UH-Manoa/Waikiki), retrieved January 5, 2009
- "First contract awarded for Honolulu light rail". Railway Gazette International. October 26, 2009. Retrieved October 26, 2009.
- Kalani, Nanea (November 18, 2017). "Rail authority looks to preserve corridor for UH Manoa option". Honolulu Star Advertiser. Retrieved December 12, 2017.
- Hao, Sean (October 22, 2009), "1st Honolulu Rail Contract Goes to Kiewit Pacific at $483M", Honolulu Advertiser, retrieved July 7, 2010
- Tim Sakahara, "Concrete poured on Honolulu rail project," Hawaii News Now, May 16, 2014, retrieved on October 29, 2014.
- Hao, Sean (February 25, 2008). "First phase of rail would end in Pearl City". Honolulu Advertiser. Retrieved March 16, 2009.
- Rodriguez, Jose (Summer 2015). "Honolulu Rail Transit Project (Sgements 1 and 2)" (PDF). ASPIRE: The Concrete Bridge Magazine. Precast/Prestressed Concrete Institute. Retrieved December 19, 2019.
- Cox, William R. (Summer 2013). "Rail Transit Bridges" (PDF). ASPIRE: The Concrete Bridge Magazine. Precast/Prestressed Concrete Institute. Retrieved December 19, 2019.
- "The Honolulu Rail Transit Project Honolulu, Hawaii - Construction Update". Segments. Vol. 59. American Segmental Bridge Institute. Fall 2014. Retrieved December 19, 2019.
- Daysog, Rick (April 18, 2014). "Rail system's new concrete casting yard". Retrieved December 19, 2019.
- Honolulu Rail Transit Project Update (PDF) (Report). Honolulu Chamber of Commerce. June 25, 2014. Retrieved December 19, 2019.
- "Honolulu Rail Transit". Somerset Engineering. Retrieved December 19, 2019.
- Time Lapse - Balanced Cantelevered Work over H1/H2 Merge on YouTube
- "Rail project's balanced cantilever work over H-1 in Pearl City finishing up". KHON 2. September 17, 2016. Retrieved December 19, 2019.
- "AECOM announced today that it had been awarded a US$38.8-million contract to design the airport segment of the Honolulu Rail transit Project in Hawaii" (Press release). AECOM Technology Corporation. January 27, 2012. Retrieved December 20, 2019.
- Tobias, Lori (August 31, 2016). "Hawaii's $8B HART Project Is Chugging Along". Construction Equipment Guide. Retrieved December 19, 2019.
- Lincoln, Mileka (July 19, 2016). "Successful Airport-Middle Street rail segment bid totals $875M". Hawaii News Now. Retrieved December 20, 2019.
- Parsons, Jim (September 13, 2017). "Funding Boost Shores Up Troubled Honolulu Rail Project". Engineering News-Record. Retrieved December 19, 2019.
- "Honolulu Authority for Rapid Transportation (HART) Airport Guideway & Stations". Finley Engineering Group. Retrieved December 20, 2019.
- "Honolulu Rail Transit Project (HART)". McNary Bergeron & Associates. Retrieved December 20, 2019.
- "Airport Guideway and Stations Design-Build Contrat". Traylor Bros., Inc. Retrieved December 20, 2019.
- "HART contractor drills largest, deepest column foundation to support the Honolulu Rail project" (PDF) (Press release). Honolulu Authority for Rapid Transportation. June 15, 2020. Retrieved January 7, 2021.
- "HART Airport Guideway and Stations Project – Honolulu, Hawaii". RJ Watson Inc. Retrieved December 20, 2019.
- "HART rail contractor reaches major milestone with completion of final precast segment" (PDF) (Press release). Honolulu Authority for Rapid Transportation. December 10, 2020. Retrieved December 30, 2020.
- Yoshioka, Wayne (May 14, 2018). "HART Looking For Private Partners to Complete Last $1.6B City Center Rail Segment". Hawai‘i Public Radio. Retrieved December 20, 2019.
- "Public-Private Partnership Development Program | Program Structure". Executive Matters and Legal Affairs Committee, City and County of Honolulu. April 16, 2019. Retrieved December 20, 2019.
- "HART & city issue initial P3 request for proposals" (Press release). Honolulu Authority for Rapid Transportation. Retrieved December 30, 2020.
- "HART and city receive P-3 proposals" (PDF) (Press release). Honolulu Authority for Rapid Transportation. July 23, 2020. Retrieved December 30, 2020.
- Honore, Marcel (December 15, 2020). "HART, City Underestimated Cost Of Rail Work By $1.3 Billion, P3 Prices Show". Honolulu Civil Beat. Retrieved December 30, 2020.
- Honore, Marcel (November 20, 2020). "'How Do We Go Forward?' Honolulu Rail Leaders Kill P3, Confront Unknown Costs". Honolulu Civil Beat. Retrieved December 30, 2020.
- "HART issues request for information for work to complete rail project construction" (PDF) (Press release). Honolulu Authority for Rapid Transportation. December 14, 2020. Retrieved December 30, 2020.
- "HART awards construction contract for West Oahu rail stations" (PDF) (Press release). Honolulu Authority for Rapid Transportation. July 16, 2015. Retrieved December 20, 2019.
- Honoré, Marcel (December 23, 2015). "NAN Inc. wins deal for last trio of transit stations". Honolulu Star-Advertiser. Retrieved December 20, 2019.
- "Farrington Highway Stations Group Construction Contract No. CT-HRT-1500236" (PDF). June 10, 2015. Retrieved December 20, 2019.
- Mendoza, Jim (October 26, 2017). "It's coming: Rail work kicks off airport leg". Hawaii News Now. Retrieved December 20, 2019.
- "Nā Inoa" (PDF). honolulu.gov. February 2018. Retrieved April 3, 2019.
- "Honolulu Transit Route Map". Honolulu Authority for Rapid Transportation. Retrieved April 3, 2019.
- "Hawaiian Names for Rail Stations". Honolulu Authority for Rapid Transportation. Retrieved April 3, 2019.
- "Hawaiian Station Naming Program" (PDF). Honolulu Authority for Rapid Transportation. November 22, 2017. Retrieved December 19, 2019.
- "HART Board of Directors unanimously approve Hawaiian names for first nine rail stations" (PDF) (Press release). Honolulu Authority for Rapid Transportation. February 22, 2018. Retrieved December 19, 2019.
- Wu, Nina (April 18, 2019). "Honolulu rail transit authority seeks feedback on Hawaiian names for train stations". Honolulu Star-Advertiser. Retrieved May 29, 2019.
- "Hawaiian names recommended for HART's rail stations" (PDF) (Press release). Honolulu Authority for Rapid Transportation. April 17, 2019. Retrieved December 19, 2019.
- "Hawaiian Station Naming Program" (PDF). Honolulu Authority for Rapid Transportation. March 2019. Retrieved December 19, 2019.
- "Ahupaa Map" (PDF). Honolulu Authority for Rapid Transportation. May 25, 2012. Retrieved December 18, 2019.
- "Kualaka'i Station #1". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Station Design and Features". Honolulu Authority for Rapid Transportation. Retrieved December 19, 2019.
- "Keone'ae Station #2". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Honouliuli Station #3". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Hō'ae'ae Station #4". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Pouhala Transit Center Station #5". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Hālaulani Station #6". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Waiawa Station #7". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Kalauao Center Station #8". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Hālawa Station #9". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Pearl Harbor Naval Base Station #10". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Honolulu International Airport #11". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Lagoon Drive Station #12". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Middle Street Station #13". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Kalihi Station #14". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Kapalama Station #15". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Iwilei Station #16". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Chinatown Station #17". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Downtown Station #18". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Civic Center Station #19". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Kakaako Station #20". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Ala Moana Center Station #21". Honolulu Authority for Rapid Transportation. Retrieved December 18, 2019.
- "Honolulu Rail Transit Project: System Resource Guide" (PDF). Honolulu Authority for Rapid Transportation. Retrieved December 19, 2019.
- "Agreement for Design-Build Services, Contract No. CT-DTS-1000449" (PDF). Honolulu High-Capacity Transit Corridor Project. June 30, 2011. Retrieved December 23, 2019.
- Honolulu Rail Transit Project Monthly Progress Report (PDF) (Report). Honolulu Authority for Rapid Transportation. July 2016. Retrieved December 23, 2019.
- Park, Gene (March 22, 2011), "Have a seat", Honolulu Star-Advertiser, 130 (50), p. A1, A6, retrieved March 22, 2011
- "Home". honolulutransit.org. Archived from the original on July 28, 2014. Retrieved September 30, 2014.
- http://hartdocs.honolulu.gov/docushare/dsweb/Get/Document-17047/20140218-hart-train-vehicle-fact-sheet.pdf
- U.S. Department of Transportation Federal Transit Administration; City and County of Honolulu Department of Transportation Services (June 2010), Honolulu High-Capacity Transit Corridor Project Final Environmental Impact Statement/Section 4(f) Evaluation (PDF), pp. 2–30, retrieved March 28, 2011
- "Agreement for Design-Build-Operate-Maintain Services, Contract No. CT-DTS-1100194" (PDF). Honolulu High-Capacity Transit Corridor Project. November 28, 2011. Retrieved December 23, 2019.
- Brown, Robert (April 15, 2011), "FACT CHECK — Carlisle: Ansaldo's Copenhagen Line One of World's Best", Honolulu Civil Beat, Peer News LLC, retrieved April 16, 2011
- "Hitachi agrees to buy Ansaldo STS and AnsaldoBreda". Railway Gazette. February 24, 2015. Retrieved February 25, 2015.
- Park, Gene (April 12, 2011), "2 bidders protest city's rail decision", Honolulu Star-Advertiser, 130 (71), retrieved April 12, 2011
- Kalani, Nanea (October 14, 2011). "Disqualified Honolulu Rail Bidder Bombardier Files New Appeal". Honolulu Civil Beat. Peer News. Retrieved July 13, 2013.
- Abramson, Mark (October 17, 2012). "Hawaii Appeals Court upholds ruling in Bombardier rail lawsuit". Pacific Business News. American City Business Journals. Retrieved July 13, 2013.
- Bombardier Transportation (Holdings) USA Inc. v. Director, Department of Budget and Fiscal Services, City and County of Honolulu, 128 Haw. 413 (App.), 289 P.3d 1049 (Haw. App. 2012)
- Barrow, Keith (March 29, 2016). "First Honolulu metro cars delivered". International Railway Journal. Retrieved December 23, 2019.
- Honoré, Marcel (March 24, 2016). "First train cars arrive in Honolulu for rail transit project". Honolulu Star-Advertiser. Retrieved December 23, 2019.
- "Honolulu Gets First Look at New Transit System Rail Cars" (Press release). Hitachi USA. May 2, 2016. Retrieved December 23, 2019.
- Rudick, Roger (June 14, 2019). "BART Train Plant Moving to Pittsburg, CA". Streetsblog SF. Retrieved December 23, 2019.
- Honoré, Marcel (December 16, 2016). "New defect could further stall rail". Honolulu Star-Advertiser. Retrieved September 8, 2017.
- "Repairs to fix rail car production defects scheduled to start in March". KHON2. February 18, 2017. Retrieved September 8, 2017.
- "Honolulu tests rail car on track for first time". Honolulu Star-Advertiser. May 30, 2017. Retrieved September 8, 2017.
- "In successful test, city rail cars reach 40 mph on its own power". Hawaii News Now. October 19, 2017. Retrieved October 20, 2017.
- "StarBulletin.com | News | /2006/02/19/". archives.starbulletin.com. Retrieved September 10, 2020.
- "Just the facts on Honolulu transit". October 12, 2008. Retrieved September 1, 2017.
- "Council OKs ballot question on transit". Honolulu Star Bulletin. Retrieved September 1, 2017.
- "Honolulu Rail: The Complete Final Environmental Impact Statement". June 16, 2010.
- Honolulu Authority for Rapid Transit, "System Figures", honolulutransit.org, archived from the original on July 29, 2014, retrieved July 22, 2014
- Kuriowa, Jared (August 18, 2016). "HART CEO Grabauskas resigns, Formby steps in as interim". KHON2. Honolulu. Retrieved January 11, 2019.
- Tim Sakahara, "Concrete poured on Honolulu rail project," Hawaii News Now, May 16, 2012, retrieved on October 29, 2014.
- "HART Recovery Plan" (PDF). Honolulu Authority for Rapid Transportation. April 28, 2017. p. 19. Retrieved August 31, 2017.
- "HART cancels bids for first 9 rail stations". KITV. September 10, 2014. Archived from the original on November 29, 2014. Retrieved November 27, 2014.
- "Year in Review 2015: Honolulu's rail transit project". Pacific Business Review. December 15, 2015. Retrieved September 5, 2017.
- "Honolulu Rail Price Estimate Jumps To $6.9B". Civil Beat News.
- "City audit calls HART's finances, plans 'outdated and unreliable'". khon2. April 15, 2016. Retrieved September 4, 2017.
- "Audit slams Honolulu rail agency over management, costs". Honolulu Star Advertiser. April 15, 2016. Retrieved September 4, 2017.
- "Add 5 years and $1B for rail, federal agency says". Honolulu Star-Advertiser. May 17, 2016. Retrieved December 10, 2017.
- Honoré, Marcel (August 18, 2016). "Grabauskas resigns as HART's chief executive". Star-Advertiser. Honolulu. Retrieved January 11, 2019.
- Daysog, Rick; Kawano, Lynn (August 18, 2016). "Outgoing rail CEO ruffled feathers, struggled with cost overruns". Hawaii News Now. Honolulu. Retrieved January 11, 2019.
- Shimogawa, Duane (December 28, 2016). "Former HART CEO Dan Grabauskas starts own consulting firm". Pacific Business News. Honolulu. Retrieved January 11, 2019.
- Honoré, Marcel (July 31, 2017). "HART board selects new executive director". Star-Advertiser. Honolulu. Retrieved January 11, 2019.
- mpennybacker@staradvertiser.com, By Mindy Pennybacker; Jan. 9, 2020 (January 9, 2020). "Honolulu's rail will be ready to run by Oct. 20, HART chief Andrew Robbins says". Honolulu Star-Advertiser. Retrieved September 11, 2020.CS1 maint: numeric names: authors list (link)
- May 16, 2020 (May 16, 2020). "Editorial: COVID-19 brings more delays and money problems for Honolulu's rail". Honolulu Star-Advertiser. Retrieved September 20, 2020.CS1 maint: numeric names: authors list (link)
- kdayton@staradvertiser.com, By Kevin Dayton; June 26, 2020 (June 26, 2020). "Scheduled 2025 opening date for 20-mile rail line being pushed into 2026". Honolulu Star-Advertiser. Retrieved September 10, 2020.CS1 maint: numeric names: authors list (link)
- "Rail's P3 Proposals Finally Arrive But Costs Remain Sealed". Honolulu Civil Beat. July 25, 2020. Retrieved September 10, 2020.
- "Honolulu Rail P3 Bidder Wants More Than $2 Billion For The Final Stretch". Honolulu Civil Beat. September 18, 2020. Retrieved September 20, 2020.
- "Rail swells to $10B to build and finance, gap now $1.2B as tax sinks". KHON2. October 16, 2020. Retrieved November 3, 2020.
- gordonpang@staradvertiser.com, By Gordon Y. K. Pang; Nov. 18, 2020 (November 18, 2020). "Mayor Kirk Caldwell: Rail cost now $11B, won't be completed until 2033". Honolulu Star-Advertiser. Retrieved November 28, 2020.CS1 maint: numeric names: authors list (link)
External links
- Media related to Honolulu Rail Transit at Wikimedia Commons
- Official website