I-77 Bus Rapid Transit

The I-77 Bus Rapid Transit is a proposed bus rapid transit (BRT) service, connecting the towns northern Mecklenburg and southern Iredell counties to Uptown Charlotte, North Carolina. The BRT replaces the previously planned commuter rail service, the Lynx Red Line, that was routed along the existing Norfolk Southern O Line right-of-way. However, several issues had arisen that included ineligibility for federal funding and Norfolk Southern refusal to allow access to its right-of-way. In 2019, after a reevaluation of the entire corridor, the Charlotte Area Transit System (CATS) decided to move forward with BRT and shelve the commuter rail; which had been met with frustration by various city leaders and residents impacted by it.[2]

I-77 Bus Rapid Transit
(Formerly Lynx Red Line)
Overview
SystemCharlotte Area Transit System
StatusPlanning phase
Route
Route typeBus rapid transit
LocaleCharlotte, Cornelius, Davidson, Huntersville, and Mount Mourne, NC
StartGateway Station
EndMount Mourne
Stations8
Proposed route map[1]

possible future extension
to Exit 35 (Mooresville)
Mount Mourne
Davidson
Cornelius
Huntersville Northcross
Huntersville Gateway
Hambright
Northlake
Uptown/
Gateway Station
      

Since February 3, 2020, MetroRAPID, a rebranding and overhauling of four existing express bus routes, has been setup to utilize the I-77 express lanes, which were completed in 2019.[3]

History

Commuter Rail

Red Line
Mount Mourne
Davidson
Cornelius
Sam Furr
Huntersville
Hambright
Eastfield
Harris Boulevard/ NC 115
Derita
Uptown/Gateway Station

The Red Line was a planned ten station commuter rail that was to connect between Mount Mourne in southern Iredell County and the proposed Gateway Station in Uptown Charlotte.[4][5][6] It would primarily serve the towns of Huntersville, Cornelius and Davidson in northern Mecklenburg County.

It would be routed along the existing Norfolk Southern O Line right-of-way, roughly paralleling North Graham Street and North Carolina Highway 115, as it extends through north Mecklenburg County. It is estimated to be 25 miles (40 km) in length. Originally, it was thought to cost $261 million to complete the first phase by 2012 and an additional $112 million to complete phase two by 2019; the line would contain 1,200 parking spaces and 10 stations along the corridor. However, several issues have arisen that have increased the project's price tag, and it currently has no scheduled construction or operations start date.[7][8]

Design and planning

By 2011, the Lynx Red Line was planned to be built in one phase. Due to less revenue in the transit tax, in January the Metropolitan Transit Commission voted that the Lynx Red Line along with the Blue Line extension were the top two priorities, leaving the streetcar to be funded by the city and postponing further work on the LYNX Silver Line and the Airport corridor until after the Red Line and Blue line projects were completed. The Red Line was projected to be in operation by mid to late 2018.

Feasibility

By June 2011 the project had been 90% designed and an operating agreement was signed with Norfolk Southern Railway, but the project lacked nearly 80% of the needed funds to begin construction. In October 2012, The Charlotte Observer noted that "the Red Line...has little chance of federal funding, and CATS may not have enough money to pay for even a portion of construction costs. The NCDOT is working on creative ways to finance the project, but it appears to be years away."[9]

On October 17, 2012, the NCDOT, the Red Line Task Force and CATS requested Norfolk Southern to conduct a study of the "Red Line" concept. As the Red Line would utilize the NS O-Line between Charlotte and Mooresville, the study would determine if and how both freight and passenger services could use the same line while allowing normal freight services to continue. It was estimated at a meeting of the task force on October 24 that the study would be initiated by late January 2013 and completed by early 2014, after which further feasibility studies and projections could be made.[10] However, in early 2013, Norfolk Southern expressed its doubts that the $416 million project would be feasible.[11]

On June 25, 2014, following the completion and release of the feasibility study, CATS officials said that the Red Line would be too costly and complicated to build.[7] Several reasons were provided, including:

  • The continued refusal of Norfolk Southern to share its existing trackage with CATS, necessitating the construction of a new railway line parallel to the NS rails. This would increase the overall project cost by $215 million and cause "multiple disruptions to adjacent communities", as building a parallel rail line would involve construction costs, right-of-way purchases, and the complete rebuilding of all road intersections along the proposed line.
  • The project's ineligibility for federal funding due to low ridership projections.
  • The inability of CATS to fund the Red Line on its own.
North Corridor reevaluation

Despite the negative assessments of the feasibility study, the Metropolitan Transit Commission, including the Red Line task force, did not take any official steps to disband the project. While the director of the N.C. DOT rail division, Paul Worley, said that he would work with Norfolk Southern officials to begin a study concerning the proposed Gateway Station, he said that the Red Line concept would not be included, as "no viable plan" for it now existed. Though the mayor of Davidson, John Woods, said the results of the feasibility study were "a serious setback," he added that developing transit in the northern portion of Mecklenburg County remained important for the region, and one possible alternative to a commuter rail line could be bus rapid transit.[8]

North Corridor reevaluation

In July 2018, CATS began a reevaluation of the Red Line and three alternative options to replace it if still not feasible. The process involves a series of public meetings and various surveys to know where the public stands regarding the Red Line and how each of the alternative options rank.[12][13] CATS recently held a survey to get the public's opinion on the LYNX Red Line. This information will be presented late 2018.[14][15]

In January 2019, CATS announced that plans for either a commuter or light rail between Uptown and Mooresville was not feasible. In the short term, CATS will run express buses along the I-77 Express lanes. In the next five to ten years, service would be expanded to true bus rapid transit (BRT).[16][17]

References

  1. "North Corridor Commuter Rail Project" (PDF). Charlotte Area Transit System. Retrieved September 6, 2014.
  2. Marusak, Joe (January 1, 2020). "Commuter rail 'essential' from Charlotte to Lake Norman, former mayor says". The Charlotte Observer. Retrieved March 29, 2020.
  3. Boraks, David (January 13, 2020). "CATS Changing North Meck Express Bus Routes To Use I-77 Toll Lanes". Charlotte, NC: WFAE. Retrieved March 29, 2020.
  4. "2030 Transit Corridor System Plan". Charlotte Area Transit System. Retrieved September 6, 2014.
  5. "Red Line Project". Charlotte Area Transit System. Retrieved September 6, 2014.
  6. "Home". Red Line Regional Rail. Archived from the original on September 6, 2014. Retrieved September 6, 2014.
  7. "Major blow dealt to CATS Red Line project". Charlotte, NC: WCNC-TV. June 27, 2014. Retrieved September 6, 2014.
  8. Harrison, Steve (June 26, 2014). "Charlotte commuter train price jumps by $215M". The Charlotte Observer. Retrieved September 6, 2014.
  9. "Light-rail extension moves to fast track; CATS to announce federal funding for uptown-to-UNCC line". The Charlotte Observer. October 15, 2012. Archived from the original on January 2, 2013.
  10. "Light Rail Task Force Agenda – Summary" (PDF). Charlotte Area Transit System (CATS). October 24, 2012.
  11. "Leaders: Charlotte area can't pay for transit needs". The Charlotte Observer. April 12, 2013. Archived from the original on June 28, 2013. Retrieved April 28, 2013.
  12. Hughes, Rob (July 17, 2018). "CATS to survey public on Red Line that would connect Lake Norman to uptown". Charlotte, NC: WCNC-TV. Retrieved July 18, 2018.
  13. "North Corridor Init Screening Brochure" (PDF). Charlotte Area Transit System. July 16, 2018. Retrieved July 18, 2018.
  14. http://charlottenc.gov/cats/transit-planning/red-line/Pages/default.aspx
  15. http://charlottenc.gov/cats/transit-planning/2030-plan/Pages/default.aspx
  16. Portillo, Ely (January 23, 2019). "No mile-long tunnel under uptown: CATS recommends a different route for light rail". The Charlotte Observer. Retrieved January 23, 2019.
  17. Harrison, Steve (January 23, 2019). "CATS Gives New Details On 2030 Plan, Including New Rail Along I-277". Charlotte, NC: WFAE. Retrieved January 23, 2019.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.