Blythe Photovoltaic Power Plant

The 21 megawatt Blythe Photovoltaic Power Plant is a photovoltaic (PV) solar project in California. It is located in Blythe, California, in Riverside County about 200 miles (320 km) east of Los Angeles.[1] Commercial operation began in December 2009. Electricity generated by the power plant is being sold to Southern California Edison under a 20-year power purchase agreement.[1] Another 20 MW plant called NRG Solar Blythe II came online in April 2017.[2]

Blythe Photovoltaic Power Plant
CountryUnited States
LocationBlythe, Riverside County, California
Coordinates33.59°N 114.74°W / 33.59; -114.74
StatusOperational
Construction beganSeptember 2009
Commission dateDecember 2009
Owner(s)NRG Energy
Operator(s)First Solar
Solar farm
TypeFlat-panel PV
Power generation
Nameplate capacity21 MW

Production

Generation (MW·h) of FSE Blythe 1 LLC [3]
YearJanFebMarAprMayJunJulAugSepOctNovDecTotal
2009 1,372 1,372
2010 1401,3503,2924,9296,9647,8837,6046,7935,5222,4742,115790 49,855
2011 292,1913,1355,2026,3848,2047,0577,2705,0184,0111,4241,351 51,275
2012 1421,4143,4675,0166,8957,4526,4445,0784,7553,7371,9111,396 47,708
2013 8611,7643,0043,1673,5644,5434,2865,7685,6074,9644,9415,156 47,624
2014 1,7011,9403,4164,0424,6435,1504,7665,1575,0314,5443,7762,575 46,740
2015 2,1922,7634,0494,5444,5684,7064,8714,9304,0693,4273,1752,614 45,908
Total290,482

See also

References