Line 12 (Mumbai Metro)

Orange Line 12 (Extension), or the Kalyan-Dombivli-Taloja Line is a proposed line of Mumbai Metro. It will be an extension of Orange Line. The total length of the line is planned to be 20.75 kilometres (12.89 mi), and the route will be completely elevated. The total cost of the construction is planned to be Rs 4,132 crore. MMRDA approved the Kalyan-Dombivli-Taloja Metro line. There will be 18 stations. This line will connect Navi Mumbai city with Kalyan-Dombivali city.[1]

Mumbai Metro Orange line 12 (Extension)
Overview
StatusApproved
OwnerMumbai Metropolitan Region Development Authority
Line number12
LocaleNavi Mumbai and Thane, Maharashtra, India
TerminiKalyan
Taloja
Stations18
Service
TypeMetro
SystemMumbai Metro
Operator(s)Mumbai Metro
Technical
Line length20.75 km (12.89 mi)
Number of tracks2
CharacterElevated
Track gauge1,435 mm (4 ft 8 12 in) standard gauge
Route map

Line 12
to Line 5
0.0000
Kalyan APMC
Kalyan APMC Depot
Central line
0.9541
Ganesh Nagar
2.4303
Pisavali Gaon
3.5103
Golavali
4.6774
Dombivali MIDC
5.6836
Sagaon
6.8103
Sonarpada
7.8000
Manpada (Dombivali East)
Badlapur–Katai Road
9.0582
Hedutane
10.0886
Kolegaon
11.2036
Nilaje Gaon
12.6636
Vadavali
14.0848
Bale
15.5892
Vaklan
16.4372
Turbhe
Pisarve Depot
17.2871
Pisarve Depot
19.0920
Pisarve
Taloja Navi Mumbai Metro Depot
20.6357
Taloja on Vasai Road–Roha line
Panchanand on Line 1
to Line 1

Delhi Metro authority show red flag to Kalyan-Dombivli-Taloja Metro line.[2] However the construction work started on 01/11/2019 and is expected to be completed on 31/10/2024 with Revenue Opening Date (ROD) as 01/11/2024. MMRDA in its 138th Authority Meeting held on 26/08/2015 vide Resolution No. 1340 has granted In-principle Approval to develop growth Centre in Kalyan Taluka (area approx. 1089 Ha.) through implementation of Town Planning Schemes (TPS).

Stations

Line 12 will have 18 stations, all elevated.

Orange Line 12
# Station Name Status Connections Layout
EnglishMarathi
1Kalyan APMCकल्याण एपीएमसीApproved Orange Line 5  (Under Construction)Elevated
2Ganesh Nagar (Kalyan)गणेश नगर (कल्याण)ApprovedNoneElevated
3Pisavali Gaonपिसावली गावApprovedNoneElevated
4GolavaliगोलावलीApprovedNoneElevated
5Dombivali MIDCडोंबिवली एमआयडीसीApprovedNoneElevated
6SagaonसागांवApprovedNoneElevated
7SonarpadaसोनारपाडाApprovedNoneElevated
8Manpada (Dombivali East)मानपाडा (डोंबिवली पूर्व)ApprovedNoneElevated
9HedutaneहेदुतनेApprovedNoneElevated
10KolegaonकोलेगावApprovedNoneElevated
11Nilaje Gaonनिळजे गावApprovedNoneElevated
12VadavaliवडवलीApprovedNoneElevated
13BaleबाळेApprovedNoneElevated
14Waklanवाक्लनApprovedNoneElevated
15Turbheतुर्भेApprovedNoneElevated
16Pisarve Depotपिसार्वे आगारApprovedNoneElevated
17Pisarveपिसार्वेApprovedNoneElevated
18TalojaतळोजाApprovedLine 1 (Navi Mumbai Metro)Elevated

References

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.