Line 4 (Mumbai Metro)

Green Line 4 of the Mumbai Metro, currently under construction, is part of the metro system for the city of Mumbai, India and is being developed by MMRDA and a consortium of international companies.[2]

Mumbai Metro Green Line 4
Overview
Status
  • Line 4 (under construction)
  • Line 4A (under construction)[1]
OwnerMMRDA
Line number4
LocaleMumbai and Thane, Maharashtra, India
TerminiGaimukh and Kasarvadavali
Wadala
Stations32 + 2 extended 34
WebsiteLine 4
Service
TypeRapid Transit
SystemMumbai Metro
Operator(s)MMRDA
Depot(s)Owale
Godrej
Daily ridership2021 0.8 million 2031 1.2 million
History
Commenced25 July 2018 (2018-07-25) (Line 4)
6 October 2019 (2019-10-06) (Line 4A)
Planned openingOctober 2022 (2022-10)
Technical
Line length32.32 km (Line 4)
2.7 km (Line 4A)
Number of tracks2
CharacterElevated
Track gauge1,435 mm (4 ft 8 12 in) standard gauge
Operating speed90 km/h (56 mph)
Highest elevation3.90 m (12.8 ft)
Route map

Line 4
to Line 10
0.0000
Gaimukh
Mogharpada Depot
1.2830
Gowniwada
2.6679
Kasarvadavali
3.7414
Vijay Garden
4.6502
Dongripada
6.1158
Tikuji-ni-wadi
6.8914
Manpada (Thane)
7.7567
Kapurbawdi on Line 5
9.1459
Majiwada
9.9701
Cadbury Junction
10.7628
Mahapalika Marg
11.7987
RTO Thane
12.4772
Teen Haath Naka (Thane)
13.7135
Mulund Naka
15.0615
Mulund Fire Station
16.1744
Sonapur
17.5651
Shangrila
18.4087
Bhandup Central line
19.4575
Bhandup Mahapalika
20.2368
Naval Housing
20.9286
Gandhi Nagar (Kanjurmarg)
Kanjurmarg on
Central line
Kanjurmarg (West) on Line 3 and Line 6
21.9307
Surya Nagar
22.9354
Vikhroli
23.6585
Godrej Company
24.8213
Shreyas Cinema
Central line
25.4421
Laxmi Nagar
26.5196
Pant Nagar
28.1522
Garodia Nagar
28.7507
Amar Mahal Junction
Santacruz–Chembur Link Road
Harbour line
30.0942
Siddharth Colony
Line 2
31.1486
Suman Nagar
Kurla–Mahul BP Refinery line
32.2269
Anik Nagar Bus Depot
33.0885
Wadala Truck Terminal
34.0885
Bhakti Park (Wadala)
on Line 1 (Mumbai Monorail)
to Line 11

The 32.32 km (20.08 mi) line is planned to be fully elevated, and is expected to consist of 32 stations from Wadala (Mumbai) to Kasarvadavali (Ghodbunder road, Thane) via Ghatkopar, Mulund and Teen Hath Naka, a popular traffic crossing in Thane. It is estimated to cost ₹14,549 crore.[3] Its construction was expected to begin by June 2018.

It is expected to be completed in 2022 and is expected to provide interconnectivity among the existing Eastern Express Highway, Central Railway, Mono Rail, the ongoing Metro Line 2B (D N Nagar to Mandale), and the proposed Metro Line 5 (Thane to Kalyan), Metro Line 6 (Swami Samarth Nagar to Vikhroli) and Metro Line 11 (Wadala to CSMT). It will provide rail based access to the commercial, government bodies and geographical landmarks in Mumbai. Dedicated depots are planned in Owale land in up to an extent of 20 ha. and in Godrej Land in up to 15.50 ha. area. It will reduce the current travel time by between 50% and 75% depending on road conditions.

Planning

The Maharashtra Cabinet approved the Metro 4 corridor on 27 September 2016. Half of the project cost will be funded by the Centre and the State Government, while the remaining will be financed through loans from the AIIB[4] and the World Bank.[5][6] The foundation stone for Metro 4 was laid by Prime Minister Narendra Modi on 24 December 2016.[7] The Maharashtra Coastal Zone Management Authority granted Coastal Regulation Zone (CRZ) to the project in February 2017. Over 1 km of the line passes over water bodies in Bhakti Park and Wadala, both areas classified as Coastal Regulation Zone II where CRZ rules limit construction activities. 48 piers are proposed to built in the CRZ II. The MMRDA will construct metro car depots for the line on a 30 hectare plot at Owala village in Thane district and another in Vikhroli.[8]

The MMRDA utilized a drone to carry out survey work for Metro 4. The drones were fitted with 360 degrees camera that provide up to 3 millimeter accuracy. The aerial survey takes less time than a regular survey, achieves greater accuracy and helps protect against false claims for compensation.[9] In March 2017, the MMRDA stated that it was conducting a pre-feasbility study on extending the line from Wadala to Mumbai General Post Office in South Mumbai, via the Mumbai Port Trust. The proposed 8 km extension is estimated to cost 300 crore per km.[10][11]

In October 2018, the MMRDA announced that it would construct Metro 4 along with three flyovers to ensure smooth flow of traffic, with the metro running on the upper deck of the flyover. The three flyovers will be built at Bhayander Pada, Kasarvadavli and Anandnagar near Ghodbunder.[12][13]

In May 2019, MMRDA Metropolitan Commissioner R.A. Rajeev announced a modified plan to use Siddharth Colony as the interchange station with Line 2. The original plan had proposed to use the Eastern Express Highway station on Line 2B and Siddharth Colony on Line 4 as the interchange stations. However, the two stations are approximately 480 metres away from Siddharth Colony and the change was made to simplify passenger transfers.[14]

Construction

A consortium of DB Engineering, Louis Berger and Hill International was awarded a project management and construction management services contract for the Metro 4 project in April 2018.[15][16] The MMRDA invited bids for civil work on the corridor on 4 January 2017.[17][18][19] The tenders for construction of viaducts and stations were divided into five packages - Wadala to Amar Mahal Junction, Garodia Nagar to Surya Nagar, Gandhi Nagar to Sonapur, Mulund Fire Station to Majiwada and Kapurbawdi to Kasarvadavali.[20][21] Metro 4 was tendered alongside Metro 2B. L&T, Afcons Infrastructure, Tata, NCC and JMC, Reliance Infrastructure-RdE, Wenig Incorporation, JKumar Group, ITD Cementation, CHEC-TPL bid for packages on both Metro 2B and Metro 4. A total of 11 firms and/or consortia submitted bids for the two lines, two of whom (Simplex Infrastructures and a consortium of GHEC-RCC-JV-China) bid exclusively for Metro 2B packages.[22][23]

The construction work was divided into five packages and awarded through the engineering, procurement and construction (EPC) model in April 2018. A joint venture between Reliance Infrastructure and Italian firm Astaldi S.p.A. was awarded three packages between Kasarwadavali and Wadala worth 1,584 crore (US$220 million).[24] The contract for the remaining two packages, worth a combined 1,048 crore (US$150 million), was awarded to a joint venture between Tata Projects Limited and China Harbour Engineering Company.[25] The civil work is expected to be completed in 30 months.[26][1]

Whereas, On the Metro 4A project, which is estimated to cost Rs 949 crore will have two stations Gowniwada and Gaimukh which is the extension Route.[27][28] The Mumbai Metropolitan Region Development Authority (MMRDA) has today issued two contract orders to major infrastructure company J Kumar Infraprojects Limited for construction of Mumbai Metro Line 4A (Kasarwadavali-Gaimukh corridor). Design and construction of elevated viaducts and two stations from Kasarwadavali to Gowinwada and Gowinwada to Gaimukh for the corridor of Mumbai Metro Line 4A (extension of Metro line 4 Wadala to Kasarwadavali of Mumbai Metro Rail Project of MMRDA). The total contract value of the letter of acceptance is Rs 342 crore.[29]

Sl No.ContractContractor
1General ConsultantDB Engineering & Consulting GmbH[30] with M/s. Louis Berger Pvt. Ltd[31] and Hill International[32]
2Rolling StockBombardier[33]
3 Signalling & Screen Doors Yet to be awarded (tenders invited in April 2020)[34]
4Detailed Design Consultant (DDC)M/s. SYSTRA MVA Consulting (India) Pvt. Ltd.[35]
5Wadala to Amar Mahal

(6.2 km Viaduct & 6 Stations)

Reliance-Astaldi JV
6Garodia Nagar-Surya Nagar

(6.4 km Viaduct & 7 Stations)

TPL-CHEC JV
7Gandhi Nagar-Sonapur

(6.7 km Viaduct & 6 Stations)

Reliance-Astaldi JV
8Mulund Fire Station-Majiwada

(7.1 km Viaduct & 7 Stations)

TPL-CHEC JV
9Kapurbawdi-Kasarvadavali

(6.8 km Viaduct & 6 Stations)

Reliance-Astaldi JV
10Kasarvadavali to Gaimukh

(2.7 km Viaduct & 2 Stations)

J Kumar Infraprojects Limited

Current status

Sr. No.Name of Work Description Status for year 2019 to 2021[36]
21 May 2019 3 June 2019 14 June 2019 4 July 2019 6 August 2019 21 October 2019 29 November 2019 29 January 2020 8 September 2020 1 January 2021
1Soil Investigation Works Soil Investigation Work For Pier Foundation Completed 78% 80.5% 81.0% 82.0% 83.0% 85% 87%
2Utility Works Works Completed 64% 66.4% 68.2% 70% 71.36% 76%
3Piling Works Piling Work For

Foundations Completed

17% 21.2% 22.7% 25.25% 33% 37% 42.56% 47% 55.15% 62.40%
4Pile Cap Works Pile Cap Work Completed 6.5% 10.1% 12.4% 14.7% 18.60% 21% 24.75% 27.3% 35.68% 44.85%
5Pier Works Piers Cast 3.5% 5.71% 8.0% 10.2% 15.70% 18.3% 29.23% 23.6% 29.29% 38.16%
6 Pier Cap Works pier caps cast Nil Casting of Pier Cap is started

at casting yard and 0.075% casting completed till May 2019.

Casting of Pier Cap is started

at casting yard and 0.063% casting completed till June 2019

Casting of Pier Cap is started

at casting yard and 0.068% casting completed till July 2019

6% Casting completed. 10% 17.98% 22% 28.99% 40.59%
pier caps erected Nil 0.80% Erection completed. 2.4% 23.34% 12% 23.81% 31.33%
7 U Girder Works Casting yard works are in progress Nil Nil Casting of U Girder started

at casting yard and 0.21% casting completed till June 2019

Casting of U Girder started

at casting yard and 0.41% casting completed till July 2019

2.33% 6% 11.83% 16% 20.09% 33.19%
U Girder erected Nil 0.9% 4% 15.69% 29.97%
8Station work Station work in progress Nil Pile Foundation works Started since last month Works are in Progress Works are in Progress.
Mumbai Metro 4 DreamLine

Stations

32 stations are being planned on Line 4. Most of them were either in the stage of planning or under early stages of construction (as of November 2018) [37]

Green Line 4
# Station Name Status Connections Layout
EnglishMarathi
1KasarvadavaliकासारवडवलीUnder Construction Green Line 4A  (Under Construction),  Green Line 10  (Planned)Elevated
2Vijay Gardenविजय गार्डनUnder ConstructionNoneElevated
3DongripadaडोंगरीपाडाUnder ConstructionNoneElevated
4Tikuji-ni-wadiटिकुजी-नी-वाडीUnder ConstructionNoneElevated
5Manpada (Thane)मानपाडाUnder ConstructionNoneElevated
6KapurbawdiकापूरबावडीUnder Construction Orange Line 5  (Under Construction)Elevated
7MajiwadaमाजिवाडाUnder ConstructionNoneElevated
8Cadbury Junctionकॅडबरी जंक्शनUnder ConstructionNoneElevated
9Mahapalika Margमहापालिका मार्गUnder ConstructionNoneElevated
10RTO Thaneआरटीओ ठाणेUnder ConstructionNoneElevated
11Teen Haath Naka (Thane)तीन हात नाका (ठाणे)Under ConstructionNoneElevated
12Mulund Nakaमुलुंड नाकाUnder ConstructionNoneElevated
13Mulund Fire Stationमुलुंड फायर स्टेशनUnder ConstructionNoneElevated
14SonapurसोनापूरUnder ConstructionNoneElevated
15Shangrilaशांग्रीलाUnder ConstructionNoneElevated
16BhandupभांडुपUnder ConstructionNoneElevated
17Bhandup Mahapalikaभांडुप महापालिकाUnder ConstructionNoneElevated
18Naval Housingनौदल गृहनिर्माणUnder ConstructionNoneElevated
19Gandhi Nagar (Kanjurmarg)गांधी नगर (कांजूरमार्ग)Under Construction Pink Line 6  (Under Construction)Elevated
20Surya Nagarसूर्य नगरUnder ConstructionNoneElevated
21Vikhroliविक्रोलीUnder ConstructionNoneElevated
22Godrej Companyगोदरेज कंपनीUnder ConstructionNoneElevated
23Shreyas Cinemaश्रेयस सिनेमाUnder ConstructionNoneElevated
24Laxmi Nagar (Ghatkopar)लक्ष्मी नगर (घाटकोपर)Under ConstructionNoneElevated
25Pant Nagarपंत नगरUnder ConstructionNoneElevated
26Garodia Nagarगरोडिया नगरUnder ConstructionNoneElevated
27Amar Mahal Junctionअमर महाल जंक्शनUnder ConstructionNoneElevated
28Siddharth Colonyसिध्दार्थ कॉलनीUnder Construction Yellow Line 2  (Under Construction)Elevated
29Suman Nagarसुमन नगरUnder Construction Yellow Line 2  (Under Construction)Elevated
30Anik Nagar Bus Depotअणिक नगर बस आगारUnder ConstructionNoneElevated
31Wadala Truck Terminalवडाळा ट्रक टर्मिनलUnder ConstructionNoneElevated
32Bhakti Park (Wadala)भक्ति पार्क (वडाळा)Under ConstructionLine 1 (Mumbai Monorail)
 Green Line 11  (Planned)
Elevated

The car depot will be located at Owale.[3]

2 stations are being planned on Line 4A. Connected to word Gaimukh to Kasarvadavali also connect Metro 10

Green Line 4A
# Station Name Status Connections Layout
EnglishMarathi
1GowniwadaगोवनीवाडाUnder ConstructionNoneElevated
2GaimukhगायमुखUnder Construction Green Line 10  (Planned)Elevated

References

  1. "Mumbai Metro 4A".
  2. "Mumbai Metro line 4 - current status". www.mmrda.maharashtra.gov.in/. MMRDA official website. Retrieved 15 November 2018.
  3. "Everything you need to know about Metro 2B and Metro 4 | Free Press Journal". Free Press Journal. Retrieved 12 February 2017.
  4. http://www.metro-report.com/news/single-view/view/mumbai-metro-line-4-receives-aiib-funding.html
  5. "Maharashtra Cabinet Gives Go-Ahead For Two Metro Lines". NDTV.com. Retrieved 14 October 2016.
  6. "Mumbai to get two more Metro Rails". Business Standard India. 27 September 2016. Retrieved 14 October 2016.
  7. "MMRDA invites civil work bids for two Metro projects". The Times of India. Retrieved 10 February 2017.
  8. "Wadala-Thane metro line clears CRZ hurdle - Mumbai Mirror -". Mumbai Mirror. Retrieved 27 February 2017.
  9. "MMRDA plans drone survey for other Metro lines". The Indian Express. 7 March 2017. Retrieved 7 March 2017.
  10. "MMRDA plans to extend Metro-IV route from Wadala to GPO". The Times of India. Retrieved 17 March 2017.
  11. "Mumbai Metro's Thane-Wadala line likely to be extended to CST/GPO | Latest News & Updates at Daily News & Analysis". dna. 16 March 2017. Retrieved 17 March 2017.
  12. "Metro-4, 9 to be built along with flyovers". The Asian Age. 1 October 2018. Retrieved 9 October 2018.
  13. "Mumbai: MMRDA to build Metro 4 & 9 corridors along with flyovers". Free Press Journal. 4 October 2018. Retrieved 9 October 2018.
  14. Naik, Yogesh (21 May 2019). "MMRDA redrafts plans for better connectivity between Mumbai Metro corridors". Mumbai Mirror. Retrieved 6 June 2019.
  15. Berger, Louis. "Louis Berger awarded Mumbai Metro Line 4 contract in India". GlobeNewswire News Room. Retrieved 9 October 2018.
  16. "DB Engineering-Louis Berger bags contract for Mumbai Metro 4". dna. 10 April 2018. Retrieved 9 October 2018.
  17. "MMRDA invites bids for 2 metro projects". dna. 5 January 2017. Retrieved 10 February 2017.
  18. "MMRDA invites tenders for design, construction of stations, viaducts for new Metro routes". The Indian Express. 5 January 2017. Retrieved 10 February 2017.
  19. "Racing against 2021 deadline, Maharashtra opens bids for two more Metro lines". Hindustan Times. 5 January 2017. Retrieved 10 February 2017.
  20. Correspondent, Special. "MMRDA invites tenders for Metro-2B and 4". The Hindu. Retrieved 12 February 2017.
  21. "Mumbai commute to get faster, firms queue up to build two more Metro lines". Hindustan Times. 13 May 2017. Retrieved 13 May 2017.
  22. "MMRDA receives interest from domestic, foreign firms for metro". India Today. Retrieved 13 May 2017.
  23. "R Infra, 10 others bid for Metro-2B, Metro-4 corridors". Asian Age. 13 May 2017. Retrieved 13 May 2017.
  24. "Reliance Infra bags three packages of Mumbai Metro Line 4". The Economic Times. 13 April 2018. Retrieved 9 October 2018.
  25. "Tata Projects bag Rs 1,048 crore Mumbai Metro packages". The Economic Times. 13 April 2018. Retrieved 9 October 2018.
  26. Pillay, Amritha (14 April 2018). "Reliance Infrastructure, Tata Projects win bids for Mumbai Metro project". Business Standard India. Retrieved 9 August 2018.
  27. "Mumbai Metro 4A Aproved".
  28. "Mumbai Metro 4A DPR".
  29. "Mumbai Metro 4A bags civil contracts".
  30. "DB Engineering & Consulting". www.db-engineering-consulting.de. Retrieved 17 December 2018.
  31. "Louis Berger awarded Mumbai Metro Line 4 contract in India".
  32. "Hill International awarded Mumbai Metro Line 4 contract in India".
  33. "Bombardier awarded Mumbai Metro Line 4".
  34. "MMRDA Invites Bids for Mumbai Metro Line-4's Signalling & PSDs". The Metro Rail Guy. 29 April 2020. Retrieved 29 April 2020.
  35. "Mumbai Metro Green Line – Info, Route Map, Fares, Tenders & Updates". The Metro Rail Guy. Retrieved 29 March 2020.
  36. https://mmrda.maharashtra.gov.in/metro-line-4#
  37. "Mumbai Metro 4 – Wadala–Ghatkopar-Mulund–Teen Hath Naka–Kasarvadavali Station".
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.