Burbo Bank Offshore Wind Farm

The Burbo Bank Offshore Wind Farm is a 348 MW offshore wind farm located on the Burbo Flats in Liverpool Bay on the west coast of the UK in the Irish Sea. It consists of an original 90 MW wind farm commissioned in 2007 and a 258 MW extension completed in 2017.

Burbo Bank Offshore Wind Farm
Turbines Viewed From The Shore
Location of the Burbo Bank Offshore Wind Farm in Merseyside
CountryEngland, United Kingdom
LocationBurbo Flats in Liverpool Bay at the entrance to the River Mersey, Merseyside
Coordinates53°29′N 03°10′W
StatusOperational
Construction began2006
Commission date2007
Owner(s)Ørsted A/S
Wind farm
TypeOffshore
Max. water depth0.5 to 8 m (1 ft 8 in to 26 ft 3 in)
Power generation
Units operational25
Make and modelSiemens Wind Power SWT-3.6-107
Nameplate capacity90 MW
Capacity factor~30%
External links
CommonsRelated media on Commons

The wind farm was developed in the 2000s by SeaScape Energy, which was acquired by DONG Energy (now Ørsted) in 2005. A 25 turbine installation using Siemens Wind Power 3.6 MW turbines was constructed from 2005, and officially opened in 2007. A further 32 8 MW turbines were constructed in 2016–17.

Burbo Bank

Burbo Bank Offshore Windfarm with North Wales behind

In September 2002 SeaScape Energy ( Zilkha Renewable Energy, enXco A/S, Wind Prospect Ltd. joint venture.[1]) submitted an application to develop a Round 1 offshore wind farm site.[2] The site, located on Burbo Flats in Liverpool bay (~7 km northwest of Wirral and ~6 km west of the Sefton coastline) was selected due to shallow water depths (0.5 to 8m at low tide), high wind speeds ~7 m/s (23 ft/s), and a generally favourable location including proximity to an electrical grid connection. Initial expectations were for a 30 × 3 MW turbine wind farm, with monopile foundations on a site of approximately 10 km2 (3.9 sq mi). An electrical connection to the mainland grid was to be made by a seabed cable running southeast to Wirral, followed by a ~3.5 km underground cable to a substation at Wallasey.[3] SeaScape received a capital grant of £10 million in 2003 to aid development of the project.[4]

In 2003 EDF subsidiary enXCo bought the interests of Wind Prospect in the project,[5] the project became a joint venture between Elsam and EDF Energies Nouvelles in 2004 with Elsam taking 50% of the projecty.[6] In September 2005 Siemens Wind Power was selected as the turbine supplier, with 25 3.6 MW turbines ordered at a cost of over €90 million.[7][8] In December 2005 Dong Energy (now Ørsted) became sole owner of the project.[9]

The logo of Orsted who owns the wind farm.

Construction began in June 2006.[2] Contractor for the foundation installation was MT Højgaard:[10] the foundation design was by Ramboll,[11] Smulders supplied the WTG foundations,[12] turbine towers by Bladt Industries,[13] monopiles and transition pieces were from Sif;[14] piling was done by Menck,[15] with Mammoet Van Oord supplying lifting barge platform Jumping Jack.[2][16][17]

The contractor for the substation was EDF Energy Contracting, cable installation was by McNicholas Construction Services Ltd. (onshore) and Submarine Cable & Pipe (offshore), with cables supplied by ABB Group.[18] Inter turbine and grid connection to the substation was at 33 kV, with voltage step up to 132 kV at the substation for grid connection.[19]

The facility began generating power in July 2007,[2][20] and the wind farm was officially inaugurated on 18 October 2007,[21] and the facility was commercially operational by the end of 2007;[18] the capital cost of developing the wind farm was €181 million.[22]

Between 2008 and 2010, the capacity factor was between 32 and 35%.[23] In 2009 the whole wind farm was put out of action for 4 weeks due to a failure in the underground electrical cable connecting to the National Grid.[24] During summer 2010 Siemens decided to change the blade bearings on all 25 turbines as a pre-emptive measure after corrosion was found in blade bearings found on other sites.[25]

At the end of the windfarm's operational life (25 years) the wind farm will be decommissioned.[26]

Burbo Bank Extension

Burbo Bank Extension
Country
  • United Kingdom
Coordinates53.48°N 3.26°W / 53.48; -3.26
StatusOperational
Commission dateApril 2017
Wind farm
Typeoffshore
Max. water depth6 to 13 m (20 to 43 ft)
Power generation
Units operational32
Make and modelV164 8.0 MW
Nameplate capacity258MW
External links
CommonsRelated media on Commons

Planning, funding and design

In 2009 the Crown Estate announced that wind farm operators could apply for extensions to their Round 1 or Round 2 offshore wind farms; DONG Energy identified Burbo Bank as a potential site and began consultation on a ~90 km2 (35 sq mi) extension westwards of the original wind farm. Between 2009 and 2010 the area of the site was reduced to the north increase clearance from the shipping lanes to the Port of Liverpool; to the south and to the west, reducing potential impact on recreational sailing activities and on certain species of sea bird, and due to potential conflicts with ship anchoring sites; also reducing the visual impact from land. In April 2010 the Crown Estate awarded an area of 40 km2 (15 sq mi) for lease.[27]

Water depths in the area are between 6 and 13 metres (20 and 43 ft).[28] The sea bed consisted primarily of sand.[29] The underlying geology is sand overlaying clay overlaying mudstone. Samples within the turbine area showed sand followed by clay down to around 30m before weak mudstone was found.[30]

The initial cable export route and grid connection identified was one making landfall near to the existing Burbo Bank land connection, and connected to a 275 kV substation in Birkenhead; subsequently a potential grid connection at the 400 kV Deeside substation (near Deeside Power Station, Wales) was identified; and later a connection with landfall at Ffrith Beach, (nr. Prestatyn, Wales) to an extension of the new Bodelwyddan 400 kV substation under construction for the Gwynt y Môr Offshore Wind Farm. In 2011 the developer reached an agreement with the National Grid to use to a connection near the Bodelwyddan substation.[31]

The planned export cable route crossed a number of pre-existing cables and pipelines: a set of pipelines related to the Liverpool Bay oil and gas field, connecting the Douglas Complex to landfall were crossed in the Mid-Hoyle channel[32] the export cable route also ran close to the North Hoyle Offshore Wind Farm export cable;[33] and crossed the 500 MW East–West Interconnector, as well as the planned route of the 2000 MW Western HVDC Link.[34]

Initial expectations were for construction to start in early 2015, and be complete by early 2017, subject to final specifications;[35] neither foundation nor turbine type was specified,[36] an offshore substation to step up the inter turbine voltage (either 33 or 66 kV) to an export voltage of either 132 or 275 kV, connection to the National Grid would be made at 400 kV, stepped up at an onshore substation at Bodelwyddan.[37]

The wind farm extension received contract for difference renewable energy subsidy funding from the UK government in April 2014,[38] with a strike price of £150 per MWh (2012 prices).[39] DONG made the decision to proceed with construction of the wind farm in December 2014.[40]

DONG Energy (now Ørsted) sold half of the wind farm extension to KIRKBI A/S (Lego holding company) and Danish pension fund PKA for £660 million in February 2016.[41]

Svanen, lifting ship, Burbo Banks Offshore Windfarm Extension

Construction

In early 2014, DONG Energy announced that the Vestas' V164 8.0 MW turbine was the preferred model for the development,[42] and made preliminary agreements to buy 32 units in August 2014.[43] The order for 32 turbines was confirmed in December 2014, the first series production of the type.[44] The nacelles are to be produced at the former Odense Steel Shipyard, while the blades are made at Vestas' Isle of Wight facilities. Assembly will take place in Belfast.[45]

In August 2014 ABB was awarded the contract to supply export cables.[46] Suppliers for inter array cabling was Nexans;[47] DONG Energy having agreed to a long-term supply arrangement for inter array cabling with Nexans in August 2014.[48]

In January 2015 RXPE (Rongxin Power Engineering) was awarded the design and build contract for the Burbo 2 extension Dynamic Reactive Compensation electrical equipment (STATCOM);[47] and Bladt Industries and EEW obtained the contract to construct wind turbine foundations and structures, with transition pieces to be manufactured by Bladt/EEW jv Offshore Structures (Britain) Ltd. (former TAG Energy Solutions plant in Billingham, UK), and by Bladt at Aalborg (Denmark) with monopiles made at EEW's factory in Rostock (Germany).[49]

In April 2015 A2SEA was contracted to for turbine installations,[50][51][52] and Jan De Nul contracted to install the offshore export cable.[53] In June 2015 Van Oord were contracted for foundation installation.[54][55] In October 2015 DONG Energy's two 200 tonne transformers were delivered by Collett & Sons Ltd[56] to the onshore substation via 550 Tonne capacity girder bridge. In early 2016 DONG Energy acquired a lease on Cammell Laird's yard in Birkenhead to be used as a base during the construction of the wind farm.[57]

The first 8MW turbine was installed in September 2016.[58] The wind farm extension was commissioned in April 2017.[59]

After around 20–25 years of operation the wind farm would be expected to be decommissioned, including removal off all offshore components above seabed level.[60]

See also

References

  1. Non-Technical Summary (SeaScape Energy, 2002) p. 2
  2. Burbo Bank 1 Offshore Wind Farm (Lorc) Timeline & Track records
  3. Non-Technical Summary (SeaScape Energy, 2002) pp. 2–4
  4. "More offshore plant go ahead", windpowermonthly.com, 1 December 2003
  5. "British consents for four in North Sea", windpowermonthly.com, 1 November 2003, Enxco - a subsidiary of French energy company EdF, bought out the interests of small developer Wind Prospect in their joint development at Burbo Bank
  6. "Nuclear utility with a wind portfolio", windpowermonthly.com, 1 September 2005, EDF Energies Nouvelles' offshore ambitions are closer to fruition in Britain, where work should start next year on the 90 MW Burbo Offshore plant in Liverpool Bay. The project is being developed by Seascape Energy Ltd, owned jointly by EDF Energies Nouvelles and Danish electricity company Elsam, which bought a 50% stake of the project in 2004
  7. "Elsam og EDF Energie Nouvelle, køber offshore møller hos Siemens til engelsk projekt" (PDF), Press release (in Danish), Elsam, 21 September 2005
  8. "Siemens' first turbine order for UK waters", windpowermonthly.com, 1 October 2005
  9. Burbo Bank (4C Offshore) Developers/Owners/Operators
  10. "Burbo Bank Offshore Wind Farm", mth.com, archived from the original on 24 April 2014, retrieved 24 April 2014
  11. "Burbo Bank offshore wind farm", ramboll.co.uk, retrieved 24 April 2014
  12. "Burbo Project", smulders-hoboken.com, archived from the original on 24 April 2014, retrieved 24 April 2014
  13. "Arklow Bank & Burbo Bank Offshore Windfarms Towers", stateofgreen.com, archived from the original on 24 April 2014, retrieved 24 April 2014
  14. References - Offshore Wind (PDF), Sif, archived from the original (PDF) on 24 April 2014, retrieved 23 April 2014
  15. "Reference Projects -Burbo Bank", menck.com, archived from the original on 24 April 2014, retrieved 24 April 2014
  16. de Vries, Eize (1 May 2007), North Sea construction: Installing monopiles for the Dutch Q7 offshore wind farm
  17. Verrinder, James (1 December 2006), "Wind it on", International Cranes & Specialised Transport, archived from the original on 24 April 2014
  18. Vestergaard 2007, p. 5.
  19. Burbo Offshore Wind Farm, River Mersey, Liverpool Bay, United Kingdom (www.renewable-technology.com)
  20. Vestergaard 2007, p. 6.
  21. "Inauguration of DONG Energy's Burbo Bank offshore wind farm" (Press release). DONG Energy. 18 October 2007. Archived from the original on 7 April 2008.
  22. Kaiser, Mark J.; Snyder, Brian (2012), Offshore Wind Energy Cost Modeling: Installation and Decommissioning, Springer, Table 8.1, p.138
  23. UK Renewable Energy Data - Monthly Generation Statistics, April 2002 – March 2010 (PDF), Renewable Energy Foundation, August 2010, pp. 95–96
  24. Dunn, Justin (16 October 2009), "EXCLUSIVE: Burbo Bank wind farm off Wirral shore out of action for four weeks after cabling failure", wirralglobe.co.uk
  25. Godske, Bjørn (24 August 2010), "Korrosion tvinger Siemens til skift af vingelejer i havmøller" [Corrosion forces Siemens to replace bearings in Wind Turbines], Ing.dk (in Danish), archived from the original on 27 August 2010, retrieved 25 August 2010
  26. Non-Technical Summary (SeaScape Energy, 2002) p. 4
  27. (5.1.1.5) Site Selection and Alternatives (Dong) sec.5.3.3-5.3.14, fig.5.1, 5.2
  28. EIA Scoping report 2010, §2.3, 3.2.2.1.
  29. EIA Scoping report 2010, §3.2.2.2.
  30. Summary of Geotechnical Investigations for the Burbo Bank Extension Project and Comparison of These to Preliminary Geophysical Survey and Interpretation (PDF), Dong Energy, 26 July 2013, archived from the original (PDF) on 23 February 2016, retrieved 15 February 2016
  31. (5.1.1.5) Site Selection and Alternatives (Dong) sec.5.3.15-5.3.30 , fig.5.3, 5.4
  32. (5.1.2.23) Other Infrastructure and Licensed Activities (Dong) sec.23.6.13, fig.23.5 Oil and gas infrastructure
  33. (5.1.2.23) Other Infrastructure and Licensed Activities (Dong) sec.23.6.21, fig.23.6 Telecommunication and power cables
  34. (5.1.2.23) Other Infrastructure and Licensed Activities (Dong) sec.23.6.25-23.6.26, fig.23.6 Telecommunication and power cables
  35. (5.1.1.6) Project Description (Dong) sec.6.3
  36. (5.1.1.6) Project Description (Dong) sec.6.6, 6.7
  37. (5.1.1.6) Project Description (Dong) sec.6.8.3, 6.8.23, 6.10
  38. "UK awards contracts for 4.5GW", renews.biz, 23 April 2014, archived from the original on 20 February 2016, retrieved 15 February 2016
  39. State aid SA.38758 (2014/N), SA.38759 (2014/N), SA.38761 (2014/N), SA.38763 (2014/N) & SA.38812 (2014/N) – United Kingdom - Support for five Offshore Wind Farms: Walney, Dudgeon, Hornsea, Burbo Bank and Beatrice (PDF), European Commission, 23 July 2014, Table 2, pp.4-5c ; § 29
  40. DONG Energy skal opføre Burbo Bank Extension Havmøllepark i Storbritannien (Press release) (in Danish), 19 December 2014, archived from the original on 24 March 2017, retrieved 24 December 2014
  41. -sells-half-of-burbo-bank-extension-to-pka-lego/ "DONG Sells Half of Burbo Bank Extension to PKA, LEGO" Check |url= value (help), offshorewind.biz, 11 February 2016
  42. "Dong Taps Vestas for Burbo Bank Offshore Wind", breakbulk.com, 24 February 2014, archived from the original on 24 April 2014, retrieved 23 April 2014
  43. Snieckus, Darius (21 August 2014), MHI Vestas 8MW gets Burbo deal
  44. "Nu starter Vestas produktion af gigantisk havvindmølle", Børsen (in Danish), 22 December 2014
  45. Bredsdorff, Magnus (22 December 2014), "Nu indleder Vestas serieproduktion af verdens største havmølle", Ingeniøren (in Danish)
  46. "ABB's Cables for Dong's Burbo Bank Extension OWF", subseaworldnews.com, 13 August 2014
  47. "Chinese land Burbo 2 electricals", renews.biz, 8 January 2015, archived from the original on 12 January 2015, retrieved 8 January 2015
  48. "DONG Energy, Nexans Ink Offshore Wind Cable Deal (UK)", subseaworldnews.com, 27 August 2014
  49. "EEW, Bladt win Burbo 2 foundations", renews.biz, 27 January 2015, archived from the original on 23 February 2016, retrieved 15 February 2016
  50. "A2SEA SIGNS CONTRACT FOR BURBO BANK EXTENSION OWF", a2sea.com (press release), 24 April 2014
  51. "A2SEA's 'SEA CHALLENGER' to Install Burbo Bank Extension Turbines", offshorewind.biz, 24 April 2015
  52. "A2Sea to tackle Burbo 8MW giants", renews.biz, 24 April 2015, archived from the original on 23 February 2016, retrieved 15 February 2016
  53. "Jan De Nul Wins Burbo Bank Extension Wires", offshorewind.biz, 21 April 2015
  54. "Van Oord signs contract for Burbo Bank Extension offshore wind farm", vanoord.com (press release), 25 June 2015
  55. "Van Oord to Install Burbo Bank Extension Foundations", offshorewind.biz, 24 June 2015
  56. Aspinall, Shell. "Transforming Burbo Bank Wind Farm". Collett & Sons. Retrieved 12 February 2019.
  57. DONG Energy secures construction base for latest wind farm (press release), Dong Energy, 27 January 2016
  58. "First 8MW giant up at Burbo 2", renews.biz, 8 September 2016
  59. http://renews.biz/106837/showtime-at-burbo-2/
  60. (5.1.1.6) Project Description (Dong) sec.6.14

Sources

Burbo Bank

Burbo Bank Extension

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.