Brightline
Brightline is a privately run inter-city rail route between Miami and West Palm Beach, Florida. Brightline began operating over its current route in January 2018 and the company is currently building an extension to the Orlando International Airport which is expected to enter service in 2022.
Brightline train at Fort Lauderdale station in December 2017 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Overview | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Service type | Inter-city rail Higher-speed rail (after 2022) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Status | Temporarily suspended | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | Florida | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
First service |
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Current operator(s) | Florida East Coast Industries | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Ridership | 885,000 (2019) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Website | www | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Route | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Start | Miami | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stops | 3 operational, 1 planned, 3 proposed | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
End | Orlando (planned) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Distance travelled | 240 mi (390 km) (includes service to Orlando) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Average journey time | Miami–West Palm Beach: 1 hour Miami–Orlando: 3 hours (planned) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service frequency | Weekdays: hourly Weekends: hourly to bi-hourly | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line(s) used | Florida East Coast Railway | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
On-board services | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Disabled access | Level boarding | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Seating arrangements |
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Catering facilities | Onboard service carts | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Entertainment facilities | Wi-Fi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Baggage facilities | Checked baggage available | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Rolling stock |
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 4 ft 8 1⁄2 in (1,435 mm) standard gauge | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating speed |
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track owner(s) | Florida East Coast Railway | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
As of August 2020, it is the only privately owned and operated intercity passenger railroad in the United States. The line was developed starting in March 2012 as All Aboard Florida by Florida East Coast Industries, a Florida real estate developer owned by Fortress Investment Group. Construction began in November 2014 on stations and improvements to tracks owned by the Florida East Coast Railway, which at the start of construction, was also owned by Fortress (it was sold in January 2018).
Fortress Investment Group is also investing in the construction of Brightline West, a high speed rail route between Las Vegas and Southern California. The route is being advertised as “A Brightline Company.”
In late 2018, it was announced that Virgin Group would become a minority investor in the railroad and would provide rights to rebrand the service as Virgin Trains USA. In August 2020, railroad managers announced that Virgin had not provided the agreed investment money and the company would be ending its branding deal, returning to the previous Brightline brand.
Origins and history
In 2012, Florida East Coast Industries (FECI) announced plans to operate passenger rail service between Miami and Orlando.[1] The construction was projected at the time to be $1.5 billion.[2] In March 2013, All Aboard Florida applied for a $1.6 billion Railroad Rehabilitation & Improvement Financing (RRIF) loan, which was administered by the Federal Railroad Administration,[3] and in late 2014, the company applied for a $1.75 billion private activity bond allocation, with proceeds from the bond sale substantially reducing or replacing entirely the amount of the RRIF loan request.[4]
The company received a Finding of No Significant Impact from the Federal Railroad Administration in January 2013, effectively clearing way for work to begin between Miami and West Palm Beach.[5] The Final Environmental Impact Statement was released on August 4, 2015.[6] By the beginning of 2015, the company had started site work at the Miami, Fort Lauderdale and West Palm Beach stations, plus right of way improvements along stretches of the corridor. On November 10, 2015, All Aboard Florida announced that the service would operate under the name Brightline.[7]
Service between Miami and West Palm Beach began on May 19, 2018.[8][9]
In September 2018, Brightline acquired XpressWest, a private company that intends to connect Las Vegas with Southern California via Victorville, California. Brightline announced the intent of purchasing 38 acres of land near the Las Vegas Strip for a station and following the Interstate 15 corridor from Las Vegas to Southern California.[10]
In November 2018, it was announced that Virgin Group would become a minority investor in the railroad and would provide rights to rebrand the service as Virgin Trains USA.[11]
Two key counties on the coastal route north of the West Palm Beach station have, for various reasons, been fighting the extension of the rail line through Martin and Indian River Counties in court. One of their objections is that Brightline is owned by a private corporation, so they should not be allowed to issue tax-exempt bonds as if they were a municipality. On December 24, 2018, after four years of legal battles,[12] a Federal District Judge threw out a suit by Indian River County that claimed the U.S. Department of Transportation improperly approved the bond allocation, clearing the way for construction of the new rail corridor through the Treasure Coast and Space Coast.[13][14] On October 5, 2020, the US Supreme Court declined to hear the appeal of that decision, ending Indian River County's efforts to stymie development. The County's efforts at a Supreme Court hearing were financed with over $200,000 in private donations in addition to over $4 million in County funds. [15]
In April 2019, the company secured $1.75 billion in funding for the Orlando extension and said construction would begin right away.[16][17][18]
In August 2020, railroad managers announced that Virgin had not provided the agreed investment money and the company would be ending its branding deal, returning to the previous Brightline brand.[19][20][21]
Construction
Construction began on the Miami to West Palm Beach section with the laying of new tracks and closure of the temporary surface lots in Government Center, Downtown Miami, in mid 2014.[22] Preliminary work on the Miami station, such as site preparation and demolition, began later in the year.[23] Suffolk Construction was the general contractor for the Miami station.[24] Piles were being set on the four lots of MiamiCentral in early 2015.[25]
On October 29, 2014, work on the Fort Lauderdale station began with the demolition of existing buildings on the site.[26] A groundbreaking ceremony for the West Palm Beach station was held in November 2014.[27] Moss & Associates, of Fort Lauderdale, was the general contractor for the West Palm Beach and Fort Lauderdale stations.[28]
In January 2015, crews started replacing track throughout the corridor.[29][30] All Aboard Florida secured leasing of easement rights alongside the Beachline from the Central Florida Expressway Authority for $1.4 million in December 2015.
Construction work on Phase 2, between West Palm Beach and Orlando, officially began in June 2019, with a groundbreaking ceremony at Orlando International Airport.[31] Preliminary work on the corridor began in September 2019, in the area of Jensen Beach and Sebastian,[32] and begin path clearing for construction of the Orlando-to-Cocoa portion in October of that year.[33]
As of May 2019, the contractors on the project were the Hubbard Construction Company, Wharton-Smith Inc., The Middlesex Corporation, Granite, and HSR Constructors. These five contractors are responsible for the development of 170 miles of new track into the completed state-of-the-art intermodal facility located in the new South Terminal at the Orlando International Airport (MCO).[34]
Opening
Public operations between West Palm Beach and Fort Lauderdale began Saturday, January 13, 2018.[35][36] Services between West Palm Beach and Miami began on May 19, 2018.[8][9]
Closing during the COVID-19 pandemic
Brightline suspended operations on March 25, 2020, due to the COVID-19 pandemic.[37] Construction north to Orlando continued.[38][39]
Service
Route
The route is made up of the following stations, from north to south:
County | Station | Brightline in-service date |
Time to Miami |
Connections |
---|---|---|---|---|
Orange County | Orlando Airport | 2022 (planned) | 3 hr | Orlando International Airport Lynx: Links 11, 42, 51, 111, 407 & 436S SunRail Train to Plane: Link 111 Nonstop Express |
Palm Beach County | West Palm Beach | January 13, 2018 | 1 hr | Palm Tran: 1, 40, 41, & The Bolt 1 Palm Trolley: Yellow Line Tri-Rail Commuter Connector: WPB-1 |
Broward County | Fort Lauderdale | January 13, 2018 | 30 min | Broward County Transit (at Central Terminal): 1, 6, 9, 10, 11, 14, 20, 22, 30, 31, 40, 50, 60, 81, US 1 Breeze Sun Trolley: Downtown Link, Neighborhood Link, & NW Community Link Tri-Rail Commuter Connector: FL-1, FL-3 |
Miami-Dade County | MiamiCentral | May 19, 2018[8][9] | – | Metrorail (at Government Center): Green Line, Orange Lines, Downtown Express Metromover (at Government Center): Omni Loop, Brickell Loop, Inner Loop Metrobus: 2, 3, 7, 9, 11, 21, 51, 77, 93, 95, S (119), 120, 207, 208, 246, 277, 500 Broward County Transit (at Government Center): 95, 595 Miami Trolley: Coral Way Tri-Rail Downtown Miami Link (planned) |
Schedule
As of January 2019, between Miami and West Palm Beach, there are 17 round trips Monday through Friday, ten on Saturdays, and nine on Sundays.[40]
Ridership
During the first two and a half months of introductory service between West Palm Beach and Fort Lauderdale, ridership totaled 74,780, increasing from 17,800 in January to 32,900 in March 2018.[41] The company itself announced that the ridership has been triple to what had been expected.[42] The forecast provided to bond investors calls for 240,000 passengers per month by 2020, which includes service to Miami,[43] and analyst Fitch Ratings has said that the company could break even at 56% of their ridership forecast.[42]
By the end of 2018 almost 600,000 passengers had ridden the train,[44] and the line welcomed its 1 millionth rider in August 2019.[45]
Stations
The three South Florida stations were designed by Skidmore, Owings & Merrill in association with Zyscovich Architects.[47] Rockwell Group designed the interiors.[48] All three have adjacent parking garages that offer parking at the rate of $6 per day, eff. July 1, 2018.[49]
Miami
The downtown Miami station, known as MiamiCentral (not to be confused with Miami Central Station, now known as Miami Intermodal Center, near Miami International Airport), spans 9 acres (3.6 ha) located just east of Miami-Dade County Hall and includes 3 million square feet (280,000 m2) of mixed-use development with residential, office and commercial, and a retail concourse. The station connects Brightline with the Metrorail, Metromover, County bus and City of Miami trolley systems.[50] The new Brightline station connects the following transit modes: 2 Metrorail stations, 2 Metromover stations, Metrobus, and the future Tri-Rail station. This increases connections to activities and tourist destinations, including the Performing Arts Center, Bayside Market and Bayfront Park. Service to Miami began on May 19, 2018.[8][9]
Fort Lauderdale
The Fort Lauderdale station is located at NW 2nd Avenue between Broward Boulevard and NW 4th Street. The four-acre station site has a 60,000 sq ft (5,574 m2) station and platform. The Brightline train service in Ft. Lauderdale connects to the Sun Trolley and Broward County Transit system.[51] Brightline also owns about three acres of land to the east of the Florida East Coast Railway corridor, where there are plans to build a transit-oriented development.[52]
West Palm Beach
The West Palm Beach station is located between Datura and Evernia Streets and to the west of Quadrille. The two-acre station site has a 60,000 sq ft (5,574 m2) station and platform that connect with the neighborhood's existing vehicular, trolley and pedestrian networks and establish links to the Tri-Rail, Palm Tran Downtown Trolley and Amtrak West Palm Beach station.[53]
Planned & proposed routes and destinations
Orlando
In 2017, the new Orlando International Airport Intermodal Terminal at Orlando International Airport was opened.[54] Brightline will terminate at this station once the 170-mile Orlando Extension track is built. Service is projected to begin in 2022, with trains travelling up to 125 miles an hour and a commute time of approximately three hours from Orlando’s airport to Miami.[55][56]
On November 23, 2020, Brightline and Walt Disney World announced an agreement to build a station at Disney Springs. The station would be built as part of the Tampa extension, so it would open later than the service to Orlando International Airport.[55]
Tampa
As of September 2019, Brightline is in negotiations with the Florida Department of Transportation (FDOT) to lease right-of-way along the Interstate 4 corridor.[57] Brightline was the only bidder to submit a proposal to construct an intercity rail line along Interstate 4, which has been designated for federally funded high-speed rail.[57] This would be utilized for an extension of the line from Orlando International Airport to Tampa.[57] Potential stops along this route are the SunRail Meadow Woods station, Walt Disney World, and Lakeland.[57] The current deadline for the negotiations between Central Florida Expressway Authority, FDOT, and Virgin was March 31, 2020.[58] In September 2020, the railroad entered into a memorandum of understanding with a local developer to potentially construct the terminal station in Ybor City.[59]
Jacksonville
As part of the initial construction for Brightline, All Aboard Florida said it was considering an extension to Jacksonville, Florida.[60]
Boca Raton
In 2019, Brightline operations sent a letter to the city of Boca Raton about the possibility of adding their city as an infill station along the Florida route. Virgin proposed constructing the station and rail infrastructure while the city would cover access and zoning requirements and costs.[61] In December 2019, Boca Raton was officially chosen as a station site with the station, to be connected to Mizner Park via pedestrian bridge.[62][63] The station is scheduled to be completed in 2022.[64]
Aventura
In October 2019, Miami-Dade County allocated $76 million to build Aventura station at the Aventura Mall in Aventura, Florida, between Miami and Fort Lauderdale. At the time of the announcement, the projected opening date was October 2020.[65] Groundbreaking on the station occurred in September 2020, with a new projected completion date in fall 2021.[66]
PortMiami
In October 2019, Brightline announced plans to start building a station in PortMiami in 2020.[63][67]
Future expansion
Brightline has expressed interest in adding a station on Florida's Treasure Coast and another on the Space Coast between West Palm Beach and Orlando. In August 2018, the company asked cities in the area to submit proposals for station locations. Fort Pierce, which last had passenger train service on July 31, 1968, has expressed interest.[68][69] The city of Stuart has also indicated that it will be negotiating for a potential station.[70]
Brightline has indicated that Stuart is the most likely location for a Treasure Coast station, and that Cocoa would make the most sense for a Space Coast station, both because of proximity to Port Canaveral's cruise lines as well as for positioning for future expansion to Jacksonville.[71] Neither station has been committed in writing, and both are pending market studies, as completion of the line to Orlando is the top priority for Brightline.
In 2020, it was revealed that Brightline was planning a commuter rail service to complement the higher-speed line. Trains would run between Miami Central and Aventura with up to five stations between.[72][73] The railroad and the Miami-Dade County Commission agreed to access fees in November 2020.[74]
Brightline West
On September 18, 2018, Fortress Investment Group announced that it would acquire XpressWest, a venture capital proposal to build a privately funded high-speed rail passenger train from Apple Valley, California to Las Vegas, Nevada from hotel developer Marnell Corrao Associates.[75][76][77] When Fortress subsequently entered into its partnership with Virgin Group in 2019, it was announced that the newly formed consortium will build and operate XpressWest when it opens.[78] In September 2020, Fortress Investment Group renamed the project Brightline West.
Fortress plans on constructing the 180-mile long Brightline West track by 2023. This 85-minute commute aims to carry passengers at speeds of up to 200 miles per hour. Trains on this line will be fully electric and run alongside Interstate 15. Fortress' Wes Edens has stated that Brightline’s service is modeled off of Eurostar's Paris-to-London commute. Its coach design includes white-and-blue interiors, roomy seating, and free Wi-Fi.[56]
Engineering
Train speeds
Upon full buildout of the Miami–Orlando route, trains will operate at up to 79 mph (127 km/h) between Miami and West Palm Beach, up to 110 mph (177 km/h) between West Palm Beach and Cocoa, and up to 125 mph (201 km/h) between Cocoa and the Orlando International Airport.[79] A future extension to Tampa from Orlando would, if constructed, also allow trains to operate at up to 125 mph (201 km/h).[80] It will be one of the few rail services in the United States to approach the high-speed rail standard set by the International Union of Railways of 250 km/h (155.3 mph) for new rail or 200 km/h (124.3 mph) for existing lines.[81]
The planned travel time between Miami and Orlando is 3 hours.[82] Driving between the two takes 3 1⁄2 hours using the Florida's Turnpike, and 3 3⁄4 hours using the I-95/SR 528 freeways along the planned train route via Cocoa. The flight time between MIA and MCO is one hour.
To meet the 3 hour schedule, trains will have to operate with an overall average speed of 80 miles per hour (130 km/h), which is similar to the overall average speed of the Acela Express operating on the Northeast Corridor between New York City and Washington, D.C.[83][84][85]
Pre-existing Miami–Cocoa Corridor upgrades
The project calls for more than $1.5 billion in upgrades to the rail corridor between Miami and Cocoa. The company is double tracking the corridor, improving signaling systems, and upgrading every grade crossing to meet the highest applicable safety standards set by FDOT and Federal Railroad Administration.[86][87] In January 2013, the Federal Railroad Administration issued a Finding of No Significant Impact (FONSI) for the Miami–Cocoa phase of the project, effectively clearing the way for work to begin.[88] Part of the corridor safety upgrades includes installing positive train control (PTC), which will enhance Brightline's ability to monitor and control train movements safely.[89]
Quiet zones
Responding to citizen concerns about increased noise from additional horns, the company stated that it will work with local communities to implement quiet zones where possible.[90] Federal law requires quiet zone requests to originate from the local authority that has jurisdiction over the roadway, not the railroad company.[91]
In August 2014, the company announced a partnership with the Broward and Palm Beach Metropolitan Planning Organizations to implement quiet zones between the city of Hallandale Beach and 15th Street in West Palm Beach.[92] In December 2014, the Miami-Dade Metropolitan Planning Organization approved funding to construct quiet zones between PortMiami and the northern Miami-Dade County line.[93] The quiet zones were originally planned to be in place when Brightline becomes operational between Miami and West Palm Beach by the end of 2017. Brightline started service on January 11, 2018, but various delays in constructing the quiet zones have stretched their in-service date to sometime in March.[94]
On May 14, 2018, quiet zones went into effect in West Palm Beach, in Lake Worth on May 21 and in Boca Raton on May 30. The “no train horn” areas apply to all trains, freight and passenger.[95] Quiet Zones remove the legal duty of a train engineer to sound the horn. Train engineers do still use the horn in quiet zones for emergency situations (such as a trespasser fouling the tracks).[96]
Bridges
The FEC rail corridor includes a number of fixed-span bridges that will be replaced as part of the project. Most do not require United States Coast Guard (USCG) permitting as they do not span significant navigable waterways and clearances will not change. Twelve other bridges—St. Johns River, Eau Gallie River, St. Sebastian River, Crane Creek, Turkey Creek, West Palm Beach Canal, Boynton Canal, Middle River (both the North and South Fork), Oleta River, Arch Creek and Hillsboro Canal—will require permitting by the USCG. In addition, the project calls for significant investment and upgrades to three movable bridges: St. Lucie, Loxahatchee, and New River. These improvements will ensure that bridge mechanical systems for raising and lowering the bridge spans are either fully upgraded or replaced. The company has stated that, prior to it becoming operational, it will start to regularly notify mariners of scheduled bridge closings via the internet, smart phone application and countdown signage on the bridges to enable mariners to have real-time information to decrease wait times at each bridge. Also, the company will station a bridge tender at the New River bridge.[97]
Deaths
During the first six days of operation, two people were killed in separate incidents at railroad crossings along the line, after they attempted to cross the tracks while the gates were down.[98]
During the first three months of operation, four people were killed by a Brightline train when they crossed the tracks illegally, with an additional three persons injured.[99]
The 11th fatality associated with a Brightline train occurred on January 1, 2019, after a pedestrian was struck and thrown into a canal.[100] As of November 16, 2019, according to the advocacy group Alliance for Safe Trains, a total of 34 people had been killed in incidents involving Virgin Trains locomotives in Florida,[101] although those include what are likely to have been suicides.[102]
In December 2019, the AP produced a story based on FRA data that Virgin Trains USA had the worst per-mile death rate of the nation's 821 railroads. It stated that none of the deaths were the fault of the company.[103]
Cocoa–Orlando
The proposed line between Cocoa and Orlando is the only segment that does not have existing track or right-of-way owned by FEC. Originally, the Central Florida Expressway Authority (CFX) believed it could accommodate building new tracks for the project within the BeachLine Expressway's 300-foot (91 m) wide right-of-way. This segment of the proposed line will operate at speeds of up to 125 mph (201 km/h).[104][105]
CFX began negotiations with Deseret Ranch, which owns the land just south of the BeachLine, to purchase additional land in order to widen the right-of-way. According to a pact made on July 16, 2013, CFX tentatively agreed to pay $12 million for an extra 200 ft (61 m) along the 22-mile (35 km) BeachLine corridor between Cocoa and Orlando International Airport.[106] In early October 2013, CFX and All Aboard Florida reached a formal purchase agreement for the land required for the right-of-way. Although construction was slated to originally begin in early 2015, construction of the segment started on May 22, 2019.[107][108]
Also in October 2013, the Greater Orlando Aviation Authority (GOAA) board approved development of a station and maintenance facility on Orlando International Airport property, as well as an easement to build track between the station and the mainline to the coast.[109]
Maintenance
Brightline is constructing two maintenance facilities. One is a Running Repair Facility, located north of the West Palm Beach station at 601 15th Street, designed for maintenance and minor repair work that does not require the train to be removed from service. The 12-acre site has been under construction since at least January 2016. The land includes vintage industrial buildings that will be renovated for the workshop. The facility, named "workshop b," will include a maintenance pit for access to the underside of the trains and will be able to handle four 10-car train sets.
More extensive maintenance/repair will be accomplished at a second site near the Orlando International Airport Intermodal Terminal.[110]
Technical
Rolling stock
All Aboard Florida ordered five Siemens trainsets in 2014. Each Brightline trainset initially consisted of four passenger coaches, with a Siemens Charger SCB-40 diesel-electric locomotive on each end.[111][112] The coaches, with interiors designed by the LAB at Rockwell Group,[113] feature ergonomic seating, Wi-Fi, level boarding, and meet ADA compliance standards. Each trainset holds 248 passengers.[8] Working with All Aboard Florida, the LAB also conceived the Brightline name, brand platform, and visual identity.[114] The entire trainset, including passenger cars, were manufactured by Siemens in its solar-powered plant in Florin, California. Once the route to Orlando is in operation, the trainsets will be expanded to seven coaches, and five more complete trainsets will be purchased.[115][116] The first of five trainsets departed the Siemens factory on December 8, 2016,[117] and arrived in West Palm Beach on December 14.[118] The fifth trainset arrived in South Florida in October 2017.[119]
The trains offers two classes of service, with one "Select" coach and three "Smart" coaches on each trainset. "Select" offers 2x1 and four-to-a-table seating with 50 21-inch (530 mm)-wide seats per car and complimentary snacks and beverages, while the slightly less expensive "Smart" fare coaches seat 66 with narrower 19-inch (480 mm)-wide seats, with snacks and beverages available for purchase.[120][121] Each trainset is able to hold 248 passengers.[8]
Photo | Year | Model | Total | Power | Weight |
---|---|---|---|---|---|
2017 | Siemens Charger SCB-40 locomotives | 10 units[112] | 4,000 hp (3,000 kW)[122] | 264,556 lb (120,001 kg)[123] | |
2017 | Siemens Venture trainsets | 5 trainsets of 4 cars (20 cars total)[124] | unpowered | TBD |
References
- "All Aboard Florida plan announced". Railway Gazette. March 28, 2012. Retrieved April 8, 2018.
- "Quiet zones plans for FEC tracks get boost, as All Aboard Florida picks up costs for some safety upgrades". Palm Beach Post. September 19, 2013.
- "All Aboard Florida seeks federal loan". Orlando Sentinel. March 18, 2013. Retrieved March 23, 2013.
- "All Aboard Florida shocker: Rail seeks private financing". Palm Beach Post. October 8, 2014.
- "High-speed rail service heads south". Florida Today. Associated Press. July 9, 2014.
- "All Aboard Florida Final Environmental Impact Statement". Federal Railroad Administration. August 4, 2015.
- "All Aboard Florida unveils branding of its rail service". The Real Deal Miami. November 9, 2015. Retrieved November 10, 2015.
- Roustan, Wayne K. (May 19, 2018). "All aboard as Brightline launches fast train service to Miami". Sun-Sentinel. Retrieved May 20, 2018.
- Jacoby, Kenny (May 19, 2018). "Brightline's inaugural West Palm-to-Miami trip draws crowd, celebration". Retrieved May 20, 2018.
- "Brightline to Build Express Intercity Passenger Rail Connecting Southern California and Las Vegas" (Press release). Brightline. September 18, 2018.
- Cohen, Howard (November 16, 2018). "Brightline forms a partnership with Virgin. A name change is coming soon". Miami Herald.
- "Brightline spending reaches $7.2 million in Martin, Indian River counties, but for what?". TCPalm (Treasure Coast Newspapers). Retrieved November 12, 2018.
- Rosenberg, Arnie (December 25, 2018). "Judge tosses out Indian River County's lawsuit against All Aboard Florida". TCPalm.
- "Florida's Brightline clears legal hurdle, gets financing extension". Bond Buyer.
- Soloman, Joshua (October 5, 2020). "U.S. Supreme Court won't hear Indian River County's appeal of Brightline lawsuit". TCPalm.
- Forester, Thomas (April 4, 2019). "Brightline secures funding to Orlando, plans to open Walt Disney World station". WPEC.
- Lyons, David (April 4, 2019). "Virgin Trains lines up funding for expansion to Orlando". Sun Sentinel.
- "Virgin Trains finally set to launch construction of West Palm Beach-to-Orlando link". miamiherald.
- "Florida Luxury Train Cuts Branson Ties, Drops Virgin Name". Bloomberg Media. August 7, 2020.
- Ohnsman, Alan (August 7, 2020). "High-Speed Rail Startup Brightline Ends Alliance With Richard Branson's Virgin". Forbes. Retrieved August 10, 2020.
- Johnston, Katie (August 11, 2020). "Brightline Trains Ends Partnership With Richard Branson's Virgin Group". WFOR-TV. Retrieved September 9, 2020.
- Chardy, Alfonso (August 25, 2014). "Work begins — finally — on Miami-to-Orlando fast train". Miami Herald. Retrieved August 26, 2014.
- Robbins, John Charles (September 27, 2016). "Brightline passenger rail service 65% built". Miami Today. Retrieved March 9, 2017.
- Judy, Scott (July 30, 2014). "All Aboard Florida Taps Suffolk to Build Miami Station". ENR Southeast. Retrieved February 11, 2015.
- Chardy, Alfonso (March 9, 2015). "On track: Details for downtown Miami railway hub are revealed". The Miami Herald. Retrieved March 9, 2015.
- Turnbell, Michael (October 29, 2014). "Demolition begins for All Aboard Florida's new station". SunSentinel. Retrieved April 8, 2018.
- Sorentrue, Jennifer (November 12, 2014). "All Aboard Florida to begin construction today on West Palm Beach station". Palm Beach Post. Retrieved February 11, 2015.
- Turnbell, Michael (January 20, 2015). "Rail picks contractor for Fort Lauderdale, WPB stations". Sun Sentinel. Retrieved February 11, 2015.
- Sorentrue, Jennifer (November 28, 2017). "Brightline to start limited service in December". Palm Beach Post. Retrieved December 28, 2017.
- Sorentrue, Jennifer (July 24, 2017). "Brightline's Orlando leg delayed to 2020". myPalmBeachPost. Cox Media Group. Retrieved July 25, 2017.
- Solomon, Joshua (June 24, 2019). "Virgin Trains' Orlando leg underway as railroad eyes expansions to Tampa, Las Vegas". TCPalm. Retrieved January 2, 2020.
- Solomon, Joshua (September 18, 2019). "Virgin Trains expects to begin work Sept. 23 along Treasure Coast, Stuart officials say". TCPalm. Retrieved January 2, 2020.
- Virgin Trains rail construction to trigger Beachline Expressway nighttime closures, Rick Neale, Florida Today, October 21, 2019.
- "Virgin Trains USA names contractors for Orlando expansion". www.MassTransitMag.com. May 30, 2019. Retrieved January 2, 2020.
- "Happy rails to you: Brightline high-speed trains roll into action". my Palm Beach Post. January 13, 2018. Retrieved May 20, 2018.
- "Brightline slates fares and service date". Railway Age. January 11, 2018. Retrieved May 20, 2018.
- Bryan, Susannah (March 25, 2020). "As Brightline suspends service, 250 employees lose their jobs". Sun-Sentinel.
- Figueroa, Jessica (April 16, 2020). "Virgin Trains Continues Construction on South Florida to Orlando Rail Throughout COVID-19 Pandemic". WDW News Today. Retrieved May 31, 2020.
- Deal, Jeff (July 17, 2020). "High-speed rail service from OIA to South Florida on track for 2022". ABC. WFTV. Retrieved July 19, 2020.
- "Schedule". Brightline. 2019. Retrieved January 1, 2019.
- Broadt, Lisa (June 29, 2018). "Brightline financial documents reveal first quarter ridership, revenue". TCPalm. Retrieved July 6, 2018.
- "Brightline Ridership Triples Expectations; Miami To Start By End Of April". The Next Miami. April 13, 2018.
- "Here's How Many Passengers Have Been Riding Brightline Trains". The Next Miami. April 30, 2018.
- Lyons, David. "Brightline expects to more than double ridership by adding three South Florida stations". sun-sentinel.com. Retrieved January 2, 2020.
- "Virgin Trains USA celebrates one million ride mark". www.MassTransitMag.com. Retrieved January 2, 2020.
- Newspapers, Joshua Solomon, Treasure Coast. "Virgin Trains OKs 3 new stations in South Florida, so when will it build stations here?". The Palm Beach Post. Retrieved January 2, 2020.
- "SOM completes three new Brightline Florida rail stations". Archinect. Retrieved June 10, 2018.
- "Brightline – Rockwell Group". www.rockwellgroup.com. Retrieved June 10, 2018.
- Kornfield, Meryl (July 2, 2018). "Brightline's garages start charging customers to park". Sun-Sentinel.com. Retrieved July 6, 2018.
- "Here Are Leasing Plans And New Renderings For All Aboard Florida's MiamiCentral Station Project". The Next Miami. September 22, 2014. Retrieved February 11, 2015.
- "Fort Lauderdale". gobrightline.com. Retrieved June 10, 2018.
- Wallman, Brittany (May 4, 2014). "Rail firm appears on track to transform Fort Lauderdale". Sun Sentinel. Retrieved February 11, 2015.
- Sorentrue, Jennifer (November 11, 2014). "All Aboard Florida updates WPB station design". Palm Beach Post. Retrieved February 11, 2015.
- Fluker, Anjali (August 11, 2014). "Exclusive: What All Aboard Florida rail station may include at Orlando airport". Orlando Business Journal. Retrieved February 11, 2015.
- "Brightline, Disney announce agreement for Disney Springs train station". Orlando Sentinel.
- Ohnsman, Alan (June 11, 2020). "Inside A Wall Street Tycoon's Plan To Get Americans Off The Highway - And On His Trains". Forbes.
- Brezina-Smith, Veronica; Lynch, Ryan (September 11, 2019). "State Extends Virgin Trains' Deadline for Orlando-to-Tampa Right-of-Way Negotiations". Orlando Business Journal. Archived from the original on November 2, 2019. Retrieved November 2, 2019.
- "Virgin Trains' Tampa-to-Orlando right of way negotiations extended again". www.bizjournals.com. Retrieved December 29, 2019.
- Brezina-Smith, Veronica (September 15, 2020). "Brightline, developer Darryl Shaw in negotiations for Ybor City rail station". Tampa Bay Business Journal. Retrieved October 1, 2020.
- Talley, Karen. "All Aboard Florida gains easement, hints at Jacksonville in contract". Orlando Sentinel. Retrieved April 8, 2018.
- Hristoforidis, Christina (September 12, 2019). "Is the Proposed Brightline Train Station a Good Idea for Boca Raton?". The Boca Raton Tribute. Retrieved September 15, 2019.
- Baitinger, Brooke (December 11, 2019). "Brightline station coming to Boca Raton by 2021". South Florida Sun Sentinel. Boca Raton, Florida. Retrieved December 29, 2019.
- Newspapers, Joshua Solomon, Treasure Coast. "Virgin Trains OKs 3 new stations in South Florida, so when will it build stations here?". The Palm Beach Post. Retrieved June 5, 2020.
- Lyons, David (September 30, 2020). "Brightline shut down commuter service for months. When will the trains run again?". Miami Sun-Sentinel. Retrieved October 1, 2020.
- Hanks, Douglas (October 11, 2019). "Miami-Dade approves $76 million to bring Brightline to Aventura Mall". Miami Herald.
- https://www.bizjournals.com/southflorida/news/2020/09/03/brightline-breaks-ground-on-aventura-station.html
- "Brightline Announces Plans to Build PortMiami Station in 2020". www.travelmarketreport.com. Retrieved January 2, 2020.
- Rodriguez, Janny (September 6, 2018). "Brightline considers Fort Pierce train station". WPTV.
- Gardner, Keona (September 5, 2018). "Fort Pierce: Brightline wants to build station, hotel at H.D. King site downtown". TC Palm.
- Broadt, Lisa (October 23, 2018). "Stuart will pursue Brightline station; city is considering three locations". TCPalm. Retrieved November 2, 2018.
- Solomon, Joshua (October 25, 2019). "Virgin Trains moving closer to station in Cocoa, leaning toward Stuart". TCPalm. Retrieved October 28, 2019.
- "Brightline in talks with Miami-Dade to run commuter-rail line, report says". Progressive Railroading. May 29, 2020. Retrieved May 31, 2020.
- Price-Williams, Abigail. "MEMORANDUM" (PDF). Miami Dade County. Retrieved May 31, 2020.
- "Brightline, Miami-Dade OK access fee for new commuter-rail system". Progressive Railroading. November 18, 2020. Retrieved November 21, 2020.
- "Brightline to Build Express Intercity Passenger Rail Connecting Southern California and Las Vegas" (Press release). XpressWest. September 18, 2018. Retrieved September 19, 2018.
- Velotta, Richard N. (September 18, 2018). "Florida firm acquires company planning Las Vegas to LA rail line". Las Vegas Review-Journal. Retrieved September 18, 2018.
- "Las Vegas officials eye linking downtown to proposed high-speed rail". May 24, 2019.
- Cordeiro, Monivette. "Brightline changes name to Virgin Trains USA in new partnership with billionaire Richard Branson". Orlando Weekly.
- "South Florida gets first peek at Brightline express train". South Florida Sun-Sentinel. January 11, 2017. Retrieved February 16, 2019.
- "Brightline-Virgin proposal for Tampa-to-Orlando rail service clears key state hurdle". Tampa Bay Times. November 28, 2018. Retrieved February 15, 2019.
- "General Definitions of Highspeed". International Union of Railways (UIC). Retrieved November 20, 2015.
- Holsman, Melissa (April 22, 2019). "Virgin Trains sells $1.75 billion in private activity bonds for expansion to Orlando". TCPalm. Port St Lucie, FL: Treasure Coast Newspapers.
- "FECI Bringing Private Passenger Rail To Florida By 2014". Metro Jacksonville. Retrieved July 16, 2012.
FECI envisions a three-hour trip between the cities at an average speed similar to the Acela between New York and Washington, DC... The initial 240-mile project between Orlando and downtown Miami is expected to cost $1 billion.
- "ACELA High-Speed Rail Network System". Railway Technology. Retrieved May 19, 2012.
The 225 mile (362km) New York Penn Station to Washington, DC takes 2 hours 48 minutes, an average of 80mph (129km/h).
- Gale, Kevin (March 22, 2012). "Florida East Coast Industries plans Miami-to-Orlando passenger service". South Florida Business Journal. Retrieved May 18, 2012.
- Parker, Terri (July 23, 2014). "State requires All Aboard Florida to install millions in safety upgrades". WPBF. Retrieved February 10, 2015.
- "Private passenger train vision calls for double-tracking Florida East Coast". Trains Magazine. March 23, 2012. Retrieved March 29, 2012.
- "All Aboard Florida Passenger Rail Project FONSI". Federal Railroad Administration. Retrieved February 11, 2015.
- "Southeast Florida Passenger Rail Update: Sept. 20, 2013 Council Meeting" (PDF). Trasurer Coast Regional Planning Council. Retrieved February 11, 2015.
- Stone, Rick (August 14, 2014). ""Quiet Zones" Along The FEC Tracks May Silence Critics As Well As Train Whistles". WLRN. Retrieved February 11, 2015.
- "Federal Railroad Administration's Train Horn & Quiet Zone Rule". Union Pacific. Retrieved February 11, 2015.
- Reiser, Emon (August 13, 2014). "All Aboard Florida secures funds for Broward-Palm Beach quiet zone". South Florida Business Journal. Retrieved February 11, 2015.
- Chardy, Alfonso (January 16, 2015). "With "quiet zones' funded for Miami-Dade, All Aboard Florida moves ahead". Miami Herald. Retrieved February 11, 2015.
- Sorentrue, Jennifer (January 11, 2018). "UPDATE: Quiet zone work to be completed in March, Brightline says". Palm Beach Post. Retrieved February 9, 2018.
- Shatzman, Marci (May 30, 2018). "Trains to silence horns at 10 Boca Raton crossings". Sun Sentinel. Retrieved June 1, 2018.
- "FRA Locomotive Horn Sounding and Quiet Zone Establishment". FRA. Retrieved August 21, 2019.
- "All Aboard Florida – Miami to Orlando Passenger Rail Service Draft Environmental Impact Statement". Federal Railroad Administration. September 19, 2014. Retrieved February 11, 2015.
- Broadt, Lisa (January 17, 2018). "Second person in less than a week killed by high-speed Brightline train in South Florida". USA Today. Retrieved January 18, 2018.
- Darrah, Nicole (April 8, 2018). "New high-speed Florida train kills 4th person since launching service". Fox News. Retrieved April 8, 2018.
- "Man's body recovered from canal after collision with Brightline train", South Florida Sun-Sentinel, January 1, 2019.
- Smalls, C. Isaiah (November 15, 2019). "A woman is dead after being involved in Brightline crash". Miami Herald.
- Brightline and Tri-Rail Have Killed Dozens, Meg O'Connor, Miami New Times, February 19, 2019.
- "Brightline, Florida's High-Speed Train, Has Highest U.S. Death Rate". CBSMiami. Associated Press. December 2, 2019. Retrieved January 2, 2020.
- "49 U.S.C. 26105 – Definitions". U.S. Government Publishing Office. Retrieved April 8, 2018.
- "The Development of High Speed Rail in the United States: Issues and Recent Events" (PDF). Congressional Research Service. Retrieved October 10, 2012.
- Tracy, Dan (July 16, 2013). "Deal could lead to Miami-Orlando train, extended Osceola toll road". Orlando Sentinel. Retrieved July 30, 2013.
- "F A Q". Brightline. Retrieved June 10, 2018.
- Spear, Kevin. "Virgin Trains announces construction start for rail between Orlando and South Florida". orlandosentinel.com. Retrieved January 2, 2020.
- "All Aboard Florida secures right-of-way, station agreements". Railway Track and Structures. October 4, 2013. Retrieved October 9, 2013.
- Seemuth, Mike (January 18, 2016). "Concrete pours for Brightline facility in West Palm Beach". The Real Deal Miami. Retrieved May 10, 2016.
- "Cummins QSK95 achieves Tier 4 certification". Railway Gazette. London. April 6, 2016.
- "Brightline unveils Siemens locomotives and coaches". Railway Gazette. London. June 8, 2016.
- Trejos, Nancy (November 9, 2015). "New Florida train service to whisk passengers between Miami and Orlando". USA Today.
- "Florida's Brightline to 'take the grey out of travel'". Railway Gazette. November 10, 2015.
- "All Aboard Florida Selects Siemens as Train Manufacturer" (Press release). All Aboard Florida. September 11, 2014. Retrieved April 8, 2018.
- Brinkmann, Paul (September 11, 2014). "Siemens to build All Aboard Florida trains". Orlando Sentinel. Retrieved February 11, 2015.
- Hendrickson, Eric (December 13, 2016). "First Brightline train on FEC rails". Trains Magazine. Retrieved December 16, 2016.
- Viglucci, Andres (December 14, 2016). "Take a gander at the very first finished Brightline train, now steaming to South Florida". Miami Herald. Retrieved December 16, 2016.
- "Fifth Trainset Delivered As Brightline Named Official Train Service Of Miami HEAT" (Press release). Brightline. October 5, 2017. Retrieved May 20, 2018 – via PR Newswire.
- "Brightline train service begins in South Florida". WFTV 9. January 11, 2018. Retrieved February 9, 2018.
- "Trains". Brightline. Retrieved February 9, 2018.
- "Brightline going biodiesel". June 5, 2017. Retrieved May 20, 2018.
- "Charger Diesel-Electric Locomotive: All Aboard Florida" (PDF). Siemens Mobility. 2014. Archived from the original (PDF) on June 23, 2016. Retrieved January 3, 2016.
- https://www.railwaygazette.com/news/passenger/single-view/view/brightline-unveils-siemens-locomotives-and-coaches.html
Further reading
- "Surface Transportation Facility Revenue Bonds (Brightline Florida Passenger Rail Project), (Series 2019B Green Bonds)" (PDF). Florida Development Finance Corporation. December 11, 2020. Archived (PDF) from the original on January 12, 2021.
External links
Wikimedia Commons has media related to Brightline. |
- Official website
- All Aboard Florida – Miami to Orlando Passenger Rail Service – Federal Railroad Administration