SRT Dark Red Line
The SRT Dark Red Line is part of the planned SRT Red Line suburban railway system to serve the greater Bangkok Metropolitan Region which includes Bangkok Province and 4 adjoining provinces. It runs on a north–south axis through Bangkok. When fully completed, the line will extend from Thammasat University's Rangsit campus in Pathum Thani Province to Maha Chai in Samut Sakhon Province for a full length of nearly 87 km.
SRT Dark Red Line สายสีแดงเข้ม | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
The elevated route under construction near Bang Sue Central Station | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Overview | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Status | Under Construction | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner | State Railway of Thailand | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Termini | Thammasat University Maha Chai | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stations | 37 (9 Initial) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Type | Commuter rail | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
System | Bangkok Suburban Commuter Train | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operator(s) | SRTET - SRT Electrified Train Company Limited | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
History | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Opened | March 2021 (trial service) Nov 2021 (full service) (Phase 1 Rangsit - Bang Sue) 2024 (est.) Phase 2 Rangsit - Thammasat Uni) 2025 (est.) (Phase 3 Bang Sue - Hua Lamphong) 2029 (est.) (Phase 4 Hua Lamphong - Maha Chai) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line length | 86.8 km (53.94 mi) (Total planned) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track length | 21.6 km (13.42 mi) (Phase 1) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 1,000 mm (3 ft 3 3⁄8 in) metre gauge | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrification | Overhead lines | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating speed | 160 km/h (99 mph) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Construction started in 2013 and was originally due to be completed within 3 years by the end of 2016. However, the project has experienced numerous delays. In May 2018, the SRT announced that the line was expected to open by October 2020 with fares to be set at between 14-45 baht.[1] At the end of September 2019, civil construction fully completed [2] with only signaling and electrical systems to be installed. By July 2020, S&E installation was at 85.12% completion.[3] The SRT has stated that the new Intercity Terminal at Bang Sue will not open until late 2021.[4]
As at September 2020, 21 of the 25 sets of rolling stock has been delivered and limited test runs from Wat Samian Nari to Rangsit began in August 2020 operating at a maximum speed of 120km/h. The test runs will be extended to Bang Sue Intercity Terminal from late November 2020.[5] In mid November 2020, the Minister of Transport announced that the line will start limited free trial operations from March to May 2021 with full service operations commencing in November 2021.[6]
Route Alignment
Initially, the SRT Dark Red Line will run from the new Intercity Terminal at Bang Sue north for 21.6 km via Don Mueang to terminate at Rangsit in Pathum Thani Province. The line will then be extended a further 10 km north from Rangsit to Thammasat University's Rangsit campus. From Bang Sue the line will be extended 11 km south via Phaya Thai to terminate at Hua Lumphong station. The final section of the line will run south east from Hua Lumphong for 39 km to Maha Chai in Samut Sakhon Province via Wong Wian Yai along the current Maha Chai railway alignment.
When completed, the SRT Dark Red Line will run from Thammasat University's Rangsit campus in Pathum Thani Province to Maha Chai in Samut Sakhon Province for a total of 87 km.
History
In February 2009, Prime Minister Abhisit Vejjajiva secured a 24 billion baht (US$685 million) loan from the Japanese Government for the 67 km (42 mi) segment.[7][8] The first Phase from Bang Sue to Rangsit was approved in 2010 but delayed due to a complicated 2.5 year contractual dispute.
The 21.6 km, 9 station Rangsit to Bang Sue section finally started construction in May 2013 after new contracts were signed in January 2013.[9] A construction period of 3 years was stated. By the end of 2013, the project was only 3% done & already months behind schedule due to a longer timetable in removing the Hopewell Pillars.[10] In June 2014, the SRT requested an additional 8.14 billion baht to modify the Dark Red line to 4 tracks instead of 3, to accordingly redesign all stations and to provide for the longer platforms for the Bang Sue Terminal to cater for future HSR lines.[11] 8.140 billion baht request is; 4.32 billion baht for Contract 1 (modifications to Bangsue Central to cater for High Speed trains); 3.35 billion Baht for Contract 2 (4th track and stations redesign) and 473 million baht for Contract 3.
The budget for the 1st Phase of the Dark Red Line project has progressively increased due to numerous delays and further redesign of the project. From an initial 59.89 billion baht in 2007, to 75.55 billion baht in 2009 and to 80.38 billion baht in 2012. The additional requested 8.14 billion baht will increase the current budget to 88.52 billion baht.
Construction Progress: Bang Sue to Rangsit (Phase 1)
The 21.6 km, 9 station Bang Sue to Rangsit section finally started construction in May 2013 with a scheduled construction period of 3 years. Construction works were delayed by 2 months due to site access issues for the contractor and delays related to removing slum dwellers residing within the right of way. However, it was hoped that the use of some of the old Hopewell pillars would speed up the initial construction timetable.[12] By the end of 2013, the project was only 3% done & already months behind schedule due to a longer timetable in removing the Hopewell Pillars.[13]
In June 2014, the SRT requested an additional 8.14 billion baht to modify the Dark Red line to 4 tracks instead of 3, to accordingly redesign all stations and to provide for the longer platforms for the Bang Sue Terminal to cater for future HSR lines.[14] 8.140 billion baht request is; 4.32 billion baht for Contract 1 (modifications to Bang Sue to cater for High Speed trains); 3.35 billion Baht for Contract 2 (4th track and stations redesign) and 473 million baht for Contract 3.
As of September 2017, civil works progress was stated to be 88.63%.[15] By the end of September 2019 civil works were almost fully complete at 99.56% and Electrical and Signalling installation was at 45.60%.[16] By July 2020, S&E installation was at 80%.[17] By October 2020, 90% of the power supply for the line had been installed by the Metropolitan Electricity Authority (MEA) with all installation due to be completed by November.[18]
New Intercity Terminal at Bang Sue (Contract 1)
Contract 1 of the project is for the construction of a new, 4 level Intercity Terminal to cater for all SRT Intercity Trains, SRT Red Line suburban trains and the yet to be built Airport Rail Link (Bangkok) extension. The delayed contract process was finally signed in January 2013.[19] In August 2013, the SRT sought extra funds for the project to be redesigned in order to extend upper level platforms to a 400-600m length in order to accommodate future planned High Speed Lines.[20] (Funding was finally requested in June 2014 - see above section)
In March 2013, the new Intercity Terminal at Bang Sue started construction. Between March and June, excavation works for the foundation of the Terminal were delayed by the unearthing of numerous World War II unexploded bombs which required safe removal by army Explosive Ordnance Teams.[21][22][23] As of July 2014, construction was 10% behind schedule.
The new Bang Sue was originally scheduled to open by end of 2016 but the above-mentioned redesign work and other delays have resulted in an expected 2020 opening date. As of September 2017, construction progress of the station civil works was at 57.50%.[24] By the end of September 2019 civil works were at 86.01%.[25] As at July 2020, civil works were almost complete at 99.8%.[26]
Rolling stock (Contract 3)
The 3rd contract for the Dark Red Line is for electrical and systems (E&S) and procuring EMU rolling stock. An overhead catenary electrical system is specified. As of April 2014, only 2 bidders remained but one of the bidding consortium's was disqualified on due to the fact that one of the consortium members (Maru Beni Corp) had convictions for bribery in an Indonesian bidding process.[27]
This left MHSC Consortium (Mitsubishi and Hitachi and Sumitomo) as the sole bidder qualified for the contract. However, their bid of 28,899 Million Baht was above the SRT median price of 26 billion baht which was set in 2010. The MHSC Consortium argued that their bid reflects 2013 prices after the minimum wage increase of January 2012. Finally, after a 2-year delay in the bidding process, in July 2014 JICA approved the loan for Contract 3.[28] However, the coup of May 2014 delayed finalization leading to further review and negotiations. By mid 2016, negotiations had concluded and Hitachi promised that all rolling stock for the Dark Red line would be delivered by 2020.[29] The contract specifies 25 EMUs consisting of ten 4 car sets and fifteen 6 car sets for 130 cars in total.
In late September 2019, the first 2 sets of rolling stock were shipped from Japan[30] and both arrived in Thailand at Laem Chabang port on 12 October 2019 for shipment to Bangkok.[31] By March 2020, 5 sets had been delivered.[32]
As of July 2020, 13 sets - 7 of the 6 car sets and 6 of the 4 car sets - of the total 25 sets of rolling stock had been delivered with a further 2 sets due to be delivered by August 2020.[33] By the end of September 2020, 21 sets had been delivered - 13 of the 6 car sets and 8 of the 4 car sets - with the final 4 sets to be delivered in October.[34]
Future extensions
In July 2016, the Thai Cabinet approved the first section of the southern extension from Bang Sue to Hua Lamphong. However, the 10km 4 station northern extension from Rangsit to Thammasat University will be built first and was originally expected to be tendered by September 2018.[35] This was delayed and then due to be tendered in the 2nd half of 2019.[36] However, the tender has yet again been further delayed until 2021 as the Transport Minister has requested that the new Department of Railways investigate conducting PPP tenders for this extension.[37]
Construction segments based on M-Map:[38]
Phase | Segment | Length | Progress |
---|---|---|---|
I | Rangsit-Bang Sue | 26 km (16.16 mi) | Under construction |
II | Thammasat University-Rangsit | 10 km (6.21 mi) | Cabinet Approved |
III | Bang Sue-Hua Lamphong | 11 km (6.84 mi) | Cabinet Approved |
IV | Hua Lamphong-Bang Bon | 18 km (11.18 mi) | Planned |
V | Bang Bon-Maha Chai | 20 km (12.43 mi) | Planned |
VI | Maha Chai-Maeklong | 24 km (14.91 mi) | Suggested |
VII | Maeklong-Pak Tho | 22 km (13.67 mi) |
There is a future extension that is not included in M-Map, but is included in information brochures.[39]
Phase | Segment | Length | Progress |
---|---|---|---|
TBA | Thammasat University-Phachi Junction Railway Station | Unknown | Unknown |
Phase II Rangsit-Thammasat University: 10.0 km (6.21 mi) (planned for tender in 2021)
The 10 km, 4 station was approved by Cabinet in 2016 and was expected to be tendered by September 2018.[40] The extension to Thammasat University was then to be tendered in the 2nd half of 2019.[41] However, the tender has further been delayed until 2021 as the Transport Minister has requested the new Department of Railways to investigate conducting PPP tenders for this extension.[42]
Phase III Bang Sue-Hua Lamphong: 11.0 km (6.84 mi) (cabinet approved)
The 11 km, 7 station southern extension to Hua Lumphong station was approved by Cabinet in 2016. However, the northern extension to Thammasat University will be built before this section.[43]
Phase IV & V Hua Lamphong-Bang Bon-Maha Chai: 39.0 km (24.23 mi) (planned)
The last section of the line will run south east from Hua Lumphong to Maha Chai in Samut Sakhon Province via Wong Wian Yai along the current Maha Chai railway alignment.
Potential extension from Maha Chai to Ratchaburi?
The Office of Transport and Traffic Policy and Planning (OTP) have studied the improvement and construction of the Mae Klong railway line[44] Which will be constructed through Samut Sakhon, Samut Songkhram and Ratchaburi provinces. It will use a bypass route in Samut Sakhon Province by deviating from the original train line for about 31 km. Between Ban Khom Railway Station and Khlong Chak Railway Station, the line will be elevate across Ekachai road And deviate along the route of Rama II Road around the km 26 + 800 to the 32 + 160 km and then divert to the left to go straight to connect with the original train line.
From Samut Songkhram the suggested route will be constructed across the Mae Klong River. A third option is expected to be in use, which is to bypass Samut Songkhram city By diverging from the original train line about 66 km after passing Bang Kraboon Railway Station, which will be an elevated railway along the National Highway No. 325 to cross the Mae Klong Canal And Highway 325 at the intersection to Damnoen Saduak District, approximately 40 + 850 km and crossing the Mae Klong River. It will then revert to ground level and end at Pak Tho Railway Station, Ratchaburi which will build a train parallel with the royal highway number 3093 and will have 3 more new railway stations in this section. Expected total value of this project is approximately 42,243 million baht.[45]
When completed, it will be a new southern railway line, which will help shorten the original train route, which originally runs through Nakhon Pathom and Ratchaburi before going to Pak Tho Station. The new Southern Railway will reduce the distance by about 43 kilometres and the aim of the project also includes the development of the Southwest Transport Center. However, as of 2016 this planned southern extension is very unlikely to be built as when Cabinet approved the northern extension to Thammasat University and the Southern extension to Hua Lumphong, only the original project scope to Maha Chai was referenced.
List of stations
Code | Station Name | Thai | Express Train | City Train | Transfer | Location |
---|---|---|---|---|---|---|
Phase II - Northern extension | ||||||
RN13 | Thammasat University | มหาวิทยาลัยธรรมศาสตร์ ศูนย์รังสิต |
● | ● | Pathum Thani | |
RN12 | Chiang Rak | เชียงราก | ● | |||
RN11 | Bangkok University | มหาวิทยาลัยกรุงเทพ | ● | |||
RN10 | Khlong Nueng | คลองหนึ่ง | ● | |||
Phase I | ||||||
RN09 | Rangsit | รังสิต | ● | ● | ||
RN08 | Lak Hok (Rangsit University) | หลักหก (มหาวิทยาลัยรังสิต) | ● | |||
RN07 | Don Mueang | ดอนเมือง | ● | ● | Don Mueang International Airport ARL (approved) | Bangkok |
RN06 | Kan Kheha | การเคหะ | ● | |||
RN05 | Lak Si | หลักสี่ | ● | MRL : Lak Si (under construction) | ||
RN04 | Thung Song Hong | ทุ่งสองห้อง | ● | |||
RN03 | Bang Khen | บางเขน | ● | MRT : Bang Khen (approved, proposed tender in 2021) | ||
RN02 | Wat Samian Nari | วัดเสมียนนารี | ● | |||
RN01 | Chatuchak | จตุจักร | ● | Mochit 2 Northern/Northeastern Bus Terminal | ||
RCEN | Bang Sue | บางซื่อ | ● | ● | SRT ARL (approved) MRT : Bang Sue | |
Phase III - Southern extension | ||||||
RS01 | Pradiphat | ประดิพัทธ์ | ● | SRT | Bangkok | |
RS02 | Sam Sen | สามเสน | ● | SRT | ||
RS03 | Ratchawithi | ราชวิถี | ● | SRT | ||
RS04 | Yommarat | ยมราช | ● | MRT : Yommarat (currently under tender) | ||
RS05 | Yot Se | ยศเส | ● | BTS : Yot Se (proposed extension) | ||
RS06 | Hua Lamphong | หัวลำโพง | ● | ● | MRT : Hua Lamphong | |
Phase IV | ||||||
RS07 | Khlong San | คลองสาน | ● | Bangkok | ||
RS08 | Wongwian Yai | วงเวียนใหญ่ | ● | BTS : Wongwian Yai MRT : Wongwian Yai (approved, tender planned for late 2020) | ||
RS09 | Talat Phlu | ตลาดพลู | ● | BTS : Talat Phlu | ||
RS10 | Taksin | ตากสิน | ● | ● | BTS : Wutthakat | |
RS11 | Chom Thong | จอมทอง | ● | |||
RS12 | Wat Sai | วัดไทร | ● | |||
RS13 | Wat Sing | วัดสิงห์ | ● | ● | ||
RS14 | Bang Bon | บางบอน | ● | |||
Phase V | ||||||
RS15 | Rang Sakae | รางสะแก | ● | Bangkok | ||
RS16 | Rang Pho | รางโพธิ์ | ● | ● | ||
RS17 | Sam Yaek | สามแยก | ● | |||
RS18 | Phrom Daen | พรมแดน | ● | |||
RS19 | Thung Si Thong | ทุ่งสีทอง | ● | ● | Samut Sakhon | |
RS20 | Bang Nam Chuet | บางน้ำจืด | ● | |||
RS21 | Khok Khwai | คอกควาย | ● | |||
RS22 | Ekkachai | เอกชัย | ● | ● | ||
RS23 | Maha Chai | มหาชัย | ● | ● | ||
Phase VI (Unlikely to be built) | ||||||
x | Tha Chalom | ท่าฉลอม | Samut Sakhon | |||
x | Nok Lek | นกเล็ก | ||||
x | Si Kot | สีคต | ||||
x | Bang Krachao | บางกระเจ้า | ||||
x | Ban Bo | บ้านบ่อ | ||||
x | Bang Thorat | บางโทรัด | ||||
x | Ban Ka Long | บ้านกาหลง | ||||
x | Ban Na Khwang | บ้านนาขวาง | ||||
x | Ban Na Khok | บ้านนาโคก | ||||
x | Ban Ket Muang | บ้านเขตเมือง | Samut Songkhram | |||
x | Lad Yai | ลาดใหญ่ | ||||
x | Bang Krabun | บางกระบูน | ||||
x | Mae Klong | แม่กลอง | ||||
Phase VII (Unlikely to be built) | ||||||
x | Bang Khan Thong | บางขันทอง | Samut Songkhram | |||
x | Plai Phong Phang | ปลายโพงพาง | ||||
x | Wat Pleng | วัดเพลง | Ratchaburi | |||
x | Pak Tho | ปากท่อ | SRT Southern line | |||
Route Districts & Provinces
Tambon/District | Amphoe/Khet | Province | ||||||
---|---|---|---|---|---|---|---|---|
Phachi / Phai Lom / Krachio | Phachi | Phra Nakhon Si Ayutthaya | ||||||
Khao Mao | Uthai | |||||||
Nong Pling | Nakhon Luang | |||||||
Ban Ko / Ho Rattanachai / Kamang / Ko Rian | Phra Nakhon Si Ayutthaya | |||||||
Khanon Luang / Ban Pho/ Bang Krasan / Chiang Rak Noi | Bang Pa-in | |||||||
Khlong Nueng | Khlong Luang | Pathum Thani | ||||||
Prachathipat | Thanyaburi | |||||||
Lak Hok | Mueang Pathum Thani | |||||||
Si Kan / Sanam Bin / Don Mueang | Don Mueang | Bangkok | ||||||
Talat Bang Khen | Lak Si | |||||||
Lat Yao / Chatuchak | Chatuchak | |||||||
Bang Sue | Bang Sue | |||||||
Sam Sen Nai | Phaya Thai | |||||||
Suan Chitlada | Dusit | |||||||
Rong Mueang | Pathum Wan | |||||||
Maha Phruettharam / Bang Rak | Bang Rak | |||||||
Khlong Ton Sai / Khlong San | Khlong San | |||||||
Bang Yi Ruea / Talat Phlu | Thon Buri | |||||||
Bang Kho / Bang Khun Thian | Chom Thong | |||||||
Khlong Bang Bon/ Bang Bon Tai | Bang Bon | |||||||
Samae Dam | Bang Khun Thian | |||||||
Bang Nam Chuet / Khok Krabue / Khok Kham / Maha Chai / Tha Chalom / Tha Chin / Bang Krachao / Ban Bo / Bang Tho Rat / Ka Long / Na Khok | Mueang Samut Sakhon | Samut Sakhon | ||||||
Lat Yai / Bang Kaeo / Mae Klong / Thai Hat / Bang Khan Taek | Mueang Samut Songkhram | Samut Songkhram | ||||||
Suan Luang / Plai Phongphang / Wat Pradu | Amphawa | |||||||
Wat Yang Ngam / Pak Tho | Pak Tho | Ratchaburi | ||||||
See also
- Mass Rapid Transit Master Plan in Bangkok Metropolitan Region
- SRT Light Red Line
- Airport Rail Link (Bangkok)
- BTS Skytrain
- Sukhumvit Line
- Silom Line
- MRT (Bangkok)
- MRT Blue Line
- MRT Brown Line
- MRT Grey Line
- MRT Light Blue Line
- MRT Orange Line
- MRT Pink Line
- MRT Purple Line
- MRT Yellow Line
- Bangkok BRT
- BMA Gold Line
References
- "Red Line set for October 2020 launch". Bangkok Post. 26 May 2018.
- "ธรรมศาสตร์พบ "ศักดิ์สยาม" เร่งสร้างรถไฟฟ้าสายสีแดงส่วนต่อขยายรังสิต "รถไฟ" คาดลงเข็มมิ.ย.63". Prachachat. 27 September 2019.
- "รฟท.สร้างเสร็จ99%พร้อมเปิด64แต่กลัวขัดนโยบาย". Dailynews. 17 July 2020.
- "ไม่รอเอกชนร่วมทุนฯ! รฟท.เปิดทดสอบเดินรถไฟฟ้า 'สายสีแดง' กลางปี 64-ลุยทางคู่สายอีสาน". Isranews. 19 September 2020.
- "สิ้นสุดรอคอย10ปี! ต.ค.นี้ทดสอบรถไฟฟ้าสีแดงตะวันตก". Dailynews. 24 September 2020.
- "รถไฟสายสีแดง มี.ค.64". Thai PBS. 16 November 2020.
- "Abhisit wins backing for train deal". Bangkok Post. 7 February 2009.
- "B23bn MRT loan inked". Bangkok Post. 30 March 2009.
- "Contracts signed for Red Line stations". The Bangkok Post. Bangkok. 31 January 2013.
- http://www.prachachat.net/news_detail.php?newsid=1388935951
- "SRT seeks extra B8bn for Red Line". The Bangkok Post. Bangkok. 27 June 2014. Retrieved 22 July 2014.
- 'Red Line deal inked; some Hopewell pillars to stay', MCOT, 31 January 2013
- http://www.prachachat.net/news_detail.php?newsid=1388935951
- "SRT seeks extra B8bn for Red Line". The Bangkok Post. Bangkok. 27 June 2014. Retrieved 22 July 2014.
- "รฟท. เสนอเดินรถสายสีแดง งัดไม้ตายมัดใจ คนร. 11 ต.ค.นี้". Voice TV. 9 October 2017.
- "ธรรมศาสตร์พบ "ศักดิ์สยาม" เร่งสร้างรถไฟฟ้าสายสีแดงส่วนต่อขยายรังสิต "รถไฟ" คาดลงเข็มมิ.ย.63". Prachachat. 27 September 2019.
- "รฟท.สร้างเสร็จ99%พร้อมเปิด64แต่กลัวขัดนโยบาย". Dailynews. 17 July 2020.
- "MEA เผยความคืบหน้าจ่ายไฟรถไฟฟ้าสายสีแดง สถานีกลางบางซื่อ พร้อมแล้วกว่าร้อยละ 90". Naewna. 6 October 2020.
- 'SRT inks deal for Bang Sue rail terminus', Bangkok Post, 19 January 2013
- http://www.dailynews.co.th/Content/economic/75425
- http://news.mthai.com/general-news/320354.html
- 'World War II bomb found at MRT project site', The Nation, 3 June 2014
- http://www.manager.co.th/Crime/ViewNews.aspx?NewsID=9570000061610
- "รฟท. เสนอเดินรถสายสีแดง งัดไม้ตายมัดใจ คนร. 11 ต.ค.นี้". Voice TV. 9 October 2017.
- "ธรรมศาสตร์พบ "ศักดิ์สยาม" เร่งสร้างรถไฟฟ้าสายสีแดงส่วนต่อขยายรังสิต "รถไฟ" คาดลงเข็มมิ.ย.63". Prachachat. 27 September 2019.
- "กางไทม์ไลน์สายสีแดง เปิดทดลองฟรี มิ.ย. 64 - "ศักดิ์สยาม" เรียกถกเคาะ PPP". Manager Online. 20 July 2020.
- http://www.prachachat.net/news_detail.php?newsid=1388935951
- 'JICA green light red line contract 3 Bang Sue - Rangsit after 2 years delay'. 24 July 2014. Economic News, http://pantip.com/topic/32365743
- "Hitachi vows on-time train carriage delivery for Red Line". The Nation. 27 August 2016.
- "Hitachi ships first Bangkok Red Line trains". International Railway Journal. 27 September 2019.
- "https://mgronline.com/business/detail/9620000098623". Manager Online. 13 October 2019. External link in
|title=
(help) - "Red Line train trials to begin in October". Bangkok Post. 19 March 2020.
- "รฟท.สร้างเสร็จ99%พร้อมเปิด64แต่กลัวขัดนโยบาย". Dailynews. 17 July 2020.
- "สิ้นสุดรอคอย10ปี! ต.ค.นี้ทดสอบรถไฟฟ้าสีแดงตะวันตก". Dailynews. 24 September 2020.
- "Ministry to forward plans for 2 Red Line extensions". Bangkok Post. 19 January 2017.
- "SRT eyeing B40bn budget". Bangkok Post. 9 June 2019.
- ""ศักดิ์สยาม" เปิดปมทำไม "รถไฟฟ้าสายสีแดง" เลื่อนเปิดปี'64". Prachachat. 19 July 2020.
- http://mrt-progress.otp.go.th/MRT/?q=node/74 Archived 2011-01-12 at the Wayback Machine
- th:รถไฟฟ้าชานเมืองสายสีแดงเข้ม
- "Ministry to forward plans for 2 Red Line extensions". Bangkok Post. 19 January 2017.
- "SRT eyeing B40bn budget". Bangkok Post. 9 June 2019.
- ""ศักดิ์สยาม" เปิดปมทำไม "รถไฟฟ้าสายสีแดง" เลื่อนเปิดปี'64". Prachachat. 19 July 2020.
- "Ministry to forward plans for 2 Red Line extensions". Bangkok Post. 19 January 2017.
- โครงการงานศึกษาและออกแบบโครงการระบบรถไฟฟ้าชานเมือง ร่วมกับรถไฟฟ้าทางไกลเชื่อมต่อระบบขนส่งมวลชน ในเขตกรุงเทพมหานครและปริมณฑล (รังสิต-สถานีบ้านภาชี มักกะสัน-ฉะเชิงเทรา ตลิ่งชัน-นครปฐม และมหาชัย-ปากท่อ) http://www.otp.go.th/th/index.php/component/content/article/16-2549/128-itsi.html
- เวนคืน 4 โครงการฝั่งธนฯสนข.ปัดฝุ่นทางด่วน-รถไฟ. หนังสือพิมพ์วัฏจักร. 17/2/2547.
External links
Wikimedia Commons has media related to SRT Dark Red Line. |