The Metro Rail Transit Line 3, also known as the MRT Line 3, MRT-3 or Metrostar Express, is a light rapid transit system line of Metro Manila, Philippines. The line runs in an orbital north to south route following the alignment of the Epifanio de los Santos Avenue (EDSA). Although it has the characteristics of light rail, such as with the type of rolling stock used, it is more akin to a rapid transit system owing to its total grade separation and high passenger throughput.
MRT Line 3 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
A MRTC 3000 class train approaching North Avenue station | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Overview | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Status | Operational | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner | •Metro Rail Transit Corporation •Department of Transportation | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line number | 3 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | Metro Manila, Philippines | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Termini | North Avenue Taft Avenue | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stations | 13[1] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Website | MRTC, DOTr-MRT3 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Type | Light rapid transit | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
System | Manila Metro Rail Transit System | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Services | 1[2] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operator(s) | •Metro Rail Transit Corporation •Department of Transportation | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Depot(s) | North Avenue | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Rolling stock | 1st Generation LRV ČKD Tatra RT8D5[3] 2nd Generation LRV CRRC Dalian 8MLB[3] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Daily ridership | 350,000 (original capacity, current minimum capacity) 650,000 (2012–2013 record) 500,000 (2011–2015 peak daily capacity) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
History | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Opened | December 15, 1999 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track length | 16.9 km (10.5 mi) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Character | At-grade separated | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 1,435 mm (4 ft 8 1⁄2 in) standard gauge | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Minimum radius | 370 m (400 yd) Mainline / 25 m (82 ft) Depot | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrification | 750 V DC Overhead lines | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating speed | Operating speed: 30–60 km/h (19–37 mph) Design speed: 60 km/h (37 mph) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Envisioned in the 1970s as part of the Metropolitan Manila Strategic Mass Rail Transit Development Plan, the thirteen-station, 16.9-kilometer (10.5 mi) line was the second rapid transit line to be built in Metro Manila when it started full operations in 2000 under a 25-year concession agreement between its private owners and the Philippine government's Department of Transportation (DOTr).
The line is owned by the Metro Rail Transit Corporation (MRTC), a private company operating in partnership with the DOTr under a Build-Lease-Transfer agreement. Serving close to 550,000 passengers on a daily basis when MRTC's maintenance provider, Sumitomo Corp. of Japan, was handling the maintenance of the system, the line is the busiest among Metro Manila's three rapid transit lines, built with essential standards such as barrier-free access and the use of contact-less card tickets to better facilitate passenger access. Total ridership significantly exceeds its built maximum capacity of 350,000 passengers a day, with various solutions being proposed or implemented to alleviate chronic congestion in addition to the procurement of new rolling stock.
Since 2006, the system's private owners had been offering various capacity expansion proposals to the DOTC. In 2014, after the DOTC's handling of the line's maintenance for two years amid questions about the line's structural integrity owing to the poor maintenance and the pronouncements that the system, in general, was safe, experts from MTR HK were commissioned to review the system. MTR HK made the opinion that the rail system was compromised due to the DOTC's poor maintenance.[4][5][6]
It is integrated with the public transit system in Metro Manila, and passengers also take various forms of road-based public transport, such as buses, to and from a station to reach their intended destination. Although the line is aimed at reducing traffic congestion and travel time along EDSA, the transportation system has only been partially successful due to the DOTC's inaction on the private sector's proposals to expand the capacity of the system to take up to 1.1 million passengers a day. Expanding the network's capacity to accommodate the rising number of passengers is currently set on tackling this problem.
Route
The line has 13 stations on 16.9 kilometers (10.5 mi) of double track,[1][2] spaced on average around 1,300 meters (4,300 ft) apart.[7] The rails are mostly elevated and erected either over or along the roads covered, with cut and underground sections between Buendia and Ayala stations, the only underground stations on the line. The southern terminus of the line is Taft Avenue station at Pasay Rotonda, the intersection between Epifanio de los Santos Avenue and Taft Avenue, while the northern terminus is the North Avenue station along Epifanio de los Santos Avenue in Barangay Bagong Pag-asa, Quezon City. The rail line serves the cities that Circumferential Road 4 (Epifanio de los Santos Avenue) passes through: Pasay, Makati, Mandaluyong, San Juan and Quezon City. The line crosses South Luzon Expressway (SLEX) at Magallanes Interchange in Makati.
Three stations serve as interchanges with the lines operated by the Light Rail Manila Corporation (LRMC), Light Rail Transit Authority (LRTA), and Philippine National Railways (PNR). Magallanes station is near the PNR's EDSA station, while Araneta Center-Cubao station is indirectly connected to the LRT Line 2 station of the same, and Taft Avenue station is connected via a covered walkway to the LRT Line 1 EDSA station. No stations are connected to other rapid transit lines within the paid areas, though that is set to change when the North Avenue Grand Central Station, which has interchanges to LRT Line 1 and MRT Line 7, opens within 2021.
Early on during the construction of the line, a plan was drafted for a spur line towards the Makati Central Business District, built between Ayala and Buendia stations. The remaining evidence of this abandoned plan is an underground tunnel between Buendia and Ayala station turning right, heading towards Ayala Avenue. The planned spur line was cancelled due to the Asian Financial Crisis in 1997, which resulted the spur line area to be abandoned since the line's opening on 1999.
Name | Distance (km) | Line Transfers | Location | |
---|---|---|---|---|
Between stations | From North Avenue | |||
North Avenue Grand Central Station | — | — | LRT Line 1 7 MRT Line 7 MMS Metro Manila Subway |
Quezon City |
North Avenue | — | 0.000 | none | |
Quezon Avenue | 1.200 | 1.200 | MMS Metro Manila Subway | |
Kamuning | 1.000 | 2.200 | none | |
Araneta Center–Cubao | 1.900 | 4.100 | LRT Line 2 | |
Santolan | 1.500 | 5.600 | none | |
Ortigas | 2.300 | 7.900 | 4 MRT Line 4 | Mandaluyong City |
Shaw Boulevard | 0.800 | 8.700 | none | |
Boni | 1.000 | 9.700 | ||
Guadalupe | 0.800 | 10.500 | 5 Makati Intra-city Subway | Makati City |
Buendia | 2.000 | 12.500 | none | |
Ayala | 0.950 | 13.450 | 5 Makati Intra-city Subway | |
Magallanes | 1.200 | 14.650 | PNR Metro Commuter Line via EDSA | |
Taft Avenue | 2.050 | 16.700 | LRT Line 1 via EDSA | Pasay City |
Stations and train systems in italics are under construction. |
The line is open from 5:30 a.m. PST (UTC+8) until 11:00 p.m. on weekdays, and 5:30 a.m. PST (UTC+8) until 10:00 pm during weekends and holidays. It operates almost every day of the year unless otherwise announced. Special schedules are announced via the PA system in every station and also in newspapers and other mass media. During Holy Week, a public holiday in the Philippines, the rail system is closed for annual maintenance, owing to fewer commuters and traffic around the metro. Normal operation resumes after Easter Sunday.[8]
It has experimented with extended opening hours, the first of which included 24-hour operations beginning on June 1, 2009 (primarily aimed at serving call center agents and other workers in the business process outsourcing sector).[9] Citing low ridership figures and financial losses, this was suspended after two days, and operations were instead extended from 5:00 a.m. to 1:00 a.m.[10] Operations subsequently returned to the former schedule by April 2010, but services were again extended starting March 10, 2014, with trains running on a trial basis from 4:30 am to 11:30 pm in anticipation of major traffic buildup in light of several major road projects beginning in 2014.[11]
History
During the construction of the first line of the Manila Light Rail Transit System in the early 1980s, Electrowatt Engineering Services of Zürich designed a comprehensive plan for metro service in Metro Manila. The plan—still used as the basis for planning new metro lines—consisted of a 150-kilometer (93 mi) network of rapid transit lines spanning all major corridors within 20 years,[12] including a line on Epifanio de los Santos Avenue (EDSA), the region's busiest road corridor.
The project (originally known as the LRT-3 project) officially began in 1989, five years after the opening of the Line 1, with the Hong Kong-based EDSA LRT Corporation winning the public bidding for the line's construction during the term of President Corazon Aquino.[7] However, construction could not commence, with the project stalled as the Philippine government conducted several investigations into alleged irregularities with the project's contract.[13] In 1995, the Supreme Court upheld the regularity of the project (G.R. No. 114222, April 6, 1995) which paved the way for construction to finally begin during the term of President Fidel V. Ramos. A consortium of local companies, led by Fil-Estate Management, Ayala Land, and 5 others, later formed the Metro Rail Transit Corporation (MRTC) in June 1995 and took over the EDSA LRT Corporation.[7]
The MRTC was subsequently awarded a Build-Lease-Transfer contract by the DOTC, which meant that the latter would possess ownership of the system after the 25-year concession period. Meanwhile, the DOTC would assume all administrative functions, such as the regulation of fares and operations, leaving the MRTC responsibility over construction and maintenance of the system as well as the procurement of spare parts for trains. In exchange, the DOTC would pay the MRTC monthly fees for a certain number of years to reimburse any incurred costs.[14]
Construction began on October 15, 1996, with a BLT agreement signed between the Philippine government and the MRTC.[7] An amended turnkey agreement was later signed on September 16, 1997 with a consortium of companies (including Mitsubishi Heavy Industries and Sumitomo Corporation). A separate agreement was signed with ČKD Dopravní Systémy (ČKD Tatra, now part of Siemens AG), the leading builder of trams and light rail vehicles for the Eastern Bloc, on rolling stock. MRTC also retained the services of ICF Kaiser Engineers and Constructors to provide program management and technical oversight of the services for the design, construction management, and commissioning.[15]
During construction, the MRTC oversaw the design, construction, equipping, testing, and commissioning, while the DOTC oversaw technical supervision of the project activities covered by the BLT contract between the DOTC and MRTC. The DOTC also sought the services of SYSTRA, a French consultant firm, with regards to the technical competence, experience and track record in the construction and operations.[15]
On December 15, 1999, the initial section from North Avenue to Buendia was inaugurated by President Joseph Estrada,[16] with all remaining stations opening on July 20, 2000, a little over a month past the original deadline.[17] However, ridership was initially far below expectations when the line was still partially open, with passengers complaining of the tickets' steep price and the general lack of connectivity of the stations with other modes of public transportation.[18] Passengers' complaint of high ticket prices pointed to the maximum fare of ₱34, which at the time was significantly higher than a comparable journey on those lines operated by the LRTA and the PNR or a similar bus ride along EDSA. Although the MRTC projected 300,000–400,000 passengers riding the system daily, in the first month of operation the system saw a ridership of only 40,000 passengers daily (the ridership improved quickly, however, when passengers experienced significantly faster and convenient travel along EDSA, which experience soon spread by word of mouth).[19] The system was also initially criticized as a white elephant, comparing it to the Manila Light Rail Transit System and the Metro Manila Skyway.[20] To alleviate passenger complaints, the MRTC later reduced passenger fares to ₱15, as per the request of then President Joseph Estrada and a subsequent government subsidy.
By 2004, the line had the highest ridership of the three lines, with 400,000 passengers daily. By early 2015, the system was carrying around 550,000 commuters during weekdays and was often badly overcrowded during peak times of access during the day and night.
On October 27, 2018, the Department of Transportation started the gradual deployment of the 2nd generation trains, after various tests and audits.[21]
Station facilities, amenities, and services
With the exception of Buendia and Ayala stations, and the platform level of Taft Avenue and Boni stations, all stations are situated above ground, taking advantage of EDSA's topology.[22]
Station layout and accessibility
The stations have a standard layout, with a concourse level and a platform level. The concourse is usually above the platform, with stairs, escalators and elevators leading down to the platform level. Station concourses contain ticket booths, which is separated from the platform level by fare gates.[7] Some stations, such as Araneta Center-Cubao, are connected at concourse level to nearby buildings, such as shopping malls, for easier accessibility. Most stations are also barrier-free inside and outside the station, and trains have spaces for passengers using wheelchairs.[7]
Stations either have island platforms, such as Taft Avenue, Buendia, Boni Avenue, and Shaw Boulevard stations, and side platforms, such as from Magallanes station to Ayala stations, Guadalupe, and from Ortigas to North Avenue stations. Due to the very high patronage of the line, part of the platform corresponding to the front car of the train is cordoned off for the use of women, children, elderly and disabled passengers.
The stations are also designed to occupy the entire span of EDSA, allowing passengers to safely cross between one end of the road and the other.[7]
Shops and services
Inside the concourse of all stations are stalls or shops where people can buy food or drinks. Stalls vary by station, and some have fast food stalls. The number of stalls also varies by station, and stations tend to have a wide variety, especially in stations such as Ayala and Shaw Boulevard.
Stations such as Taft Avenue and North Avenue are connected to or are near shopping malls and/or other large shopping areas, where commuters are offered more shopping varieties.
Since November 19, 2001, in cooperation with the Philippine Daily Inquirer, passengers are offered copies of the Inquirer Libre, a free, tabloid-size, Tagalog version of the Inquirer, which is available at all stations.[23] In 2014, Pilipino Mirror also started distributing free tabloid newspapers.
Safety and security
The line has always presented itself as a safe system to travel in, which was affirmed in a 2004 World Bank paper prepared by Halcrow describing the overall state of metro rail transit operations in Manila as being "good".[24] However, in recent years after the DOTr (formerly DOTC) took over maintenance of the train system in 2012, the safety and reliability of the system has been put into question, with experts calling it "an accident waiting to happen", and while several incidents and accidents were reported between 2012 and 2014, that has not deterred commuters from continuing to patronize the system.[25] The Philippine government, meanwhile, continues to assert that the system is safe overall despite those incidents and accidents.[26]
With a current daily ridership of around 560,000 passengers, the line operates significantly above its designed capacity of between 360,000 and 380,000 passengers per day.[27] Operating over capacity since 2004,[6] government officials have admitted that capacity and system upgrades are overdue,[28] although the DOTr never acted on the numerous capacity expansion proposals of the private owners. In the absence of major investment in improving system safety and reliability, DOTr project management office of the line has resorted to experimenting with and/or implementing other solutions to reduce strain on the system, including crowd management on station platforms,[29] the proposed implementation of peak-hour express train service.[30] However, some of these solutions, such as platform crowd management, are unpopular with passengers.[31]
For safety and security reasons, persons who are visibly intoxicated, insane and/or under the influence of controlled substances, persons carrying flammable materials and/or explosives, persons carrying bulky objects or items over 1.5 meters (5 ft) tall and/or wide, and persons bringing pets and/or other animals are prohibited from entering the line.[32] Products in tin cans are also prohibited on board, citing the possibility of home-made bombs being concealed inside the cans.[33]
In 2000 and 2001, in response to the Rizal Day bombings and the September 11 attacks, security was stepped up on the line. The Philippine National Police has a special police force,[34] and security police provided by private companies can be found in all stations. All stations have a head guard. Some stations may also have a deployed K9 bomb-sniffing dog. It also employs the use of closed-circuit television inside all stations to monitor suspicious activities and to assure safety and security aboard the line. Passengers are also advised to look out for thieves, who can take advantage of the crowding aboard the trains. Wanted posters are posted at all stations to help commuters identify known thieves.
Ridership
The original designed ridership of the line is 350,000, yet as the years passed, the number doubled to as much as 650,000 in 2012–2013, due to the time consumed when commuting via EDSA, as well as the speed of the trains reaching up to 60 kilometers per hour (37 mph), and connectivity to Metro Manila's major transport hubs and central business districts. The daily ridership can reach as much as 300,000–500,000 passengers from 2012 to 2016, despite poor maintenance and long lines, causing the government to launch bus services, known as MRT Buses, around its stations, to serve as alternatives for 1 Million passengers. In addition to the rising daily ridership that continues to exceed the line's designed capacity, and as it continues to implement the metro line's capacity expansion project, it aims to reach a ridership of 800,000 daily passengers as all of the new trains from China will be added to its current fleet.[35]
Currently, the line serves more than 320,000 passengers, while running at a maximum speed of up to 60 km/h (37 mph) in 3.5-4 minute intervals, from the previous 30 km/h (19 mph) in 8–10 minute intervals.
Fares and ticketing
The line, like all other lines in Metro Manila, uses a distance-based fare structure, with fares ranging from 13 to 28 pesos (29 to 63 U.S. cents), depending on the destination. Commuters who ride the line are charged ₱13 for the first two stations, ₱16 for 3–4 stations, ₱20 for 5–7 stations, ₱24 for 8–10 stations and ₱28 for 11 stations or the entire line. Children below 1.02 meters (3 ft 4.4 in) (the height of a fare gate) may ride for free.
Magnetic tickets (1999–2015)
Two types of tickets exist: a single-journey (one-way) ticket whose cost is dependent on the destination, and a stored-value (multiple-use) ticket for 100 pesos. The 200-peso & 500-peso stored-value tickets were issued in the past, but have since been phased out. The single-journey ticket is valid only on the date of purchase. Meanwhile, the stored-value ticket is valid for three months from date of first use.[32]
The tickets come in several incarnations: these include tickets bearing the portraits of former presidents Joseph Estrada and Gloria Macapagal-Arroyo,[36] which have since been phased out, and one bearing the logos of the DOTC and the MRTC. Ticket shortages are common: in 2005, the MRTC was forced to recycle tickets bearing Estrada's portrait to address critical ticket shortages, even resorting to borrowing stored-value tickets from the LRTA[37] and even cutting unusable tickets in half for use as manual passes. Shortages were also reported in 2012,[38] and the DOTC was working on procuring additional tickets in 2014.[39] Because of the ticket shortages, it had become common practice for regular passengers to purchase several stored-value tickets at a time, though ticket shortages still persist.[40]
Although it has partnered with private telecommunications companies in experimenting with RFID technology as an alternative ticketing system in the past,[41][42] these were phased out in 2009.[43]
Beep cards (2015–present)
Currently, inter-operable beep cards with similar-to-the-previous single-journey and stored-value ticket types are now issued, along with the deployment of brand-new ticketing machines that replaced the barely-used ticketing machines that has been in place since the line's inauguration. The beep, tap-and-go tickets, loadable up to ₱10,000 can be used in all three rail lines since December 2015.
Fare adjustment
Adjusting passenger fares was ordered by President Joseph Estrada as a means to boost flagging ridership figures,[44] and the issue of fares both historically and in the present day continues to be a contentious political issue involving officials at even the highest levels of government.
Current fare levels were set on January 4, 2015 as a consequence of DOTr (formerly DOTC) having to increase fares for Line 1 as per their concession agreement with MPIC-Ayala, with fare hikes delayed for several years despite inflation and rising operating costs.[45] Prior to the current fares levels, fares were set on July 15, 2000 under the orders of then President Estrada; this was intended to have the line become competitive against other modes of transport,[46] but had the effect of causing revenue shortfalls which the government shouldered. While originally set to last only until January 2001,[46] the new fare structure persisted due to strong public opposition against increasing fares,[47] especially as ridership increased significantly after lower fares were implemented.[44] These lower fares—which are only slightly more expensive than jeepney fares—ended up being financed through large government subsidies amounting to around ₱45 per passenger,[47][48] and which for both the MRT and LRT reached ₱75 billion for the 10-year period between 2004 and 2014.[49] Without subsidies, the cost of a single trip is estimated at around ₱60,[48] and a ₱10 increase in fares would yield additional monthly revenues of ₱2–3 billion a month.[50]
Passenger fare subsidies are unpopular outside Metro Manila, with subsidy opponents claiming that their taxes are being used to subsidize Metro Manila commuters without any benefit to the countryside, and that the fare subsidies should be used for infrastructure improvements in the rest of the country.[51] In his 2013 State of the Nation Address, President Benigno Aquino III claimed that it would be unfair for non-Metro Manila residents to use their taxes to subsidize the LRT and MRT.[52] However, supporters of the subsidies claimed that the rest of the country benefits economically from efficient transportation in Metro Manila.[53]
Rolling stock
Two train types run in the line, the latest being those purchased from CRRC Dalian, under the Aquino administration.
The deployment of the Dalian trainsets was delayed due to several factors, including weight limits on existing tracks and inconsistencies in production, which has since been corrected. Due to these factors, only 3 trainsets, with 1 reserve trainset, are in operation for daily revenue services, while the targeted deadline for the full deployment of the Dalian Trainsets are set on July 2021.[54]
The maximum speed of these trains is 80 km/h (50 mph), but currently run at a safe speed of 30 to 60 km/h (19 to 37 mph). The trains currently run at a operational maximum speed of 60 km/h (37 mph) on December 2020, due to the completion of the rail replacement program. Previously, all trains ran at speeds of 30 km/h (19 mph) due to worn-out tracks. However, due to the Enhanced community quarantine in Luzon, the rail replacement works has been fast-tracked and was completed on September 2020, a few months ahead of its targeted completion, while finishing the rail replacement on the line's Taft Avenue switch tracks on November 2020. Due to the installation of new railway tracks, the maximum speed of the trains were gradually increased, from 30 km/h (19 mph), to 40 km/h (25 mph) on October 2020, and to 50 km/h (31 mph) on November 2020.[55][56][57]
Rolling stock | First-generation[58][59] | Second-generation[60][61] |
---|---|---|
Year | 1999 | 2016 |
Manufacturer | ČKD Tatra | CRRC Dalian |
Model | Class 3000/000 ČKD Tatra RT8D5M | Class 3100 CRRC Dalian 8MLB |
Number built (cars) | 73 built (57 in service, 19 trains operational in 3 car trainsets)[62] | 48 built (12 in service, 4 trains available for revenue service, 36 undergoing evaluation)[63] |
Length | 33,000 mm (108 ft) (31,720 mm (104.07 ft) without couplers) | |
Width | 2,480 mm (8.14 ft) | 2,500 mm (8.2 ft) |
Height (pantograph lowered) | 3,550 mm (11.65 ft) | 3,650 mm (11.98 ft) |
Door height | 1,900 mm (6.2 ft) | |
Door width | 1,255 mm (4.117 ft) | |
Floor height | 925 mm (36.4 in) | |
Minimum curve radius | 20 m (66 ft) | 25 m (82 ft) |
Empty weight | 46,800 kg (103,200 lb) | 49,700 kg (109,600 lb)[62] |
Body shell material | Low alloy high tensile steel (aluminum for ceiling) |
Stainless steel |
Electrification | 750 V DC overhead lines | |
Transmission | Right-angle cardan drive | Quill drive |
Traction control | IGBT chopper (ČKD) | IGBT-VVVF (Voith) |
Traction motor | 64.5 kW DC motor (ČKD) | 120 kW totally enclosed AC induction motor (Traktionssysteme Austria) |
Seating capacity | 74 | |
Standing capacity | 320 (8 passengers/square meter) | |
Maximum operating speed | 65 km/h (40 mph) | |
Acceleration | 1.03 m/s^2 | at least 1.03 m/s^2 |
Deceleration (normal and emergency) | 1.01 m/s^2-1.58 m/s^2 | at least 1.01 m/s^2-1.58 m/s^2 |
Maximum gradient | 5% | at least 5% |
Configuration | 3 car sets (4 car planned) | |
Total capacity (3–4 cars) | 1182/1576 passengers | 1182[62]/1576 passengers |
Wheelbase | 1,900 mm (6.2 ft) | |
Status | In service; under rehabilitation | In service[64] or under testing |
The system has 73 light rail vehicles (LRV) made in the Czech Republic by ČKD (now part of Siemens AG) in a three-car configuration, a number of which are now damaged due to poor maintenance since 2012 by the previous appointed contractor of DOTC (now DOTr).[3] The LRV's were purchased with export financing from the Czech government.[65] Trains have a capacity of 1,182 passengers,[3] which is a little bigger than the normal capacity of LRT Line 1 first generation rolling stock, although trains came with air conditioning. Despite this, it is designed to carry in excess of 23,000 passengers per hour per direction (PPHPD), and is expandable to accommodate 48,000 passengers per hour per direction.[2]
The plans for new rolling stock has been an issue for the MRT during the Aquino Administration, with plans to acquire 52 second-hand LRVs offered from Spain, under the leadership of then DOTC Secretary Joseph Emilio Abaya, with ₱8.43 billion budget, along with Inekon Trams.[66][67] However, undisclosed issues and train incompatibility issues regarding the project, the project was downgraded to 48 LRVs, with the contract having CRRC Dalian supply 48 new LRVs.
Due to poor maintenance by the previous maintenance contractors, the line previously operated with 7–10 minute headways under the DOTr orders,[68] and the system's passenger volume is presently closer to 14,000–18,000 passengers per hour per direction. With the enhancements and rehabilitation, the delays were gradually shortened, but the passenger volume is still limited due to COVID-19 prevention policies still in effect.
Early 2018, lack of spare parts for the trains decreased the number of usable trains to just 3 operational trains running during peak hour[69] however by April 2018, 14–16 trains are now operational in peak and off-peak hours.[70] On October 27, 2018, DOTr started the gradual deployment of the 2nd-generation trains.[21] Three trainsets are set for full deployment by the end of 2019, as signalling upgrades and safety certificates are being made under the takeover of Sumitomo.[71]
Due to aging air conditioning units that have been in place since the line's inauguration and complaints of uncomfortable indoor temperatures from riders, replacement air conditioning units for the first-generation trainsets were ordered from Thermo King and installed.
The Passenger Assist Railway Display System (PARDS), a passenger information system powered by LCD screens installed near the ceiling of the train that shows news, advertisements, current train location, arrivals and station layouts, are already installed inside the trains. PARDS is also installed on trains on LRT lines 1 and 2.[72]
Depot
The line maintains an underground depot in Quezon City near North Avenue station. On top of the depot is TriNoma, a shopping mall owned by the Ayala Corporation. The depot occupies 84,444 square meters (908,950 sq ft) of space and serves as the center of operations and maintenance. It is connected to the mainline through a spur line. The depot is capable of storing 81 light rail vehicles, with the option to expand to include 40 more vehicles as demand arises. They are parked on nine sets of tracks, which converge onto the spur route and later on to the main network. However, a lot of rail tracks for storage inside the depot were taken by DOTr to repair broken rails, as DOTr's previous maintenance provider did not purchase spare rails.
Maintenance
Firm | From | Until | |
---|---|---|---|
Sumitomo Group | January 1, 2001 | October 18, 2012 | |
PH Trams CB & T | October 19, 2012 | September 3, 2013 | |
Global APT | September 4, 2013 | July 4, 2015 | |
SBI CB & T | July 5, 2015 | January 8, 2016 | |
Busan Universal Rail, Inc. | January 9, 2016 | November 5, 2017 | |
Department of Transportation[74] | November 6, 2017 | November 7, 2018 | |
Sumitomo Group[75] | November 8, 2018 | present | |
Under DOTC Secretary Abaya
By 2014, the line was seen to have significantly deteriorated due to the removal of tested maintenance provider Sumitomo Corp. in 2012 by the then Department of Transportation and Communications (Predecessor of DOTr) and its persistence in using unqualified maintenance providers. The government of Benigno Aquino III had been planning to buy the line from the MRT Corporation (MRTC), the private concessionaire that built the line, and then bid it out to private bidders. The Aquino government accused the MRTC of neglecting and not improving the services of the line under its watch.[76]
In February 2016, the Philippine Senate released a report stating that DOTC Secretary Jun Abaya and other DOTC officials "may have violated" the Anti-Graft and Corrupt Practices Act in relation to questionable contracts with the subsequent maintenance providers.[77] In a Senate report where the line's condition was found to be in "poor maintenance" as per studies made by MTR HK,[78] DOTC officials were reported to be involved in graft in relation to questionable contracts, especially those for the maintenance of the line.[79]
Under Busan Universal Rail Inc. (2016–2017)
A Korean-Filipino consortium, Busan Universal Rail Inc. (BURI), became the maintenance provider of the line in January 2016. In 2017, DOTC's succeeding agency, the Department of Transportation (DOTr) attributed the operation's disruptions of the rail system to BURI with Transport Undersecretary noting 98 service interruptions and 833 passenger unloadings (or average of twice daily) as well as train derailments in April–June 2017.[73]
BURI insisted that the disruptions the railway line was experiencing is due to "inherent design and quality concerns" and not to poor maintenance or normal tear or wear. It said that the trains had "excessive lateral movement", the train-protection equipment has a "short delay time", the trains' air conditioning system were "underrated", and other equipments and features such as bogie frames, couplers, line contractors, and tracks are of "poor quality".[80]
The maintenance provider also said that the design flaws in the railway line has been causing disruptions since the first year of operation in the year 2000. According to data cited by BURI 1,492 glitches were recorded in 2000, 1,927 glitches in 2008 and the figure rose to 2,199 in 2009. MRT Corp. the owner of the line dismissed BURI's claim on the train's lateral movement and said that the issues raised by the firm were absent when the line was maintained by Sumitomo.[80]
The DOTr announced its intentions on August 24, 2017 to terminate its contract with BURI.[81] By October 2017, the government agency issued its termination notice and took over maintenance by November 2017.[74]
Return of Sumitomo
Due to dissatisfaction in performance, the government planned to replace BURI with the maintenance provider of Singapore's MRT, France's RATP, or Sumitomo back as the maintenance provider.[74] In late-November it was reported that Sumitomo will return as the maintenance provider for the line with an agreement to formalize the beginning of talks to facilitate the return of the firm within the later-half of December 2017. The DOTr projects that Sumitomo could work with the line again by around October–December 2018.[82]
The comeback of Sumitomo commenced with an Exchange of Notes signed on November 7, followed by the loan agreement the next day.[83] On December 27, 2018, Sumitomo and DOTr signed the contract for the rehabilitation of the line.[84] The rehabilitation started in February 2019 and is expected to last for 43 months.[85] The maintenance deal is worth $32.6 million (₱1.608 billion).[86]
The rehabilitation includes the overhaul of the all MRTC Class 3000 vehicles, as well as the deployment of 3 MRTC Class 3100 train sets, escalator and elevator operations; railway track, communication and signalling system replacement, and upgrades on power supply, overhead systems, maintenance and station equipment.[87] Interest in deploying the rest of the Class 3100 trains were expressed both by DOTr and Sumitomo, but ultimately will be deferred pending railtrack replacement and further equipment rehabilitation.[88] The newer Dalian trains that have not undergone RAMS test are currently stored at the LRT-1 depot in Paranaque.
As of July 2020, the rehabilitation project is now 49.94 percent complete.
Plans and proposals
Capacity Expansion Project
Due to the high ridership of the line, a proposal under study by the DOTC and NEDA proposed to double the current capacity by acquiring additional light rail vehicles to accommodate over 520,000 passenger a day.[89]
In line with this need, the DOTC secured the procurement of a total of 48 light rail vehicles (LRVs) or 16 trains from Chinese rolling stock manufacturer CRRC Dalian. Delivery began in January 2016 until January 2017. The introduction of the new LRVs will allow the line to now handle over 800,000 passengers.[35]
The first train was scheduled to be in revenue service before April 2016[90][91] but delays in its 5,000 kilometers (3,100 mi) run test had delayed its deployment for Revenue service.[92][93] Moreover, further tests and analysis of the new trains revealed several incompatibilities that made it unable to run along the lines safely, which was a subject of audit from TuV Rheinland, hired by the DOTr to determine the true usability of the trains.
Later, it was revealed that several adjustments to the Dalian trains are required prior to revenue run deployment.[94] The train manufacturer CRRC Dalian has agreed to amend the train specifications to match the contract terms at no cost, and will do so in the soonest possible time.[95] Due to the Dalian trains undergoing said adjustments, they are now slowly being introduced into revenue runs.
Plans were also laid to increase the number of cars in each train set, from the current 3-car configuration to 4-car configuration, which also increases the number of passengers being accommodated for each trip, from 1182 passengers to 1576 passengers for each train set. The transportation department, along with railway experts also revealed from studies that the MRT system can upgrade the line's entire power supply and signalling systems, for the line to coincide with the high commuting demand and increase the number of trains needed to serve the railway line daily, from 21 trains to 25-32 trains running along the line.
Platform screen doors were also planned for each station, with the plans for the platform doors were laid out as early as 2013,[96] however, these plans were delayed until it was reconsidered in 2017.[97]
Line merge with Line 1
Although Phase 1 of the line (Taft Avenue to North Avenue) has already been built, the route envisioned by the DOTC and the government, in general, was for it to traverse the entire length of EDSA (from Monumento to Taft Avenue), eventually meeting with the LRT 1 at Monumento in Caloocan (Phase 2) to create a seamless rail loop around Metro Manila. The expansion has been shelved by then President Gloria Arroyo in favor of the LRT Line 1's extension from Monumento to a new common station that it will share with at North Avenue, thus closing the loop. However, this move of President Arroyo to take away Phase 2 had proven to be ill-advised as the ridership is very low at only about 30,000 passengers a day. The southern terminus of the MRT 7 (originally Line 4 along Quezon Avenue., but had since changed route several times), which will link Quezon City, Caloocan (north), and San Jose del Monte City, Bulacan will be sharing the same station.
The National Economic and Development Authority as well as then President Arroyo herself have said that the link at North Avenue is a national priority, since it would not only provide seamless service between the LRT 1 and MRT 3, but would also help decongest Metro Manila.[98] It is estimated that by 2010, when the extension is completed, some 684,000 commuters would use the line every day from the present 400,000, and traffic congestion on EDSA would be cut by as much as 50%.[99]
Proposals to fully unite LRT 1 and MRT 3 operations and systems have been pitched but has not been pursued so far. Feasibility tests for this proposition included LRT 1 trains visiting MRT 3 depot facilities and running them on the entire line. It has since been shelved for undisclosed reasons, but may be a possibility should Manny Pangilinan's Metro Pacific attempts to purchase the entire system succeed. If and when this happens, the system may be theoretically controlled or connected to LRT 1's current operating concessionaire, LRMC (Light Rail Manila Consortium), of whom Pangilinan has a controlling stake, paving the way to a possible line merger.
Transfer of operations from MRTC to LRTA
A new study for the Metro Manila Rail Network has been unveiled by DOTC Undersecretary for Public Information Dante Velasco that LRT 1, LRT 2, and MRT 3 will be placed under the management of the Light Rail Transit Authority (LRTA). This is due to maintenance cost issues for LRT 1's maintenance cost, which is approximately ₱35 million, along with Line 2's ₱25 million and Line 3's ₱54 million maintenance costs. Another reason for this study is for the unification of the lines. According to DOTC Undersecretary for Rails Glicerio Sicat, the transfer was set by the government in June 2011.[100] However, it is unlikely that the private owners, MRTC, will approve this plan.
On January 13, 2011, Light Rail Transit Authority Chief Rafael S. Rodriguez took over as officer-in-charge of the line in preparation for the integration of operations of the three lines,[101] but with the entry of a new leadership into the MRTC that year and in 2012, the transfer was deemed not likely to happen; however, in April 2012, a LRT 1 trainset made the first trial journey to the MRT 3 depot.
On May 26, 2014, the line's general manager Al Vitangcol was sacked by Transportation and Communication Secretary Joseph Emilio Abaya, and was replaced by LRTA Administrator Honorito Chaneco as officer-in-charge. The move came after Vitangcol was accused by the ambassador of the Czech Republic of extortion and for awarding an anomalous deal, the maintenance contract, to an uncle-in-law.[102]
Common station with LRT 1, MRT 7, and the Metro Manila Subway
On November 21, 2013, the NEDA board, chaired by then Former President Benigno Aquino III, approved the construction of a common station within North Avenue between SM City North EDSA and TriNoma Mall. It is estimated to cost 1.4 billion pesos. It will feature head-to-head platforms for LRT 1 and MRT 3 trains with a 147.4 m (484 ft) elevated walkalator to MRT 7.[103] SM Investments Corporation posted 200 million pesos for the naming rights of the common station.[104] This is inconsistent with the original plan of having seamless connectivity to Monumento and is also an unusual arrangement of having two train stations beside each other. However, the project was shelved indefinitely due to disputes over cost, engineering issues and naming rights.[105] Even if the physical infrastructure connecting the two rail systems are in place and successfully tested, commuters have to go down at the Roosevelt station of Line 1 and walk over or take a tricycle or jeepney for the one kilometer distance to the Trinoma terminal of Line 3.[106] The Supreme Court halted the construction of the project in August 2014 after SM Prime Holdings contested the new location near Trinoma.[107][108] An agreement was later reached under the administration of President Rodrigo Duterte, and the common station is now under construction.[109]
Incidents
During the testing period of the system, the MRT–3 has been prone to numerous disruptions and breakdowns due to technical problems in the overall systems and design since its opening in 1999, due to many factors, such as the humid conditions in the country, lack of accessibility to the stations, and incompatible problems in the rolling stock, causing major adjustments to the system.
However, problems start to arise in 2012, due to poor maintenance causing train glitches, lack of spare parts, and negligence, the system has faced numerous interruptions and accidents. This in turn has caused lower ridership, frequent unloading of passengers and passenger inconvenience.[110]
- On November 3, 2012, a train from the Araneta Center-Cubao Station caught fire as it approached GMA-Kamuning Station, causing passengers to scramble to the exits, and having two women injured. The train caught fire due to electrical short-circuit technical failure.[111]
- On March 19, 2013, operations were halted between the Taft Avenue and Magallanes Stations due to two high-voltage breakers being tripped off, which was caused by a Surge arrester being snapped. This, together with the lack of spare parts, caused disruption of power in the whole northbound system.[112]
- On March 26, 2014, at 10:50 am, a southbound train at Guadalupe Station suddenly stopped due to the train driver not observing the red light status at the Guadalupe Station and accelerated southbound without getting prior clearance from the Control Center, causing the automatic train stop system to trigger, resulting in 8 injuries.[113]
- On June 3, 2014, a lightning strike hit the MRT's overhead lines between GMA-Kamuning and Quezon Avenue station. The situation normalized two hours later.[114]
- On August 13, 2014, a southbound train heading to Taft Avenue station derailed and overshot to the streets. The train first stopped after leaving Magallanes station due to a technical problem. Later on, the train broke down altogether, so another train was used to push the stalled train. During this process, however, the first train got detached from the rails and overshot towards Taft Avenue, breaking the concrete barriers and falling to the street below. At least 38 people were injured. The accident was blamed on 2 train drivers and 2 control personnel for failing to follow the proper coordination procedures and protocol.[115][116]
- On October 23, 2017, at 6:16 am, a thrown used adult diaper was seen at the overhead catenary lines between Ayala and Buendia Stations. On the same morning at 8:16 AM, a south-bound train from Shaw Boulevard unloaded passengers due to a train door malfunction.[117]
- On November 16, 2017, at 11:30 am, at least 140 passengers were evacuated from a "detached train" coach between the railway lines of Buendia and Ayala Avenue Stations.[118]
- On March 18, 2019, at 6:02 pm, a southbound train was stopped after smoke caused by a short circuit fire at the train's traction motors was being emitted while in between the Araneta Center-Cubao and Santolan stations.[119]
- On September 6, 2019, an overhead line section snapped at Guadalupe Station, causing a power supply glitch in the whole line affecting over 7,000 passengers. Partial operations began from North Avenue Station to Shaw Boulevard Station. The situation normalized at 5:00 pm.[120]
- On November 5, 2019, at 4:08 pm, a train suddenly emitted smoke while on the northbound track of the line. Around 530 passengers were unloaded. Around two hours after the incident, the operation of the line was back to normal.[121]
- On February 5, 2020, at 7:18 AM, a northbound train at Ayala station unloaded some 700 passengers because of a door failure. The unloaded passengers were able to board the next train after 5 minutes.[122]
References
- "About Us – MRT3 Stations". Metro Rail Transit. Archived from the original on January 22, 2013. Retrieved June 8, 2014.
- "About Us – Background". Metro Rail Transit. Archived from the original on May 8, 2014. Retrieved June 8, 2014.
- "About Us – Trains". Metro Rail Transit. Archived from the original on May 8, 2014. Retrieved June 8, 2014.
- Salazar, Irineo B. R. (January 31, 2016). "On a clear day you can see the MRT". The Society of Honor by Joe America. Retrieved July 20, 2016.
- Mendez, Christina (August 11, 2015). "Poe's Senate panel to resume hearing on Line 3". Retrieved July 20, 2016.
- Amojelar, Darwin G. (August 14, 2014). "DERAILED | 5 things you should know about MRT3 and the mess it's in". TV5 News and Information. Archived from the original on August 16, 2014. Retrieved August 17, 2014.
- Anonas, Alma S. (June 10, 1999). "On track and heading for Year 2K on MRT-3". Manila Standard. Kamahalan Publishing Corporation. Retrieved January 21, 2014.
- Ronda, Rainier Allan (March 31, 2010). "LRT, MRT closed for Holy Week". The Philippine Star. PhilStar Daily, Inc. Retrieved August 21, 2014.
- Olchondra, Riza T. (May 29, 2009). "MRT-3 rides to go 24 hours starting June 1". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Archived from the original on May 30, 2009. Retrieved May 31, 2009.
- Kwok, Abigail (June 3, 2009). "MRT-3 stops 24-hour run". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Archived from the original on October 27, 2014. Retrieved March 11, 2014.
- Camus, Miguel R.; Calleja, Niña P. (February 21, 2014). "DOTC extends MRT-3 operating hours". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Retrieved March 11, 2014.
- "Light Rail Transit Authority Company History". Light Rail Transit Authority. Archived from the original on September 24, 2014. Retrieved September 13, 2014.
- Macaspac, Joem H.; Garcia, Ma. Luisa M. (March 28, 1996). "First phase of Edsa metro rail transit system under way". Manila Standard. Kamahalan Publishing Corporation. Retrieved January 21, 2014.
- Background Archived June 26, 2006, at the Wayback Machine, Metro Rail Transit Corporation History. Retrieved July 7, 2006.
- Construction Archived June 26, 2006, at the Wayback Machine, Metro Rail Transit Corporation History. Retrieved July 7, 2006.
- "Miracle rail project to rid Edsa of jams". New Straits Times. The New Straits Times Press (M) Bhd. December 15, 1999. Retrieved January 21, 2014.
- "MRT 3 Fully Completed; Inauguration, Turnover Set on July 20". Manila Bulletin. Manila Bulletin Publishing Corporation. July 16, 2000. Retrieved August 14, 2014 – via Questia Online Library.
- Trinidad, Andrea H. (January 2, 2000). "Metrostar Express proves a big disappointment". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Retrieved January 21, 2014.
- Rivera, Blanche S. (January 13, 2000). "Metro trains on EDSA running almost empty". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Retrieved January 21, 2014.
- Katigbak, J.R. (January 8, 2000). "New white elephants in Metro Manila". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Retrieved January 21, 2014.
- "Department of Transportation – Philippines". www.facebook.com. Retrieved October 27, 2018.
- Satre, Gary L. (June 1998). "The Metro Manila LRT System—A Historical Perspective" (PDF). Japan Railway and Transport Review. 16: 33–37. Archived from the original (PDF) on May 5, 2006. Retrieved August 14, 2014.
- Ulanday, Abelardo S. (December 9, 2001). "The best things in life are Libre". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Retrieved August 14, 2014.
- World Bank (December 2, 2004). "A Tale of Three Cities: Urban Rail Concessions in Bangkok, Kuala Lumpur and Manila – Final Report" (PDF): 17. Archived from the original (PDF) on April 25, 2006. Cite journal requires
|journal=
(help) (Prepared by Halcrow Group Limited). - "Months ago, experts warned line was unsafe". ABS-CBN News and Current Affairs. August 13, 2014. Retrieved August 17, 2014.
- Ayalin, Adrian (August 15, 2013). "MRT-3: A history of accidents". Primetime on ANC. ABS-CBN News Channel.
- Hegina, Aries Joseph (August 14, 2014). "Abaya: MRT3 is safe, riding it 'a personal decision'". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Retrieved August 21, 2014.
- de Fiesta, Ria (February 27, 2014). "Abaya: MRT-3 operating at overcapacity". ABS-CBN News and Current Affairs. Retrieved August 17, 2014.
- Cupin, Bea (August 14, 2014). "Abaya admits MRT-3 upgrade overdue". Rappler. Retrieved August 17, 2014.
- Manabat, Johnson (December 18, 2013). "MRT-3 enforces new crowd control scheme". ABS-CBN News and Current Affairs. Retrieved August 17, 2014.
- Camus, Miguel R. (May 6, 2014). "All is set for MRT-3 express train run". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Retrieved August 18, 2014.
- Camus, Miguel R. (December 20, 2013). "MRT-3 boss defends 'crowd control' amid jeering riders". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Retrieved August 17, 2014.
- "MRT3 Reminders". Metro Rail Transit Line 3. Metro Rail Transit Corporation. Archived from the original on August 19, 2014. Retrieved August 17, 2014.
- Antiporda, Jefferson (August 10, 2005). "MRT-3 issues directive imposing ban on tin cans". The Manila Times. Manila Times Publishing Corporation. Archived from the original on August 19, 2006. Retrieved May 19, 2006.
- Del Puerto, Luige A.; Quismundo, Tarra V. (November 13, 2004). "New task force formed to keep LRT, MRT safe". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Archived from the original on January 4, 2005. Retrieved May 19, 2006.
- "More MRT-3 coaches on the way". Official Gazette of the Republic of the Philippines. January 18, 2016. Retrieved April 20, 2016.
- Araneta, Sandy (October 21, 2005). "DOTC: MRT-3 fare could increase by P10 in 2006". The Philippine Star. PhilStar Daily, Inc. Retrieved May 19, 2006.
- Casanova, Sheryll B. (November 12, 2003). "MRTC borrows value tickets from LRTA". The Manila Times. Manila Times Publishing Corporation. Archived from the original on January 5, 2004. Retrieved May 18, 2006.
- Amojelar, Darwin G. (September 21, 2012). "Expect long queues at MRT-3 amid shortage of tickets – MRT3". TV5 News and Information. Archived from the original on September 13, 2014. Retrieved September 13, 2014.
- Agcaoili, Lawrence (July 20, 2014). "DOTC earmarks P25M to buy additional MRT-3 tickets". ABS-CBN News and Current Affairs. Retrieved September 13, 2014.
- "MRT3 woes". The Manila Times. Manila Times Publishing Corporation. November 16, 2005. Archived from the original on December 8, 2015. Retrieved July 2, 2006.
- Reyes, Mary Ann Ll. (November 17, 2006). "Globe bares G-Pass ticketing for MRT3". The Philippine Star. PhilStar Daily, Inc. Retrieved September 13, 2014.
- Reyes, Mary Ann Ll. (March 31, 2007). "Smart ties up with MetroPass on MRT-3". The Philippine Star. PhilStar Daily, Inc. Retrieved September 13, 2014.
- Amojelar, Darwin G. (January 29, 2013). "Ayala group to bid for common ticket system". TV5 News and Information. Archived from the original on October 19, 2014. Retrieved September 23, 2014.
- Serfino, Dennis C. (May 1, 2003). "Metro Star still can't get enough revenue". Manila Standard. Kamahalan Publishing Corporation. Retrieved April 23, 2014.
- "LRT-MRT FARES TO BE INCREASED ON JAN.4". dotc.gov.ph. Department of Transportation and Communications (DOTC). Archived from the original on December 25, 2014. Retrieved March 10, 2015.
- Tuazon, Brenda P. (July 16, 2000). "Estrada Orders MRT3 Firm to Reduce Metrostar Fares". Manila Bulletin. Manila Bulletin Publishing Corporation. Retrieved August 14, 2014 – via Questia Online Library.
- Mandri-Perrott, Cledan (2000). Private Sector Participation in Light Rail-Light Metro Transit Initiatives. Washington, D.C.: World Bank. p. 94. ISBN 0821380850.
- Diokno, Benjamin E. (December 17, 2013). "Folly of government subsidy". BusinessWorld. BusinessWorld Publishing Corporation. Retrieved April 25, 2014.
- Valderrama, Tita C. (February 9, 2014). "Messed up mass transport system". The Manila Times. Manila Times Publishing Corporation. Archived from the original on April 23, 2014. Retrieved April 23, 2014.
- Agcaoili, Lawrence (December 14, 2013). "DOTC says MRT, LRT fare hike to yield P2-B add'l revenues". The Philippine Star. PhilStar Daily, Inc. Retrieved April 23, 2014.
- Casauay, Angela (October 25, 2012). "Visayan solons back P10 MRT3 fare hike". Rappler. Retrieved September 23, 2014.
- Aquino III, Benigno S. (July 22, 2013). [English] Benigno S. Aquino III, Fourth State of the Nation Address, July 22, 2013 (Speech). State of the Nation Address. Quezon City. Retrieved September 23, 2014.
Each trip that one passenger makes on the LRT is estimated to cost 40 pesos. What does each passenger pay? 15 pesos. This means that the government subsidizes the remaining 25 pesos. As for the line, the true cost of one trip is 60 pesos: 15 pesos paid by passengers, 45 pesos by the government—in the end, each and every Filipino pays a share of the subsidy. Whether you live in Mindanao or Visayas, and not once have you ever stepped onto the LRT or MRT, you help to fund this.
- Cruz, Neal H. (November 18, 2012). "No improved MRT3 service, no fare hike". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Retrieved September 23, 2014.
- Peralta, Janine (October 16, 2019). "All Dalian trains for MRT-3 line to be fully operational by July 2021 – MRT". CNN Philippines. Retrieved March 3, 2020.
- https://newsinfo.inquirer.net/1369292/mrt-3-now-runs-at-60-kph-speed/amp
- Balinbin, Arjay L. (May 19, 2020). "MRT-3 train speed, capacity expected to double by December". BusinessWorld. Retrieved June 7, 2020.
- Subingsubing, Krixia (May 20, 2020). "DOTr: Over half of MRT 3's tracks replaced". Inquirer.net. Retrieved June 7, 2020.
- "Procurement of MRT3 Capacity Expansion Project Lot 2 : Upgrade of Ancillary Systems" (PDF). December 2010. pp. 87–89. Retrieved May 1, 2016.
- "Tramcar RT8D5M Model Basic Features". skd.cz. SKD. Retrieved November 1, 2020.
- "DS_Manila-MRT3_18_vvk_DS2399_en.pdf" (PDF). Voith.com. Voith. Retrieved May 28, 2020.
- http://www.crrcgc.cc/dl/g8425/s16347/t281974.aspx
- "China-made trains within 'allowable' weight for MRT: consultant". ABS-CBN News. February 20, 2018. Retrieved February 22, 2018.
- Rey, Aika (January 23, 2019). "LOOK: 3rd China-made Dalian train hits MRT3 tracks until February 1". Rappler. Retrieved January 23, 2019.
- "More transport services to resume operations on June 1". CNN Philippines. May 31, 2020. Retrieved June 4, 2020.
- "MRT3 stress and Camp John Hay turmoil". The Manila Times. Manila Times Publishing Corporation. June 21, 2005. Retrieved July 2, 2006.
- Macapagal, Maan (February 2, 2013). "MRT-3 to get additional 52 coaches". ABS-CBN News.
- Agcaoili, Lawrence (September 12, 2013). "Inekon: PH can save $5M a year with new MRT trains". ABS-CBN News.
- "About Us – Train Schedules". Metro Rail Transit. Archived from the original on May 8, 2014. Retrieved June 8, 2014.
- "MRT3 Only 3 trains running as spare parts start arriving". Interaksyon. February 14, 2018. Retrieved February 19, 2018.
- "MRT records 16 running trains". ABS-CBN News. April 5, 2018. Retrieved April 10, 2018.
- Esmael, Lisbet K. (September 16, 2019). "MRT to 'gradually' deploy Dalian trains".
- "Passenger information system to be installed in LRT, MRT". BusinessWorld. March 27, 2019. Retrieved December 12, 2020.
- Dela Paz, Chrisee (August 28, 2017). "Busan Universal Rail calls DOTr's move to end contract 'unfair'". Rappler. Retrieved November 21, 2017.
- "DOTr: Gov't to take over MRT3 maintenance". CNN Philippines. November 6, 2017. Retrieved November 21, 2017.
- https://www.facebook.com/dotrmrt3/photos/a.1877783779117100/2275585966003544/
- Rosario, Ben (October 14, 2014). "House committee to investigate MRT3 controversies". Manila Bulletin. Retrieved January 30, 2016.
- "Abaya, DOTC officials 'may have violated' anti-graft law over MRT-3". CNN Philippines. February 5, 2016. Retrieved February 5, 2016.
Transport officials led by Secretary Joseph Emilio "Jun" Abaya may have violated provisions of the Anti-Graft and Corrupt Practices Act in relation to the Metro Rail Transit Line 3 (MRT-3).
- De Guzman, Kristine. "DOTC chief shrugs off Senate report on MRT3". CNN Philippines. Retrieved February 5, 2016.
The report described what commuters put up with every day — the lack of coaches, poor maintenance of trains and platform facilities, and deteriorating rails..
- De Guzman, Kristine. "DOTC chief shrugs off Senate report on MRT3". CNN Philippines. Retrieved February 5, 2016.
Questionable deals and contracts also hound the line, which could bring transport officials to court for graft charges.
- Marisigan, Lorenz (July 27, 2017). "MRT 3 flawed from the start–Busan". BusinessMirror. Retrieved November 21, 2017.
- Rey, Aika (August 24, 2017). "DOTr to terminate MRT3 maintenance contract". Rappler. Retrieved November 21, 2017.
- Bacungan, VJ (November 29, 2017). "DOTr: New MRT-3 maintenance provider could start work by April 2018". CNN Philippines. Retrieved November 29, 2017.
- "LIVE: Ongoing signing ceremony for the Exchange of Notes for the Metro Rail Transit 3 (MRT-3) Rehabilitation Project between the Department of Foreign Affairs (DFA) and the Japan International Cooperation Agency (JICA)". facebook.com. November 6, 2018.
- Gonzales, Val [@dzrhnews] (December 27, 2018). "JUST IN: Kontrata sa pagitan ng @DOTrPH at Sumitomo Corporation para sa rehabilitasyon ng @dotrmrt3, pirmado na | via @dzrh5 Val Gonzales #DZRHNationwide" (Tweet) (in Filipino). Retrieved January 2, 2019 – via Twitter.
- Subingsubing, Krixia (December 29, 2018). "Sumitomo back on track with MRT 3". Inquirer.net. Retrieved January 2, 2019.
- https://www.railjournal.com/news/contract-manila-mrt-3-rehabilitation/
- Amojelar, Darwin (December 31, 2018). "Sumitomo asked to start MRT 3 rehabilitation in '19". Manila Standard. Retrieved January 2, 2019.
- Peralta, Janine (October 16, 2019). "All Dalian trains for MRT-3 line to be fully operational by July 2021 – MRT". CNN Philippines.
- JICAChannel02 (June 10, 2014). "(The Philippines) MEGA MANILA INFRASTRUCTURE ROADMAP (Long Ver.)". Retrieved April 20, 2016.
- "New MRT-3 train to be launched before April | GOVPH". Official Gazette of the Republic of the Philippines. February 23, 2016. Retrieved April 20, 2016.
- Dela Paz, Chrisee (February 23, 2016). "DOTC sees launch of new MRT3 train by April". Rappler. Retrieved April 20, 2016.
- De Guzman, Kristine (April 15, 2016). "New MRT trains to finally run on revenue hours". CNN Philippines. Retrieved April 20, 2016.
- De Guzman, Kristine (April 16, 2016). "New MRT3 train starts running next week". CNN Philippines. Archived from the original on September 25, 2018. Retrieved April 20, 2016.
- "Dalian to pay cost of adjustments of unused MRT3 trains —Tugade". GMA News Online. July 8, 2018. Retrieved September 25, 2018.
- Rey, Aika (August 30, 2018). "Chinese firm Dalian agrees to pay all costs to fix unused MRT3 trains". Rappler.
- "Platform doors installed in MRT station". ABS-CBN News. June 26, 2013. Retrieved September 20, 2020.
- Nicholls, AJ; Bacungan, VJ (November 15, 2017). "Gov't considers screen doors at MRT Ayala station after accident". CNN Philippines. Retrieved September 20, 2020.
- Torres, Ted P. (September 21, 2004). "LRT-MRT link is nat'l priority – NEDA". Philippine Daily Inquirer. Philippine Daily Inquirer, Inc. Archived from the original on September 25, 2004. Retrieved May 12, 2006.
- "After gov't takeover of NAIA Terminal 3, PGMA orders immediate completion of EDSA MRT3 extension" (Press release). Department of Transportation and Communications. January 4, 2005. Retrieved May 19, 2006.
- Amojelar, Darwin G. (December 28, 2010). "Govt creates team for MRT-3 due diligence, sets June takeover". The Manila Times. Manila Times Publishing Corporation. Retrieved January 15, 2011.
- Dagcutan, Aura Marie P. (December 28, 2010). "LRTA chief takes over MRT-3". BusinessWorld. BusinessWorld Publishing Corporation. Retrieved January 18, 2011.
- Camus, Miguel R. (May 27, 2014). "Vitangcol replaced as head of MRT-3". Inquirer.net. Retrieved May 27, 2014.
- Tan, Kimberly Jane (November 21, 2013). "NEDA approves MRT 7, LRT-1 extension projects". GMA News and Public Affairs. Retrieved January 1, 2014.
- Lectura, Lenie (September 23, 2013). "DOTC ready to refund SM's P200-M naming-rights fee for common station". BusinessMirror. Philippine Business Daily Mirror Publishing, Inc. Archived from the original on January 2, 2014. Retrieved January 1, 2014.
- Marasigan, Gelo; Remitio, Rex (September 28, 2016). "Finally: A common station for LRT, MRT lines". CNN Philippines. Retrieved April 10, 2018.
- Chanco, Boo (January 2, 2013). "P-Noy can't deliver MRT-3 upgrades". Philstar. Retrieved January 2, 2013.
- Flores, Mikhail Franz; dela Paz, Chrisee Jalyssa (August 2, 2014). "High court stops transfer of common train station site". BW. Retrieved August 2, 2014.
- Fe, Kaye (September 29, 2017). "Construction of P2.8-B Grand Unified Central Station to begin after almost a decade of delay". EBC. Retrieved September 29, 2017.
- Jiao, Claire (September 29, 2017). "LRT-MRT common station breaks ground". CNN Philippines. Retrieved April 10, 2018.
- Santos Jr., Reynaldo (August 13, 2014). "TIMELINE: MRT3 mishaps". Rappler. Retrieved September 17, 2019.
- Geronimo, Gian (November 3, 2012). "MRT train coach catches fire near Kamuning Station". GMA News Online. Retrieved September 6, 2019.
- Dimacali, TJ; Dinglasan, Rouchelle (March 19, 2013). "MRT operations suspended due to 'technical difficulties'". GMA News Online. Retrieved June 6, 2020.
- Fernandez, Amanda (March 26, 2014). "10 passengers hurt as MRT train makes sudden stop". GMA News Online. Retrieved June 4, 2020.
- Ronda, Rainier Allan (June 4, 2014). "Lightning stops MRT train on tracks". Philstar. Retrieved June 6, 2020.
- Pineda, Mj Lising (August 13, 2014). "MRT-3 Gets Derailed". Buhaykolehiyo. Archived from the original on October 25, 2014.
- Camus, Miguel R. (August 19, 2014). "DOTC: Human error blamed for MRT-3 train accident; 4 train workers face raps". Inquirer.net. Retrieved June 6, 2020.
- Echeminada, Perseus (October 23, 2017). "Diaper disrupts MRT-3 operations". Philstar. Retrieved September 6, 2019.
- Lagrimas, Nicole-Anne (November 16, 2017). "Up to 140 riders evacuated from 'detached train'". GMA News Online. Retrieved November 16, 2017.
- Ramos, Christia Marie (March 18, 2019). "MRT-3 unloads passengers after train emits smoke". Inquirer.net. Retrieved June 6, 2020.
- "Ilang pasahero ng MRT, nag-panic dahil sa nangyaring aberya kaninang umaga". GMA News Online. September 6, 2019. Retrieved September 12, 2019.
- Galvez, Daphne (November 4, 2019). "MRT-3 resumes normal ops from North to Taft stations after train emits smoke". Inquirer.net. Retrieved November 5, 2019.
- Marquez, Consuelo (February 5, 2020). "MRT-3 glitch: 700 passengers unloaded at Ayala Station". Inquirer.net. Retrieved June 4, 2020.