The Otis Bridge is a six-lane girder bridge crossing the Estero de Concordia, a tributary of the Pasig River, in Manila, the Philippines. Built in 1968 and carrying Paz Mendoza Guazon Street, formerly known as Otis Street, the bridge is a major artery for commercial vehicles carrying cargo from the Port of Manila,[2] with some 10,000 trucks crossing the bridge daily.[3]
Otis Bridge | |
---|---|
Coordinates | 14°35′12.4″N 120°59′41.7″E |
Carries | Vehicular traffic and pedestrians |
Crosses | Estero de Concordia |
Locale | Paco, Manila |
Characteristics | |
Design | Girder bridge |
Material | Concrete |
Total length | 80 meters (260 ft) |
Load limit | 20 metric tons (20 long tons; 22 short tons)[1] |
No. of lanes | 6 (3 lanes per direction) |
History | |
Constructed by | Department of Public Works and Highways |
Opened | 1968 (original bridge) 2018 (new bridge) |
Rebuilt | 2015 |
Location | |
In 2015, the bridge was slated for replacement or reconstruction as it neared the end of its 50-year service life,[3] with ₱37,000,000 initially being allocated for construction work by the Department of Public Works and Highways (DPWH).[4] However, on June 26, 2018, the bridge was ordered closed by the Metropolitan Manila Development Authority (MMDA) on the advice of the Manila Disaster Risk Reduction Management Council,[5] after media reports showed that 20-foot (6.1 m) long cracks started appearing along the center island, caused by the number of overloaded trucks that used the bridge,[6] as well as construction work on the nearby Concordia Bridge which prevented its timely replacement.[4]
The bridge was reopened on December 4, 2018, three months ahead of the March 2019 target date, with ₱217,000,000 being allocated from the national budget for its replacement.[1][3] Construction took place 24/7 in phases until the project was completed.[6][7]
References
- Orellana, Faye (December 4, 2018). "DPWH announces opening of Manila's new Otis Bridge". Philippine Daily Inquirer. Retrieved June 11, 2020.
- Pornelos, Vince (June 26, 2018). "Otis Bridge in Manila closed due to partial collapse". AutoIndustriya.com. Double B Web Solutions Company. Retrieved June 26, 2018.
- Rey, Aika (June 26, 2018). "Otis Bridge in Manila closed for repairs until March 2019". Rappler. Rappler, Inc. Retrieved June 26, 2018.
- Macairan, Evelyn (June 26, 2018). "Damaged Otis Bridge closed for reconstruction". The Philippine Star. PhilStar Daily, Inc. Retrieved June 26, 2018.
- Orellana, Faye (June 26, 2018). "Otis bridge in Manila closed to traffic". Philippine Daily Inquirer. Retrieved June 26, 2018.
- Zurbano, Joel E. (June 26, 2018). "MMDA to close Otis Bridge in Manila for rehab". Manila Standard. Philippine Manila Standard Publishing, Inc. Retrieved June 26, 2018.
- Manabat,Johnson (December 4, 2018). "Otis Bridge reopens in time for Christmas rush". ABS-CBN News. ABS-CBN News. Retrieved December 5, 2018.